國際核能現況 : Toshiba scraps project to build ABWRs in Texas
發表人 nicenter 於 2018/6/1 14:16:45 (15 人讀取)

Japan's Toshiba Corporation is to withdraw from the project to construct two of its advanced boiling water reactors (ABWRs) as units 3 and 4 of the South Texas Project (STP) in the USA. The company said the project, which has failed to find investors, is no longer financially viable.





Toshiba - through its US-based wholly-owned subsidiary Toshiba America Nuclear Energy Corporation (TANE) - and US utility NRG Energy founded Nuclear Innovation North America (NINA) in 2008 to promote the use of Toshiba's ABWR in North America. A combined construction and operating licence (COL) application for two ABWRs at STP, where NRG Energy already operates two pressurised water reactors, had already been submitted to the Nuclear Regulatory Commission (NRC) in 2007. In February 2009, TANE signed an engineering, procurement and construction (EPC) contract with STP Nuclear Operating Company, acting as an agent for NINA, and thereby became the main contractor for STP units 3 and 4. However, in 2011 NRG Energy announced that it would be withdrawing from the project and writing down its USD331 million investment in NINA. Since then, Toshiba has bankrolled the licensing process.


The NRC notified NINA in late 2011 that the corporation did not meet the foreign ownership requirements and would therefore be ineligible to receive a licence; however NINA subsequently filed revisions to its COL application and a "negation action plan" to address the issue. The NRC told NINA that it will continue to review the remaining portions of the COL application while the company "considers its options", but will not issue a licence until the foreign ownership requirements are met. The NRC Atomic Safety Licensing Board has since ruled that Toshiba's formal 10% ownership of NINA was acceptable and the COLs for STP 3 and 4 were eventually granted in February 2016.


Toshiba announced today that its board had decided TANE will withdraw from the project. "Toshiba will proceed with the necessary procedures for the withdrawal with all related parties, and target its early completion," the company said. It expects to complete its withdrawal by the end of this year.


"The economic circumstances supporting the project have declined as a result of significant decreases in electricity rates due to the shale gas revolution, and the trend to tighter regulation of nuclear power plants in the aftermath of the Great East Japan Earthquake," Toshiba said. "Under current and expected economic conditions, further development of STP units 3 and 4 has ceased to be financially viable. In addition, maintaining the project incurs continuous costs, and no investors have expressed an interest in participation." It continued, "In these circumstances, there is no clear pathway to securing profitability and Toshiba has decided to completely withdraw from the project. The company has resolved to cancel all contracts related to NINA, the EPC contract and deferred loans, and to forgive loans under loan contracts."


Toshiba said its decision to exit the STP units 3 and 4 project is in line with its basic policy "to eliminate risk from the overseas nuclear power business, particularly from construction-related cost overruns in nuclear power plant construction projects, by withdrawing from projects where Toshiba Group serves as prime contractor or has to bear risk from construction-related cost overruns".


The company said that, as of today, it has claims of USD641 million and an equity interest of USD147 million in the US ABWR project. However, it noted that it recorded allowances for most of all bad debt and impairment loss by FY2017, which ended 31 March 2018, and the impact on business results in FY2018 "will be minimal".


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Toshiba-scraps-project-to-build-ABWRs-in-Texas-3105184.html



其他新聞
2018/6/15 15:27:03 - 端午連假豪雨報到 台電成立緊急應變中心待命
2018/6/15 15:14:42 - Nuclear Body Sounds Warning On Premature Shutdowns In France And Calls For ‘Renewal’ Of Nuclear Fleet
2018/6/15 15:13:41 - First yellowcake from seawater for US team
2018/6/15 15:11:29 - Start-up of Finnish EPR put back four months
2018/6/13 15:12:06 - 新機組陸續上線 台電:明年起備用維持15%以上 穩定供電無虞
2018/6/13 15:09:41 - 以最高標準要求安全,核二廠2號機因高壓輸電線路夾板溫度偏高之非機組因素,預定今(12)日晚上解聯調整
2018/6/13 15:04:17 - Jordan Abandons Nuclear Station Deal With Russia
2018/6/13 15:02:06 - Cooperation strengthens mining radiation protection
2018/6/13 14:58:59 - IAEA launches challenge on materials for fusion
2018/6/6 14:39:25 - 竹園超高壓變電所正式啟用 再提升竹科及新竹地區供電品質
2018/6/6 14:28:38 - 原能會今(5)日同意台電公司核二廠2號機急停後再起動
2018/6/6 14:27:30 - DOE announces funding for innovative nuclear technology
2018/6/6 14:25:29 - Tepco frees up Fukushima Daiichi fuel storage space
2018/6/6 14:24:23 - UK starts talks on public investment in nuclear power
2018/6/1 14:22:44 - 針對媒體評論「備轉容量率3%多是『電力供應充足』!」的回應說明
2018/6/1 14:20:00 - 「低放射性廢棄物貯存設施再評估報告審查導則草案」徵詢各界意見
2018/6/1 14:19:06 - Kansai cuts power rates as reactors restart
2018/6/1 14:16:45 - Toshiba scraps project to build ABWRs in Texas
2018/6/1 14:14:33 - US energy regulators back Illinois legislation
2018/5/30 14:20:00 - Barakah 1 start-up schedule revised for operator training

 線上期刊目錄

 瀏覽人數
今天: 37
昨天: 156
本月: 2726
總計: 526142

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw