國際核能現況 : Chinese AP1000s pass commissioning milestones
發表人 nicenter 於 2018/6/25 11:50:00 (108 人讀取)

Chinese AP1000s pass commissioning milestones


The start of power generation by two AP1000 reactors under construction in China moved a step closer

yesterday with first criticality being achieved at Sanmen 1 and the loading of fuel beginning at Haiyang 1.

Both units are expected to start up by the end of this year, becoming the first operating AP1000 reactors.



Sanmen 1-2 - 460 (Westinghouse)

Sanmen units 1 and 2 (Image: Westinghouse)

Unit 1 of the Sanmen nuclear power plant in China's Zhejiang province attained first criticality

- a sustained chain reaction - at 2.09am yesterday, State Nuclear Power Technology Corporation announced.


Westinghouse President and CEO José Gutiérrez said, "Today we completed the final major milestone before

commercial operation for Westinghouse's AP1000 nuclear power plant technology. We are one step closer to

delivering the world's first AP1000 plant to our customer and the world - with our customers, we will provide

our customers in China with safe, reliable and clean energy from Sanmen 1."


The next stage in the commissioning of Sanmen 1 will be synchronisation to the electricity grid. This will be

followed by gradual power ascension testing until all testing is safely and successfully completed at 100% power.


Westinghouse said, "Once plant operations begin at Sanmen 1, it will be the first AP1000 nuclear power plant in

operation, offering innovative passive safety system technology, multiple layers of defence and advanced controls

for unequalled reliability and safety."


In September 2007, Westinghouse and its partner the Shaw Group received authorisation to construct four AP1000 units

in China: two at Sanmen and two more at Haiyang in Shandong province. Construction of Sanmen 1 began in April 2009,

while first concrete for Sanmen 2 was poured in December 2009. Construction of Haiyang 1 and 2 began in September 2009

and June 2010, respectively.


Hot testing of Sanmen 1 was completed in June 2017. The loading of fuel assemblies into its core began on 25 April

following the issuance of a permit by the country's nuclear regulator, the National Nuclear Safety Administration (NNSA).


Hot tests at Sanmen 2 were completed in January. That unit is also expected to begin operating by the end of this year.



Haiyang 1 fuel loading



Westinghouse also announced that loading of the 157 fuel assemblies into the core of Haiyang 1 began at 7.36pm yesterday.



Haiyang 1 - 460 (Westinghouse)

Haiyang unit 1 (Image: Westinghouse)

The company said the unit recently successfully completed the necessary testing and regulatory reviews conducted by the NNSA.

"Haiyang unit 1 met all the criteria, confirming the capability of Westinghouse's AP1000 technology," it said.


Haiyang 1 expected to begin operating by the end of this year, with Haiyang 2 expected to start up in 2019.


"The lessons learned and resources shared between Sanmen and Haiyang throughout all phases of construction and start-up have

made tremendous improvements in terms of quality and execution, which will benefit future AP1000 fleets," said Gavin Liu,

Westinghouse's president for the Asia Region. "We will continue to work side by side with our Chinese customers and ensure

the success of the remaining testing."


Four AP1000 reactors were also being built in the USA - two each at Vogtle and Summer. However, construction of the two Summer

units was suspended last August.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Chinese-AP1000s-pass-commissioning-milestones-2206184.html



其他新聞
2019/2/20 10:18:29 - Public hearing for Whiteshell licence renewal
2019/2/20 10:16:05 - Russia's Kola plant completes second WANO review
2019/2/20 10:09:05 - 回應環團抗議興達電廠更新計畫 台電:減開發增綠地 救空氣護溼地立場一致
2019/2/20 10:07:34 - 核二未來面臨燃料池滿 新北稱「目前尚有空間」 台電:避重就輕、張飛打岳飛
2019/2/18 10:18:09 - NRC seeks input on legacy uranium cleanup
2019/2/18 10:14:08 - BP forecasts nuclear growth to 3400 TWh by 2040
2019/2/18 10:11:32 - Melted fuel photographed at Fukushima
2019/2/18 10:09:53 - Search for UK repository site resumes
2019/2/15 13:56:22 - NRC terminates US MOX plant authorisation
2019/2/15 13:54:09 - Foratom highlights role of nuclear in meeting EU's target

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
原能會輻務小站臉書
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 北育成三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter[@]nicenter.org.tw