國際核能現況 : Bruce Power signs advanced manufacturing contracts
發表人 nicenter 於 2018/4/25 14:13:20 (84 人讀取)

Bruce Power has signed CAD914 million (USD712 million) in advanced manufacturing contracts for its major component replacement (MCR) that starts in 2020 and will allow the site to provide low-cost, carbon-free electricity to Ontario to 2064. Announcing the deals yesterday, Bruce Power said its Life-Extension Programme - which includes the MCRs on units 3-8 - remains on time and on budget.





The Bruce B plant (Image: Bruce Power)

The new contracts include: CAD642 million to BWXT Canada Inc for the manufacturing of 32 steam generators to be produced at BWXT's Cambridge facility; CAD144 million to Laker Energy Products for end fittings, liners and flow elements, which will be manufactured at its Oakville location; CAD62 million to Cameco Fuel Manufacturing, in Cobourg, for calandria tubes and annulus spacers for all six MCRs; and CAD66 million for Nu-Tech Precision Metals, in Arnprior, for the production of zirconium alloy pressure tubes for Units 6 and 3.


Mike Rencheck, Bruce Power's president and CEO, said that, by extending the life of Bruce Power's reactors to 2064, the company will create and sustain 22,000 jobs annually, while investing CAD4 billion a year into Ontario's economy. At the same time, Bruce Power will produce 30% of the province's electricity at almost one-third less than the average cost to generate residential power, while also producing zero-carbon emissions.


Bruce Power operates eight Candu reactors - units 1-4 at Bruce A and units 5-8 at Bruce B. Units 1 and 2 at Bruce A have already been refurbished.


In January 2016, the company launched its CAD$13 billion, multi-year Life-Extension Programme under an agreement with the Independent Electricity System Operator, the government corporation responsible for Ontario's power supply. Bruce unit 6 will be the first unit to undergo refurbishment, beginning in 2020, and the programme will take until 2053 to complete.


Researched and written
by World Nuclear News




source:http://www.world-nuclear-news.org/C-Bruce-Power-signs-advanced-manufacturing-contacts-24041801.html



其他新聞
2018/10/17 9:29:49 - 核三廠舊廢料廠房流程輻射警報器產生警戒訊號補充說明
2018/10/17 9:27:15 - 核三廠舊廢料廠房流程輻射警報器產生警戒訊號
2018/10/15 11:28:40 - USA announces China export policy
2018/10/12 9:38:39 - 總統出席「中華民國中樞暨各界慶祝107年國慶大會」,發表演說強調非核家園也不能走回頭路,原能會配合政府政策就核安管制機關立場說明
2018/10/12 9:34:50 - 核三廠2號機預定於10月14日降載例行測試,原能會持續監控電廠運轉安全
2018/10/8 9:29:55 - IAEA assesses operational safety of Torness plant
2018/10/5 9:16:24 - IAEA assesses operational safety of Torness plant
2018/10/3 9:51:44 - HTR-PM steam generator passes pressure tests
2018/10/3 9:50:00 - First criticality for Tianwan unit 4
2018/10/3 9:48:18 - Rostov unit 4 enters commercial operation
2018/10/3 9:46:54 - USA awards HEU downblending contract
2018/10/3 9:42:38 - WANO invites early engagement on new nuclear build
2018/10/1 9:39:11 - IAEA-led project looks at climate change mitigation
2018/10/1 9:37:47 - Tokai 2 cleared for restart
2018/10/1 9:36:21 - Injunction lifted on operation of Japanese reactor
2018/10/1 9:34:33 - NuScale SMR enters first manufacturing phase
2018/10/1 9:33:21 - Swedish regulator calls for national strategy
2018/9/28 9:36:07 - Vogtle progress rests on Oglethorpe vote
2018/9/28 9:34:21 - Senegal aims to build nuclear technology centre
2018/9/28 9:32:31 - Draft law supports Chinese nuclear exports

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw