Chinese AP1000s pass commissioning milestones


The start of power generation by two AP1000 reactors under construction in China moved a step closer

yesterday with first criticality being achieved at Sanmen 1 and the loading of fuel beginning at Haiyang 1.

Both units are expected to start up by the end of this year, becoming the first operating AP1000 reactors.



Sanmen 1-2 - 460 (Westinghouse)

Sanmen units 1 and 2 (Image: Westinghouse)

Unit 1 of the Sanmen nuclear power plant in China's Zhejiang province attained first criticality

- a sustained chain reaction - at 2.09am yesterday, State Nuclear Power Technology Corporation announced.


Westinghouse President and CEO José Gutiérrez said, "Today we completed the final major milestone before

commercial operation for Westinghouse's AP1000 nuclear power plant technology. We are one step closer to

delivering the world's first AP1000 plant to our customer and the world - with our customers, we will provide

our customers in China with safe, reliable and clean energy from Sanmen 1."


The next stage in the commissioning of Sanmen 1 will be synchronisation to the electricity grid. This will be

followed by gradual power ascension testing until all testing is safely and successfully completed at 100% power.


Westinghouse said, "Once plant operations begin at Sanmen 1, it will be the first AP1000 nuclear power plant in

operation, offering innovative passive safety system technology, multiple layers of defence and advanced controls

for unequalled reliability and safety."


In September 2007, Westinghouse and its partner the Shaw Group received authorisation to construct four AP1000 units

in China: two at Sanmen and two more at Haiyang in Shandong province. Construction of Sanmen 1 began in April 2009,

while first concrete for Sanmen 2 was poured in December 2009. Construction of Haiyang 1 and 2 began in September 2009

and June 2010, respectively.


Hot testing of Sanmen 1 was completed in June 2017. The loading of fuel assemblies into its core began on 25 April

following the issuance of a permit by the country's nuclear regulator, the National Nuclear Safety Administration (NNSA).


Hot tests at Sanmen 2 were completed in January. That unit is also expected to begin operating by the end of this year.



Haiyang 1 fuel loading



Westinghouse also announced that loading of the 157 fuel assemblies into the core of Haiyang 1 began at 7.36pm yesterday.



Haiyang 1 - 460 (Westinghouse)

Haiyang unit 1 (Image: Westinghouse)

The company said the unit recently successfully completed the necessary testing and regulatory reviews conducted by the NNSA.

"Haiyang unit 1 met all the criteria, confirming the capability of Westinghouse's AP1000 technology," it said.


Haiyang 1 expected to begin operating by the end of this year, with Haiyang 2 expected to start up in 2019.


"The lessons learned and resources shared between Sanmen and Haiyang throughout all phases of construction and start-up have

made tremendous improvements in terms of quality and execution, which will benefit future AP1000 fleets," said Gavin Liu,

Westinghouse's president for the Asia Region. "We will continue to work side by side with our Chinese customers and ensure

the success of the remaining testing."


Four AP1000 reactors were also being built in the USA - two each at Vogtle and Summer. However, construction of the two Summer

units was suspended last August.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Chinese-AP1000s-pass-commissioning-milestones-2206184.html



其他新聞
2018/11/19 9:34:29 - PRISM selected for US test reactor programme
2018/11/19 9:27:09 - UK HPR1000 moves to next design assessment stage
2018/11/19 9:25:07 - Orano prepares Fugen ATR fuel for reprocessing
2018/11/14 9:20:55 - 行政院107年11月8日通過核研所改行政院法人「原子能科技研究院」
2018/11/14 9:14:47 - 原能會於今(13)日接獲台電公司核二廠1號機第26次大修後再起動臨界申請
2018/11/9 9:44:29 - Toshiba decides to scrap Moorside project
2018/11/7 9:30:04 - Hurricane-hit Puerto Rico to consider nuclear power
2018/11/7 9:28:12 - Saudi Arabia lays research reactor foundation stone
2018/11/7 9:25:41 - First reactor on Russia's floating plant starts up
2018/11/7 9:21:42 - Cameco notes market improvements
2018/11/5 9:36:36 - UK, Canada sign Nuclear Cooperation Agreement
2018/11/5 9:34:12 - Idaho proposed for HALEU fuel fabrication
2018/11/5 9:32:35 - IAEA reviews long-term safety of Argentinean plant
2018/11/5 9:30:50 - Decommissioning milestone for space fuel plant
2018/11/5 9:26:17 - 除役首部曲 核一乾貯核定計畫遭新北市府認定失效 台電今再提訴願
2018/11/2 9:51:26 - Climate goal demands huge boost in Chinese nuclear
2018/11/2 9:48:15 - 核三廠預定於107年11月02~03日 期間執行11.4kV定期維護檢查,部分饋線將受影響停電,原能會持續監控電廠輻射安全
2018/11/2 9:44:35 - 核三廠2號機預定於11月4日降載例行測試,原能會持續監控電廠運轉安全
2018/11/2 9:39:26 - 今(31)日中央氣象局發布豪雨特報,原能會要求台電公司強化各核能電廠及放射性物料設施防汛作業
2018/11/2 9:32:57 - 因應中火工安意外 台電:痛定思痛 全面進行工安總體檢

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw