國際核能現況 : Start-up of Finnish EPR put back four months
發表人 nicenter 於 2018/6/15 15:11:29 (62 人讀取)

Regular electricity generation at the Olkiluoto 3 EPR in Finland is now expected to begin in September 2019 as commissioning tests will take longer than planned, Finnish utility Teollisuuden Voima Oyj (TVO) announced yesterday. According to the previous schedule provided by plant supplier the Areva-Siemens consortium, production was planned to start next May.






The Olkiluoto EPR, pictured in August 2016 (Image: TVO)

In April, TVO said it was waiting for "an overall rebaseline schedule" from the Areva-Siemens consortium "due to some delays in the hot functional testing phase".


Hot functional testing of the Olkiluoto 3 (OL3) EPR began in December and was completed in late May. These key pre-operational tests ensure coolant circuits and nuclear safety systems are functioning properly before fuel is loaded. They are the first tests at plant-level where the 1600 MWe pressurised water reactor and turbine plant are operated as a whole, although still without fuel. During the tests, the water temperature and the pressure of the primary circuit were gradually increased to the level where they would be during actual operation.


TVO has now said completion of the hot functional tests took 50 days longer than planned. "Based on the findings of the commissioning tests, a comprehensive modification package will be implemented at OL3 over the next few months to update the plant's electrical and instrumentation and control (I&C) systems," the company said. "After the modification works, the necessary parts of the commissioning tests will be repeated and commissioning will continue. In addition, the pressuriser surge line vibrations that delayed the hot functional tests will be corrected before fuel loading."


Fuel loading will begin once a safety assessment of Olkiluoto 3 is carried out by the Radiation and Nuclear Safety Authority and a decision by the Finnish government to issue an operating licence.


The Areva-Siemens consortium has informed TVO that the loading of fuel into the core of OL3 is now expected in January 2019, connection of the plant to the electrical grid in May and the start of regular electricity production in September next year. Under the previous schedule, fuel loading was planned for later this year, grid connection taking place in December, with the start of regular electricity production in May next year.


"The hot functional testing has now been successfully completed and the schedule for the next phases has been defined," said TVO's OL3 Project Director Jouni Silvennoinen. "The whole commissioning is performed with utmost care, without compromise. We will have a modern and safe plant, and its commissioning will strengthen our know-how for the operating phase."


The Areva-Siemens consortium began construction of Olkiluoto 3 - the first-of-a-kind EPR - in 2005 under a turnkey contract signed with TVO in late 2003. Completion of the reactor was originally scheduled for 2009, but the project has suffered various delays and setbacks.


Fuel was loaded into the core of the Taishan 1 EPR in China's Guangdong province in April and that reactor achieved first criticality on 6 June. The unit is later this year scheduled to become the first EPR reactor to enter operation. Fuel loading at the Flamanville EPR in France is scheduled to begin in the fourth quarter of this year.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Start-up-of-Finnish-EPR-put-back-four-months-1406184.html



其他新聞
2018/7/16 10:00:56 - WANO completes reviews of Leningrad and Tianwan plants
2018/7/16 9:57:23 - Yangjiang 5 enters commercial operation
2018/7/16 9:46:00 - ‘Breakthrough’ For Bulgaria As €31M Plasma Melting Plant Begins Operations At Kozloduy Nuclear Station
2018/7/16 9:43:19 - European Court Dismisses Austria’s Objections To Hinkley Point C
2018/7/13 10:22:08 - Austrian case against Hinkley Point C aid rejected
2018/7/13 10:19:37 - UK's post-Brexit nuclear plans face scrutiny
2018/7/13 10:13:34 - 輻射監測生力軍!石門水庫、清華大學環境輻射監測站正式上線
2018/7/13 10:06:30 - 核三廠1號機預定於7月15日降載例行測試,原能會持續監控電廠運轉安全
2018/7/9 10:51:40 - Think-tanks call for states to adopt Clean Energy Standards
2018/7/9 10:49:29 - EDF maintains plant safety is a priority
2018/7/9 10:47:06 - NEI issues guidelines for regulatory interactions
2018/7/6 12:09:34 - 核二廠2號機於今(6)日降載進行例行測試,原能會持續監控電廠運轉安全(更新)
2018/7/6 12:08:15 - 核二廠2號機預定於7月7日降載例行測試,原能會持續監控電廠運轉安全
2018/7/4 10:08:53 - Boss launches Honeymoon restart strategy
2018/7/4 10:04:16 - NDA to take over management of Magnox sites
2018/7/4 9:58:23 - Japanese Cabinet approves new basic energy plan
2018/7/4 9:50:06 - 今(04)日04時10分台東縣政府北方規模4.6有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/7/4 9:42:18 - 核二廠1號機反應器圍阻體廠房氣體流程輻射監測器發出警戒訊號之說明
2018/7/2 10:44:58 - China's Taishan 1 reactor connected to grid
2018/7/2 10:40:05 - Bruce Power and ITM to supply cancer therapy isotope

 線上期刊目錄

 瀏覽人數
今天: 140
昨天: 122
本月: 2464
總計: 530691

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw