國際核能現況 : Equipment installation milestones at Hualong One units
發表人 nicenter 於 2019/1/9 9:43:58 (14 人讀取)

Equipment installation milestones at Hualong One units


All the main equipment has now been installed at the first of two demonstration Hualong One units under construction at the Fuqing site in China's Fujian province. Installation of the steam generators has begun at the second unit.




Installation of the third coolant pump at Fuqing 5 (Image: CNNC)

Installation of the third and final main reactor coolant pump at Fuqing unit 5 was completed on 5 January, China National Nuclear Corporation (CNNC) announced today.


The company said the pumps have a "complex and special structure". The components for the pumps were shipped to the construction site for assembly. The main pump components for unit 5 arrived packed within more than 150 separate boxes. The unpacking of these boxes was subject to rigorous inspection, CNNC said.


The first main pump components were installed on 10 December. CNNC noted that all the main equipment of unit 5 at the plant is now in place within the nuclear island.


Meanwhile, the installation of the first of three steam generators has begun at unit 6 of the Fuqing plant.




The first steam generator is moved into the reactor building of Fuqing 6 (Image: CNNC)

The component - weighing about 365 tonnes - was designed by China Nuclear Power Institute and manufactured by Dongfang Electric Corporation. The steam generator was delivered to the construction site on 20 December and then moved into the reactor building on 23 December in preparation of installation.


Installation of the reactor pressure vessel at unit 6 was completed on 10 December.


In November 2014, CNNC announced that the fifth and sixth units at Fuqing will use the domestically-developed Hualong One pressurised water reactor design, marking its first deployment. The company had previously expected to use the ACP1000 design for those units, but plans were revised in line with a re-organisation of the Chinese nuclear industry. China's State Council gave final approval for construction of Fuqing units 5 and 6 in April 2015.


The pouring of first concrete for Fuqing 5 began in May that year, marking the official start of construction of the unit. Construction of unit 6 began in December the same year. The dome of unit 5 was installed on the containment building in May 2017 and the reactor pressure vessel was installed in January last year.


Fuqing 5 and 6 are scheduled to be completed in 2019 and 2020, respectively.


Construction of two Hualong One (HPR1000) units is also under way at China General Nuclear's Fangchenggang plant in the Guangxi Autonomous Region. Those units are also expected to start up in 2019 and 2020. Two HPR1000 units are under construction at Pakistan's Karachi nuclear power plant. Construction began on Karachi unit 2 in 2015 and unit 3 in 2016; the units are planned to enter commercial operation in 2021 and 2022. The HPR1000 has also been proposed for construction at Bradwell in the UK, where it is undergoing Generic Design Assessment.


Researched and written by World Nuclear News



source: http://www.world-nuclear-news.org/Articles/Equipment-installation-milestones-at-Hualong-One-u



其他新聞
2019/1/23 9:54:54 - Swedish repository expansion given regulatory approval
2019/1/23 9:42:54 - USA clears way for HALEU
2019/1/23 9:38:05 - Dismantling of Oskarshamn 2 internals completed
2019/1/23 9:36:15 - Ukraine highlights role of science in nuclear sector
2019/1/22 9:19:52 - 原能會於今(21)日完成核二廠除役許可申請之程序審查,開始進行實質審查作業
2019/1/21 9:40:58 - NRG receives funding for nuclear medicine R&D centre
2019/1/21 9:38:54 - Russia and Serbia to cooperate in nuclear power
2019/1/21 9:37:19 - The next steps for Horizon
2019/1/21 9:34:59 - US company demonstrates innovative waste disposal concept
2019/1/21 9:32:54 - 核三廠1號機預定於1月20日降載例行測試,原能會持續監控電廠運轉安全

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
原能會輻務小站臉書
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 北育成三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter[@]nicenter.org.tw