國際核能現況 : Waste package in place ahead of MSSS clearance
發表人 nicenter 於 2018/8/15 9:22:04 (93 人讀取)

Waste package in place ahead of MSSS clearance


The first shielded waste transfer package has been installed onto one of three machines at the Magnox Swarf Storage Silo (MSSS) at the Sellafield site in the UK. The machines will begin removing magnesium swarf waste from the building's 22 silo compartments from next year.




The first waste transfer package is put in place at the MSSS (Image: Sellafield Ltd)

The Magnox Swarf Storage Silo project was built in Cumbria, England in the 1960s to store waste from the UK's earliest nuclear reactors. These 16-metre deep silos were constructed to accommodate the magnesium swarf waste produced by the decanning of Magnox fuel prior to reprocessing. The swarf was stored underwater, and the first facility of six silos began operations in 1964. By 1983 a total of 22 silos had been built, but by the early 1990s wet storage of Magnox swarf was superseded by dry storage.


The MSSS closed in 2000 and has been prioritised for clean-up by the Nuclear Decommissioning Authority (NDA). Decommissioning of the MSSS is under way, but all the waste stored in the silos, including the water in which the swarf is submerged, must be removed before the building can be demolished. A robot was deployed in the MSSS silos last October to help dislodge and clear waste. The solid waste will be removed from the silos, processed and encapsulated for long-term storage.


Sellafield Ltd announced on 10 August that the first 50-tonne waste package has been safely placed onto one of the three machines that will be used to remove the swarf from the silos.


"Preparations for removing the 11,000 cubic metres of historic waste from the silos and placing them into safe, modern storage have been over twenty years in the making," the company said. "Next year three 360-tonne Silo Emptying Plant (SEP) machines will start reaching in to the silos and removing the waste with a hydraulic grab."


This waste will then be loaded into the transfer packages and transferred to the Magnox Encapsulation Plant, which has been built to receive dry Magnox swarf, encapsulate it in cement and seal it in stainless steel drums. These will then be stored on the Sellafield site until a permanent geological disposal facility is constructed.


Head of Programme for MSSS, Chris Halliwell, said: "The transfer package is the essential link in the chain to safer storage. It's a big moment to see it finally being attached to the SEP machine inside the silo. Never before have these two bits of machinery met inside the place where they'll be carrying out our biggest job in hazard reduction."


The first transfer package to enter MSSS was manufactured by Workington firm TSP Engineering and is one of nine original packages they have built and modified for Sellafield Ltd. TSP is currently competing with Cavendish Nuclear to build the next batch of 15 transfer packages.


Researched and written by World Nuclear News



source: http://www.world-nuclear-news.org/Articles/Transfer-package-in-place-ahead-of-MSSS-waste-clea



其他新聞
2019/2/20 10:18:29 - Public hearing for Whiteshell licence renewal
2019/2/20 10:16:05 - Russia's Kola plant completes second WANO review
2019/2/20 10:09:05 - 回應環團抗議興達電廠更新計畫 台電:減開發增綠地 救空氣護溼地立場一致
2019/2/20 10:07:34 - 核二未來面臨燃料池滿 新北稱「目前尚有空間」 台電:避重就輕、張飛打岳飛
2019/2/18 10:18:09 - NRC seeks input on legacy uranium cleanup
2019/2/18 10:14:08 - BP forecasts nuclear growth to 3400 TWh by 2040
2019/2/18 10:11:32 - Melted fuel photographed at Fukushima
2019/2/18 10:09:53 - Search for UK repository site resumes
2019/2/15 13:56:22 - NRC terminates US MOX plant authorisation
2019/2/15 13:54:09 - Foratom highlights role of nuclear in meeting EU's target

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
原能會輻務小站臉書
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 北育成三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter[@]nicenter.org.tw