國際核能現況 : Barakah 1 start-up schedule revised for operator training
發表人 nicenter 於 2018/5/30 14:20:00 (19 人讀取)

Fuel loading at unit 1 of the United Arab Emirates' first nuclear power plant will now take place in late 2019 or early 2020. Nawah Energy Company said the updated start-up schedule reflects the time required to complete operator training and to obtain the necessary regulatory approvals.





Barakah units 1 to 4, pictured in December 2017 (Image: Enec)

Nawah said it has completed a comprehensive operational readiness review, carried out "in strict accordance with the principles of a healthy nuclear safety culture, which requires conservative decision-making to support nuclear safety". The resulting projection for the start-up of Barakah 1 "reflects the time required for the plant's nuclear operators to complete operational readiness activities and to obtain necessary regulatory approvals, all of which are designed to ensure safe, sustainable nuclear operations after start-up". Nawah added that the review "reflects a conservative approach intended to ensure that the highest standards of nuclear quality, safety and security are firmly established as the foundation for future nuclear operations in the UAE".


The loading of fuel into unit 1 will only begin once all preparations for nuclear operations are successfully completed and an operating licence has been received from the Federal Authority for Nuclear Regulation, Nawah said. This is now expected to occur between the end of 2019 and early 2020.


Nawah CEO Mark Reddemann said: "Nawah's commitment to meet the highest standards of quality and safety is the main driver for all our work. As a result, our review relied on global nuclear standards to analyse the remaining work required for nuclear operations, and we are confident that this new projection for fuel load gives Nawah a nuclear-centric and conservative schedule to deliver nuclear operations in alignment with the highest standards of safety and quality.


"Unit 1 is the pioneering nuclear energy reactor in the UAE and will set the benchmark for the three remaining units of the Barakah plant and, possibly, for other nuclear energy projects in the Arab world."


Four Korean-designed APR-1400 units are being built for the Emirates Nuclear Energy Corporation (Enec) at Barakah, in the Dhafrah region of Abu Dhabi, by a consortium led by the Korean Electric Power Company (Kepco). Construction began on the first unit in July 2012, unit 2 in May 2013, unit 3 in September 2014 and unit 4 in September 2015. The completion of construction at unit 1 was celebrated in March at a ceremony attended by President Moon Jae-in of South Korea and Crown Prince of Abu Dhabi Sheikh Mohamed bin Zayed Al Nahyan. The unit is now in the commissioning and testing phase.


Enec established Nawah Energy in 2016 as a joint venture with Kepco to operate and maintain Barakah units 1-4. The company is 82% owned by Enec and 18% owned by Kepco.


Overall construction of the Barakah plant is now more than 88% complete. All four units had originally been expected to be in service by the end of 2020. When operational, the four Barakah units will provide up to one-quarter of the UAE's electricity needs.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Barakah-1-start-up-schedule-revised-for-operator-training-2905184.html



其他新聞
2018/6/15 15:27:03 - 端午連假豪雨報到 台電成立緊急應變中心待命
2018/6/15 15:14:42 - Nuclear Body Sounds Warning On Premature Shutdowns In France And Calls For ‘Renewal’ Of Nuclear Fleet
2018/6/15 15:13:41 - First yellowcake from seawater for US team
2018/6/15 15:11:29 - Start-up of Finnish EPR put back four months
2018/6/13 15:12:06 - 新機組陸續上線 台電:明年起備用維持15%以上 穩定供電無虞
2018/6/13 15:09:41 - 以最高標準要求安全,核二廠2號機因高壓輸電線路夾板溫度偏高之非機組因素,預定今(12)日晚上解聯調整
2018/6/13 15:04:17 - Jordan Abandons Nuclear Station Deal With Russia
2018/6/13 15:02:06 - Cooperation strengthens mining radiation protection
2018/6/13 14:58:59 - IAEA launches challenge on materials for fusion
2018/6/6 14:39:25 - 竹園超高壓變電所正式啟用 再提升竹科及新竹地區供電品質
2018/6/6 14:28:38 - 原能會今(5)日同意台電公司核二廠2號機急停後再起動
2018/6/6 14:27:30 - DOE announces funding for innovative nuclear technology
2018/6/6 14:25:29 - Tepco frees up Fukushima Daiichi fuel storage space
2018/6/6 14:24:23 - UK starts talks on public investment in nuclear power
2018/6/1 14:22:44 - 針對媒體評論「備轉容量率3%多是『電力供應充足』!」的回應說明
2018/6/1 14:20:00 - 「低放射性廢棄物貯存設施再評估報告審查導則草案」徵詢各界意見
2018/6/1 14:19:06 - Kansai cuts power rates as reactors restart
2018/6/1 14:16:45 - Toshiba scraps project to build ABWRs in Texas
2018/6/1 14:14:33 - US energy regulators back Illinois legislation
2018/5/30 14:20:00 - Barakah 1 start-up schedule revised for operator training

 線上期刊目錄

 瀏覽人數
今天: 37
昨天: 156
本月: 2726
總計: 526142

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw