Outages extended at Belgian plants


Scheduled outages at Belgium's Tihange 2 and 3 have been further extended while concrete degradation issues in adjacent non-nuclear buildings are addressed, operator Electrabel has announced.




Tihange (Image: Electrabel)

Engie subsidiary Electrabel said on 21 September that Tihange 2 is now expected to restart on 1 June 2019, and not on 31 October 2018 as previously planned. Tihange 3 is now expected to restart on 2 March 2019 instead of 30 September. There has been no change to the expected restart of date 15 December 2018 for Doel 4, where similar issues are being addressed.


The revisions to the outage calendar will result in a shortfall of around EUR250 million (USD295 million) in the Group's 2018 EBITDA, Electrabel said. Based on these dates, the availability factor for Belgium's nuclear plants - four units at Doel and three at Tihange - is expected to be 52% for 2018, and 74% for 2019.


Electrabel in 2017 noted a deterioration in the concrete in the ceilings of buildings housing the outlet nozzles for the steam exhaust valves in the building attached to the reactor building at Doel unit 3. These buildings, which are located in the non-nuclear zone of Belgian plants, offer an additional safety facility but are subject to intense steam pressure, which degrades concrete over time, the company said.


Work on Tihange 3 and analysis at Tihange 2 and Doel 4 show that the deterioration varies from one building to another, Electrabel said. "The teams are currently working on diagnosing the problem and on calculations that should enable the submission of action plans to the authorities," it added.


"Electrabel emphasises that these dates are best estimates in light of the information currently available and may be altered depending on the optimisation of scheduling, the results of future inspections, the progress of the works and injunctions issued by the authorities," it said.


Researched and written by World Nuclear News



source: http://www.world-nuclear-news.org/Articles/Outages-extended-at-Belgian-plants



其他新聞
2018/10/15 11:28:40 - USA announces China export policy
2018/10/12 9:38:39 - 總統出席「中華民國中樞暨各界慶祝107年國慶大會」,發表演說強調非核家園也不能走回頭路,原能會配合政府政策就核安管制機關立場說明
2018/10/12 9:34:50 - 核三廠2號機預定於10月14日降載例行測試,原能會持續監控電廠運轉安全
2018/10/8 9:29:55 - IAEA assesses operational safety of Torness plant
2018/10/5 9:16:24 - IAEA assesses operational safety of Torness plant
2018/10/3 9:51:44 - HTR-PM steam generator passes pressure tests
2018/10/3 9:50:00 - First criticality for Tianwan unit 4
2018/10/3 9:48:18 - Rostov unit 4 enters commercial operation
2018/10/3 9:46:54 - USA awards HEU downblending contract
2018/10/3 9:42:38 - WANO invites early engagement on new nuclear build
2018/10/1 9:39:11 - IAEA-led project looks at climate change mitigation
2018/10/1 9:37:47 - Tokai 2 cleared for restart
2018/10/1 9:36:21 - Injunction lifted on operation of Japanese reactor
2018/10/1 9:34:33 - NuScale SMR enters first manufacturing phase
2018/10/1 9:33:21 - Swedish regulator calls for national strategy
2018/9/28 9:36:07 - Vogtle progress rests on Oglethorpe vote
2018/9/28 9:34:21 - Senegal aims to build nuclear technology centre
2018/9/28 9:32:31 - Draft law supports Chinese nuclear exports
2018/9/28 9:30:57 - Outages extended at Belgian plants
2018/9/28 9:29:09 - NuScale SMR enters first manufacturing phase

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw