國際核能現況 : Approval for decommissioning of Swiss reactor
發表人 nicenter 於 2018/6/25 12:00:00 (139 人讀取)

Approval for decommissioning of Swiss reactor



Swiss utility BKW has been issued with a decommissioning order for the Mühleberg nuclear power plant, which is scheduled

to permanently shut down at the end of 2019. The order from the country's Department of the Environment, Transport, Energy and

Communication (DETEC) states the decommissioning work must be carried out in accordance with a plan submitted by BKW in 2015.



Sanmen 1-2 - 460 (Westinghouse)

The Mühleberg plant, due to shut next year (Image: ENSI)

BKW announced in late 2013 that Mühleberg will be permanently shut down in 2019 instead of the earlier planned 2022 because of

"uncertainty surrounding political and regulatory trends". The single 372 MWe boiling water reactor began operating in 1972.

It will be the first Swiss nuclear power plant to be decommissioned.


In December 2015, BKW submitted an application to DETEC for permission to decommission the plant, together with a plan for the

decommissioning works.


BKW informed the Federal Nuclear Safety Inspectorate (ENSI) in February 2016 that the Mühleberg plant will be disconnected from

the grid on 20 December 2019. However, it noted this shutdown date assumes that "the legal framework necessary to begin immediate

dismantling is implemented". One of the prerequisites is obtaining the necessary decommissioning permit from ENSI.


DETEC has now approved BKW's application to decommission Mühleberg. The order says the decommissioning works must be carried out in

accordance with the decommissioning plan submitted by BKW in 2015. In addition, various requirements will have to be met,

in particular the technical, organisational and procedural conditions laid down by ENSI in its report of August 2017.


DETEC also requires BKW to submit a plan to the Swiss Federal Office of Energy for the dismantling of the conventional parts of

the plant by the end of 2027.



BKW said receipt of the order "represents another milestone and paves the way for the first decommissioning of a power reactor

in Switzerland".


"We are happy to have received the decommissioning order in mid-2018," said BKW CEO Suzanne Thoma. "This way, we are procedurally on track,

as well as financially and in terms of planning."


Planning for the decommissioning and dismantling of Mühleberg is already at an advanced stage, according to BKW. The company submitted

detailed outlines to ENSI at the end of 2017 for the period immediately after the end of operations in December 2019, as well as

the first stage of decommissioning. "In doing so, BKW laid the groundwork for dismantling to begin immediately after the Mühleberg

nuclear power plant has been taken off the grid," BKW said.


BKW said it will cover the entire costs of decommissioning and dismantling Mühleberg. It said it has made the necessary provisions and

pays money into the country's Decommissioning and Waste Disposal Funds, which are monitored by the federal government.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/WR-Approval-for-decommissioning-of-Swiss-reactor-2206185.html



其他新聞
2019/2/20 10:18:29 - Public hearing for Whiteshell licence renewal
2019/2/20 10:16:05 - Russia's Kola plant completes second WANO review
2019/2/20 10:09:05 - 回應環團抗議興達電廠更新計畫 台電:減開發增綠地 救空氣護溼地立場一致
2019/2/20 10:07:34 - 核二未來面臨燃料池滿 新北稱「目前尚有空間」 台電:避重就輕、張飛打岳飛
2019/2/18 10:18:09 - NRC seeks input on legacy uranium cleanup
2019/2/18 10:14:08 - BP forecasts nuclear growth to 3400 TWh by 2040
2019/2/18 10:11:32 - Melted fuel photographed at Fukushima
2019/2/18 10:09:53 - Search for UK repository site resumes
2019/2/15 13:56:22 - NRC terminates US MOX plant authorisation
2019/2/15 13:54:09 - Foratom highlights role of nuclear in meeting EU's target

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
原能會輻務小站臉書
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 北育成三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter[@]nicenter.org.tw