國際核能現況 : Start-up of Finnish EPR put back four months
發表人 nicenter 於 2018/6/15 15:11:29 (177 人讀取)

Regular electricity generation at the Olkiluoto 3 EPR in Finland is now expected to begin in September 2019 as commissioning tests will take longer than planned, Finnish utility Teollisuuden Voima Oyj (TVO) announced yesterday. According to the previous schedule provided by plant supplier the Areva-Siemens consortium, production was planned to start next May.






The Olkiluoto EPR, pictured in August 2016 (Image: TVO)

In April, TVO said it was waiting for "an overall rebaseline schedule" from the Areva-Siemens consortium "due to some delays in the hot functional testing phase".


Hot functional testing of the Olkiluoto 3 (OL3) EPR began in December and was completed in late May. These key pre-operational tests ensure coolant circuits and nuclear safety systems are functioning properly before fuel is loaded. They are the first tests at plant-level where the 1600 MWe pressurised water reactor and turbine plant are operated as a whole, although still without fuel. During the tests, the water temperature and the pressure of the primary circuit were gradually increased to the level where they would be during actual operation.


TVO has now said completion of the hot functional tests took 50 days longer than planned. "Based on the findings of the commissioning tests, a comprehensive modification package will be implemented at OL3 over the next few months to update the plant's electrical and instrumentation and control (I&C) systems," the company said. "After the modification works, the necessary parts of the commissioning tests will be repeated and commissioning will continue. In addition, the pressuriser surge line vibrations that delayed the hot functional tests will be corrected before fuel loading."


Fuel loading will begin once a safety assessment of Olkiluoto 3 is carried out by the Radiation and Nuclear Safety Authority and a decision by the Finnish government to issue an operating licence.


The Areva-Siemens consortium has informed TVO that the loading of fuel into the core of OL3 is now expected in January 2019, connection of the plant to the electrical grid in May and the start of regular electricity production in September next year. Under the previous schedule, fuel loading was planned for later this year, grid connection taking place in December, with the start of regular electricity production in May next year.


"The hot functional testing has now been successfully completed and the schedule for the next phases has been defined," said TVO's OL3 Project Director Jouni Silvennoinen. "The whole commissioning is performed with utmost care, without compromise. We will have a modern and safe plant, and its commissioning will strengthen our know-how for the operating phase."


The Areva-Siemens consortium began construction of Olkiluoto 3 - the first-of-a-kind EPR - in 2005 under a turnkey contract signed with TVO in late 2003. Completion of the reactor was originally scheduled for 2009, but the project has suffered various delays and setbacks.


Fuel was loaded into the core of the Taishan 1 EPR in China's Guangdong province in April and that reactor achieved first criticality on 6 June. The unit is later this year scheduled to become the first EPR reactor to enter operation. Fuel loading at the Flamanville EPR in France is scheduled to begin in the fourth quarter of this year.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Start-up-of-Finnish-EPR-put-back-four-months-1406184.html



其他新聞
2018/11/9 9:44:29 - Toshiba decides to scrap Moorside project
2018/11/7 9:30:04 - Hurricane-hit Puerto Rico to consider nuclear power
2018/11/7 9:28:12 - Saudi Arabia lays research reactor foundation stone
2018/11/7 9:25:41 - First reactor on Russia's floating plant starts up
2018/11/7 9:21:42 - Cameco notes market improvements
2018/11/5 9:36:36 - UK, Canada sign Nuclear Cooperation Agreement
2018/11/5 9:34:12 - Idaho proposed for HALEU fuel fabrication
2018/11/5 9:32:35 - IAEA reviews long-term safety of Argentinean plant
2018/11/5 9:30:50 - Decommissioning milestone for space fuel plant
2018/11/5 9:26:17 - 除役首部曲 核一乾貯核定計畫遭新北市府認定失效 台電今再提訴願
2018/11/2 9:51:26 - Climate goal demands huge boost in Chinese nuclear
2018/11/2 9:48:15 - 核三廠預定於107年11月02~03日 期間執行11.4kV定期維護檢查,部分饋線將受影響停電,原能會持續監控電廠輻射安全
2018/11/2 9:44:35 - 核三廠2號機預定於11月4日降載例行測試,原能會持續監控電廠運轉安全
2018/11/2 9:39:26 - 今(31)日中央氣象局發布豪雨特報,原能會要求台電公司強化各核能電廠及放射性物料設施防汛作業
2018/11/2 9:32:57 - 因應中火工安意外 台電:痛定思痛 全面進行工安總體檢
2018/10/31 9:37:12 - Poland needs nuclear power, explains energy minister
2018/10/31 9:33:52 - Fourth Tianwan unit connected to grid
2018/10/31 9:24:20 - 今(31)日8時11分花蓮縣萬榮鄉規模4.2有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/10/31 9:22:01 - 台電2018全民節電運動今頒獎 338萬戶響應節電飆歷年新高
2018/10/29 9:22:07 - NEI to review US-China export policy

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw