logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 相關資訊
* 瀏覽人數
今天: 13455
昨天: 19414
本月: 427638
總計: 1219847
國際核能現況 : Turbine equipment installed at Leningrad II-2
發表人 nicenter 於 2018/8/8 11:08:17 (102 人讀取)

Turbine equipment installed at Leningrad II-2


Installation of the main equipment for the turbine of unit 2 of the Leningrad Phase II nuclear power plant in northwest Russia has been completed and according to schedule, state nuclear corporation Rosatom said yesterday.




The turbine of Leningrad II-2 (Image: Rosatom)

The stator, separators, superheaters, deaerator, turbine condensers, high- and low-pressure heaters and heat exchangers have all been installed, it said. The shaft of the turbine has been aligned and three bridge cranes have been successfully operated, it added. The turbine building consists of four platforms, a total area of ​​ almost 25,000 square meters, more than 5000 tonnes of pipes and nearly 4000 valves.


Work will now start on insulation, low-current and electrical installation works as well as the laying of external and internal engineering networks, it said. In total, 71 technological systems will be housed in the turbine building of the unit.


Alexander Chebotarev, head of construction at the plant, said that personnel are working with established cooperation and successful experience of similar operations with unit 1, which is now at the final stage of commissioning.


“This enables us not only to keep to schedule, but in some areas even to shorten the time required," he said.

The existing Leningrad plant site has four operating RBMK-1000 units, while Leningrad-II will have four VVER-1200 units.


Leningrad II-1 is the second VVER-1200 reactor, following the launch in 2016 of Novovoronezh 6. Start-up operations of the new Leningrad unit began on 8 December last year, when the first fuel assemblies were loaded into the reactor core. The reactor was brought to the minimum controllable power level on 6 February and connected to the grid on 9 March. It entered the final stage of its commissioning on 26 March.


Researched and written by World Nuclear News



source: http://www.world-nuclear-news.org/Articles/Turbine-equipment-installed-at-Leningrad-II-2



其他新聞
2019/2/20 10:18:29 - Public hearing for Whiteshell licence renewal
2019/2/20 10:16:05 - Russia's Kola plant completes second WANO review
2019/2/20 10:09:05 - 回應環團抗議興達電廠更新計畫 台電:減開發增綠地 救空氣護溼地立場一致
2019/2/20 10:07:34 - 核二未來面臨燃料池滿 新北稱「目前尚有空間」 台電:避重就輕、張飛打岳飛
2019/2/18 10:18:09 - NRC seeks input on legacy uranium cleanup
2019/2/18 10:14:08 - BP forecasts nuclear growth to 3400 TWh by 2040
2019/2/18 10:11:32 - Melted fuel photographed at Fukushima
2019/2/18 10:09:53 - Search for UK repository site resumes
2019/2/15 13:56:22 - NRC terminates US MOX plant authorisation
2019/2/15 13:54:09 - Foratom highlights role of nuclear in meeting EU's target

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
原能會輻務小站臉書
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 北育成三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter[@]nicenter.org.tw