國際核能現況 : Chinese AP1000s pass commissioning milestones
發表人 nicenter 於 2018/6/25 11:50:00 (18 人讀取)

Chinese AP1000s pass commissioning milestones


The start of power generation by two AP1000 reactors under construction in China moved a step closer

yesterday with first criticality being achieved at Sanmen 1 and the loading of fuel beginning at Haiyang 1.

Both units are expected to start up by the end of this year, becoming the first operating AP1000 reactors.



Sanmen 1-2 - 460 (Westinghouse)

Sanmen units 1 and 2 (Image: Westinghouse)

Unit 1 of the Sanmen nuclear power plant in China's Zhejiang province attained first criticality

- a sustained chain reaction - at 2.09am yesterday, State Nuclear Power Technology Corporation announced.


Westinghouse President and CEO José Gutiérrez said, "Today we completed the final major milestone before

commercial operation for Westinghouse's AP1000 nuclear power plant technology. We are one step closer to

delivering the world's first AP1000 plant to our customer and the world - with our customers, we will provide

our customers in China with safe, reliable and clean energy from Sanmen 1."


The next stage in the commissioning of Sanmen 1 will be synchronisation to the electricity grid. This will be

followed by gradual power ascension testing until all testing is safely and successfully completed at 100% power.


Westinghouse said, "Once plant operations begin at Sanmen 1, it will be the first AP1000 nuclear power plant in

operation, offering innovative passive safety system technology, multiple layers of defence and advanced controls

for unequalled reliability and safety."


In September 2007, Westinghouse and its partner the Shaw Group received authorisation to construct four AP1000 units

in China: two at Sanmen and two more at Haiyang in Shandong province. Construction of Sanmen 1 began in April 2009,

while first concrete for Sanmen 2 was poured in December 2009. Construction of Haiyang 1 and 2 began in September 2009

and June 2010, respectively.


Hot testing of Sanmen 1 was completed in June 2017. The loading of fuel assemblies into its core began on 25 April

following the issuance of a permit by the country's nuclear regulator, the National Nuclear Safety Administration (NNSA).


Hot tests at Sanmen 2 were completed in January. That unit is also expected to begin operating by the end of this year.



Haiyang 1 fuel loading



Westinghouse also announced that loading of the 157 fuel assemblies into the core of Haiyang 1 began at 7.36pm yesterday.



Haiyang 1 - 460 (Westinghouse)

Haiyang unit 1 (Image: Westinghouse)

The company said the unit recently successfully completed the necessary testing and regulatory reviews conducted by the NNSA.

"Haiyang unit 1 met all the criteria, confirming the capability of Westinghouse's AP1000 technology," it said.


Haiyang 1 expected to begin operating by the end of this year, with Haiyang 2 expected to start up in 2019.


"The lessons learned and resources shared between Sanmen and Haiyang throughout all phases of construction and start-up have

made tremendous improvements in terms of quality and execution, which will benefit future AP1000 fleets," said Gavin Liu,

Westinghouse's president for the Asia Region. "We will continue to work side by side with our Chinese customers and ensure

the success of the remaining testing."


Four AP1000 reactors were also being built in the USA - two each at Vogtle and Summer. However, construction of the two Summer

units was suspended last August.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Chinese-AP1000s-pass-commissioning-milestones-2206184.html



其他新聞
2018/7/16 10:00:56 - WANO completes reviews of Leningrad and Tianwan plants
2018/7/16 9:57:23 - Yangjiang 5 enters commercial operation
2018/7/16 9:46:00 - ‘Breakthrough’ For Bulgaria As €31M Plasma Melting Plant Begins Operations At Kozloduy Nuclear Station
2018/7/16 9:43:19 - European Court Dismisses Austria’s Objections To Hinkley Point C
2018/7/13 10:22:08 - Austrian case against Hinkley Point C aid rejected
2018/7/13 10:19:37 - UK's post-Brexit nuclear plans face scrutiny
2018/7/13 10:13:34 - 輻射監測生力軍!石門水庫、清華大學環境輻射監測站正式上線
2018/7/13 10:06:30 - 核三廠1號機預定於7月15日降載例行測試,原能會持續監控電廠運轉安全
2018/7/9 10:51:40 - Think-tanks call for states to adopt Clean Energy Standards
2018/7/9 10:49:29 - EDF maintains plant safety is a priority
2018/7/9 10:47:06 - NEI issues guidelines for regulatory interactions
2018/7/6 12:09:34 - 核二廠2號機於今(6)日降載進行例行測試,原能會持續監控電廠運轉安全(更新)
2018/7/6 12:08:15 - 核二廠2號機預定於7月7日降載例行測試,原能會持續監控電廠運轉安全
2018/7/4 10:08:53 - Boss launches Honeymoon restart strategy
2018/7/4 10:04:16 - NDA to take over management of Magnox sites
2018/7/4 9:58:23 - Japanese Cabinet approves new basic energy plan
2018/7/4 9:50:06 - 今(04)日04時10分台東縣政府北方規模4.6有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/7/4 9:42:18 - 核二廠1號機反應器圍阻體廠房氣體流程輻射監測器發出警戒訊號之說明
2018/7/2 10:44:58 - China's Taishan 1 reactor connected to grid
2018/7/2 10:40:05 - Bruce Power and ITM to supply cancer therapy isotope

 線上期刊目錄

 瀏覽人數
今天: 142
昨天: 122
本月: 2466
總計: 530693

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw