logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 相關資訊
* 瀏覽人數
今天: 95
昨天: 328
本月: 2285
總計: 556138
國際核能現況 : First criticality for Tianwan unit 4
發表人 nicenter 於 2018/10/3 9:50:00 (31 人讀取)

First criticality for Tianwan unit 4


Unit 4 of the Tianwan nuclear power plant in China's Jiangsu province moved closer to commissioning by achieving a sustained chain reaction for the first time. The Russian-supplied VVER-1000 is scheduled to begin generating electricity by the end of this year.




Unit 4 of the Tianwan plant (Image: CNNC)

Tianwan Phase I - units 1 and 2 - was constructed under a 1992 cooperation agreement between China and Russia. First concrete was poured in October 1999, and the units were commissioned in June 2007 and September 2007, respectively.


Tianwan Phase II - units 3 and 4 - are similar to the first stage of the Tianwan plant, comprising two AES-91 VVER-1000 units designed by Gidropress and supplied by Russian state nuclear corporation Rosatom. First concrete for unit 3 was poured in December 2012, while construction of the fourth unit began in September 2013. Unit 3 achieved first criticality on 29 September last year and was connected to the grid on 30 December. The unit entered commercial operation on 15 February having completed demonstration operation at nominal capacity for 100 hours.


The loading of a total of 163 fuel assemblies into the core of unit 4 was started on 25 August and completed on 2 September.


The reactor achieved first criticality at 2.27pm on 30 September, Rosatom and China National Nuclear Corporation (CNNC) have announced.


"Loading of fuel was completed ahead of schedule, and after obtaining all the required permits, unit 4 of the Tianwan nuclear power plant was brought to a minimum controlled level of power," said Alexey Bannik, ASE Group's director of projects in China. ASE Group is Rosatom's engineering subsidiary. "A controlled chain reaction started, the monitoring systems recorded the first neutrons. This will be followed by power start-up and connection of the unit to China's electricity grid."


Tianwan 4 is expected to enter commercial operation in March 2019.


Construction of Tianwan Phase III - units 5 and 6 - was originally scheduled to start in early 2011. However, following the March 2011 accident at Japan's Fukushima Daiichi plant, the Chinese government suspended the approval of new nuclear power projects, including those two units.


The latest Five-Year Plan called for construction of Phase III of the Tianwan plant to be accelerated. China's State Council gave its approval for Tianwan units 5 and 6 - both featuring 1080 MWe ACPR1000 reactors - on 16 December 2015. First safety-related concrete was poured for unit 5 on 27 December 2015, with that for unit 6 poured on 7 September 2016. CNNC plans to put both units 5 and 6 into commercial operation by the end of 2021.


On 8 June, Russia and China signed four agreements, including for the construction of two VVER-1200 reactors as units 7 and 8 of the Tianwan plant. In addition, two VVER-1200 units are to be constructed at the new Xudabao site in Liaoning province.


The Tianwan plant is owned and operated by Jiangsu Nuclear Power Corporation, a joint venture between CNNC (50%), China Power Investment Corporation (30%) and Jiangsu Guoxin Group (20%).


Researched and written by World Nuclear News



source: http://www.world-nuclear-news.org/Articles/First-criticality-for-Tianwan-unit-4



其他新聞
2018/12/7 10:41:45 - Nuclear important to sustainable energy mix, says UNECE report
2018/12/7 10:40:07 - First Taiwanese reactor to enter decommissioning
2018/12/7 10:31:03 - Russia completes testing of modified VVER-440 fuel
2018/12/7 10:30:00 - 核一廠1號機於107年12月6日進入除役期間,原能會將嚴格監督台電公司落實除役計畫及安全要求
2018/12/7 10:29:55 - Russia and Rwanda to cooperate in nuclear power
2018/12/7 10:20:00 - 核一廠1號機執照屆滿依法停機 待取得除役許可正式啟動除役
2018/12/7 10:19:17 - 回應新北市府指核一乾貯未按圖施工 台電:配合地形調整減少開挖 盼與市府再溝通
2018/12/5 9:56:19 - Argentina, Russia expand nuclear energy cooperation
2018/12/5 9:53:07 - Lawsuit launched as Bellefonte sale falters
2018/12/5 9:51:20 - CNNC launches R&D centre for fuels and materials
2018/12/5 9:48:24 - Nuclear must remain in South African mix, committee finds
2018/12/5 9:44:27 - UK's Bradwell site enters care and maintenance
2018/12/5 9:32:07 - 放射性物質或可發生游離輻射設備銷售服務業者名單
2018/12/3 10:51:18 - US companies collaborate on TRISO fuel facility
2018/12/3 10:49:38 - Amano calls for nuclear technology to go 'mainstream'
2018/12/3 10:48:11 - Russia starts cobalt-60 production at Kursk plant
2018/12/3 10:42:32 - Saskatchewan files suit over mine remediation costs
2018/12/3 9:25:36 - 原能會於今(2)日18時10分同意台電公司核二廠1號機併聯申請
2018/11/30 9:38:48 - New delay in start-up of Finnish EPR
2018/11/30 9:36:30 - Europe aims to be carbon neutral by 2050

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw