Cold functional tests start at Novovoronezh II-2


Russia's Rosatom has announced the start of cold functional tests at unit 2 of the Novovoronezh II nuclear power plant. Cold and hot tests will take about 100 days, with the cold tests accounting for 35 days, the state nuclear corporation said yesterday.




Unit 2 of Novovoronezh II under construction (Image: Rosatom)

Also known as Novovoronezh 7, the unit is a VVER 1200/392M pressurised water reactor (PWR) unit with a design net capacity of 1114 MWe. It is the second of two such units at Novovoronezh II - the lead project for the deployment of the AES-2006 design incorporating a Gidropress-designed PWR, an evolutionary development from the VVER-1000. Unit 1 was connected to the grid in August 2016.


Cold and hot tests on the unit’s equipment are the most important stage of commissioning work, Rosatom said. They confirm the unit is fit for safe and reliable operation and form the last major technological operation before its physical launch, it added.


"We have already carried out hydraulic tests on the first and second circuits at a pressure of 3.2 MPa and 2.0 MPa, thus confirming their integrity," Vladimir Povarov, director of the Novovoronezh nuclear power plant, said. “Now we will include the main circulation pumps, performing the necessary tests for density and strength. We need to confirm that all the mechanisms are working as they should and then we’ll go on to the stages that are associated with obtaining a licence from [regulator] Rostekhnadzor to load nuclear fuel into the reactor,” he added.


Hot tests will confirm the operability of the main and auxiliary equipment and systems of the reactor installation under operating conditions. Commissioning and operation specialists will run the four main circulation pumps for 100 hours at a given pressure of 16.0 MPa and a coolant temperature of 280 degrees Celsius.


Researched and written by World Nuclear News



source: http://www.world-nuclear-news.org/Articles/Cold-functional-tests-start-at-Novovoronezh-II-2



其他新聞
2018/8/15 9:37:51 - Chinese AP1000 reaches full power operation
2018/8/15 9:35:29 - Public to comment on Hanford tunnel work
2018/8/15 9:30:49 - Chinese research reactor sets operational record
2018/8/15 9:26:52 - ENEC launches youth council
2018/8/15 9:22:04 - Waste package in place ahead of MSSS clearance
2018/8/13 9:42:09 - NNL, Wood contracted for nuclear fuel research
2018/8/13 9:36:48 - Safety review sought for new Japanese reactor
2018/8/13 9:34:22 - US agencies working on critical plant list
2018/8/13 9:28:20 - 全國首創「雙綠能電廠」 台電首座水上光電站大甲溪啟用
2018/8/10 9:51:46 - Call for UK government to back small nuclear projects
2018/8/10 9:37:07 - Fuqing 5 enters system commissioning phase
2018/8/10 9:34:28 - Progress at Vogtle, but cost forecast rises
2018/8/10 9:30:45 - Pickering relicensed to 2028
2018/8/10 9:20:00 - 台灣電力不足?台電重申無缺電問題 能源轉型兼顧穩供與環保
2018/8/8 11:15:18 - UK SMRs ‘Should Get Same Subsidies As Offshore Wind’, Says Independent Review
2018/8/8 11:12:54 - We Cannot Rely On Variable Renewables Without Nuclear, Says New Research
2018/8/8 11:08:17 - Turbine equipment installed at Leningrad II-2
2018/8/8 11:06:37 - French, British regions unite for nuclear growth
2018/8/6 10:44:50 - CEZ to test use of Westinghouse fuel at Temelin-1
2018/8/6 10:38:29 - First nuclear plant visit for Perry

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw