國際核能現況 : Tokai 2 cleared for restart
發表人 nicenter 於 2018/10/1 9:37:47 (50 人讀取)

Tokai 2 cleared for restart


Japan's Nuclear Regulation Authority (NRA) yesterday approved the restart of unit 2 of the Tokai nuclear power plant after concluding that safety measures submitted by Japan Atomic Power Company (JAPC) passed revised safety standards.




Tokai unit 2 (Image: JAPC)

JAPC applied to the NRA in May 2014 to restart the 1060 MWe boiling water reactor in Japan's Ibaraki prefecture. The unit automatically shut down and lost external power during the 11 March 2011 earthquake that led to the accident at the Fukushima Daiichi plant. One of Tokai 2's three emergency generators was damaged by a 5.4 meter tsunami, but the plant was still able to safely enter cold shutdown.


Under Japan's reactor restart process, plant operators are required to apply to the NRA for: permission to make changes to the reactor installation; approval of its construction plan to strengthen the plant; and final safety inspections to ensure the unit meets new safety requirements. Operators are required to add certain safety-enhancing equipment within five years of receiving the NRA's approval of a reactor engineering work programme.


At a meeting yesterday, the NRA officially announced the plant meets stricter safety standards introduced after the Fukushima Daiichi accident.


Having started commercial operation in 1978, Tokai 2 is one of the oldest of Japan's reactors to have applied for restart.


Under the revised regulations, reactors have a nominal lifespan of 40 years. However, extensions can be granted once only and limited to a maximum of 20 years, contingent on exacting safety requirements. So far, three pressurised water reactors have been approved for extended operation under the revised regulations. These are Takahama units 1 and 2 and Mihama 3, all owned and operated by Kansai Electric Power Company.


To extend the operating life of Tokai 2, JAPC must receive NRA approval by this November - the mandatory deadline - on two outstanding issues: detailed plans to implement safety countermeasures and extension of operations. The company applied to the NRA in November 2017 to extend the operation of the reactor by 20 years.


Construction work on such countermeasures - including a 1.7km-long sea wall to protect the plant from a potential tsunami as high as 17.1 meters - is scheduled to be completed in March 2021. The company expects investment of about JPY180 billion (USD1.6 billion) is needed to put additional safety measures in place at the plant.


After completing all construction work related to the extended operation of the unit, JAPC will also need the approval of local municipalities prior to the resumption of operation of Tokai 2.


JAPC said in a statement: "We will continue to seek approval for the [detailed] construction plan of the Tokai 2 power station and of an extension to the operating period. We will do our utmost to examine the situation and will steadily advance safety countermeasure construction."


Tokai 2 is the 15th power reactor approved to restart by the NRA and is the first plant damaged by the March 2011 tsunami to receive such approval. The unit is also the third boiling water reactor - the same type of reactor damaged at Fukushima Daiichi - to be approved for restart, following Tokyo Electric Power Company's Kashiwazaki-Kariwa units 6 and 7.


Researched and written by World Nuclear News



source: http://www.world-nuclear-news.org/Articles/Tokai-2-cleared-for-restart



其他新聞
2018/12/7 10:41:45 - Nuclear important to sustainable energy mix, says UNECE report
2018/12/7 10:40:07 - First Taiwanese reactor to enter decommissioning
2018/12/7 10:31:03 - Russia completes testing of modified VVER-440 fuel
2018/12/7 10:30:00 - 核一廠1號機於107年12月6日進入除役期間,原能會將嚴格監督台電公司落實除役計畫及安全要求
2018/12/7 10:29:55 - Russia and Rwanda to cooperate in nuclear power
2018/12/7 10:20:00 - 核一廠1號機執照屆滿依法停機 待取得除役許可正式啟動除役
2018/12/7 10:19:17 - 回應新北市府指核一乾貯未按圖施工 台電:配合地形調整減少開挖 盼與市府再溝通
2018/12/5 9:56:19 - Argentina, Russia expand nuclear energy cooperation
2018/12/5 9:53:07 - Lawsuit launched as Bellefonte sale falters
2018/12/5 9:51:20 - CNNC launches R&D centre for fuels and materials
2018/12/5 9:48:24 - Nuclear must remain in South African mix, committee finds
2018/12/5 9:44:27 - UK's Bradwell site enters care and maintenance
2018/12/5 9:32:07 - 放射性物質或可發生游離輻射設備銷售服務業者名單
2018/12/3 10:51:18 - US companies collaborate on TRISO fuel facility
2018/12/3 10:49:38 - Amano calls for nuclear technology to go 'mainstream'
2018/12/3 10:48:11 - Russia starts cobalt-60 production at Kursk plant
2018/12/3 10:42:32 - Saskatchewan files suit over mine remediation costs
2018/12/3 9:25:36 - 原能會於今(2)日18時10分同意台電公司核二廠1號機併聯申請
2018/11/30 9:38:48 - New delay in start-up of Finnish EPR
2018/11/30 9:36:30 - Europe aims to be carbon neutral by 2050

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw