國際核能現況 : Darlington refurbishment achieves new milestone
發表人 nicenter 於 2018/3/30 14:17:55 (26 人讀取)

Removal of the final calandria tube insert (CTI) at Ontario Power Generation's (OPG) Darlington unit 2 yesterday marks the completion of an important step in disassembly of the Candu reactor as it undergoes refurbishment.





Inside Darlington 2's reactor vault during CTI removal (Image: OPG)


Calandria tubes sit in the reactor's core, each housing a pressure tube containing nuclear fuel bundles. They are secured at each end by a CTI, a metal ring which forms a mechanical seal.

A new production planning tool used during CTI removal allowed the work series to be completed early, OPG said. The tool involved a process map including timed durations for each of the steps in the process, including removing the components, placing them in flasks, transferral to waste containers, and returning the flasks back to the unit. These maps are now being used in subsequent work series, the company said.

"The result was like clockwork since we understood every discrete step of the sequence including the impact of speeding up or slowing down one step and the impact on the rest of the steps," the Darlington Refurbishment Team's Perrik Le Dreff said.

Completion of CTI removal means the extraction of the calandria tubes themselves can now begin. After this, the reactor will undergo inspections before it is rebuilt.

Darlington 2 is the first of the plant's four Candu units to undergo refurbishment in a phased CAD12.8 billion (USD9 billion) project which is scheduled for completion by 2026. Refurbishment of Darlington unit 2 formally began on 14 October 2016 after six years of planning, and will take some 40 months to complete. The project passed the halfway mark on 15 February. Refurbishment of unit 3 is scheduled to begin after completion of work on unit 2 to allow the implementation of lessons learned.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/C-Darlington-refurbishment-achieves-new-milestone-2903188.html



其他新聞
2018/4/20 14:20:00 - 台電回應綠色和平,深澳對pm2.5的貢獻度最多0.08~0.18%,不知「相當於160萬輛汽車」的推估是從何而來?
2018/4/20 14:11:05 - 大潭電廠新增機組輸電線路變更 降低環境衝擊 依法提出環差申請
2018/4/20 14:07:49 - IAEA tests drone to fight disease-carrying mosquitos
2018/4/20 14:05:39 - Canada considers participation in Iter fusion project
2018/4/18 15:20:00 - 還原瑞芳保育區爭議的真相,台電籲請外界回歸事實討論
2018/4/18 15:18:00 - 台電深澳超超臨界計畫空品影響不到法規萬分之一 不會有許厝國小第2
2018/4/18 15:13:38 - AEM Technology sees milestone with first VVER-TOI
2018/4/18 15:10:12 - Report highlights impact of US nuclear plant closures
2018/4/18 15:04:37 - India, USA to collaborate on neutrino science
2018/4/11 15:10:00 - 台電簽署離岸風電第三方驗證合作備忘錄 為健全綠色金融環境助力
2018/4/11 15:08:23 - 原能會已設立「核二廠2號機再起動」專區,持續公開管制資訊
2018/4/11 15:03:05 - Council formed to support Canadian isotope production
2018/4/11 14:56:44 - Final Barakah dome complete
2018/3/30 14:47:16 - 今(29)日8時17分南投地區規模4.8有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/3/30 14:46:01 - 地熱發電國家隊首部曲 台電與中油簽MOU開發宜蘭地熱
2018/3/30 14:26:54 - FirstEnergy gives notice to deactivate four units
2018/3/30 14:17:55 - Darlington refurbishment achieves new milestone
2018/3/30 14:13:35 - Court approves Westinghouse reorganisation plan
2018/3/28 15:02:51 - 因應能源轉型 積極面對核四資產處理 台電:採影響最小化
2018/3/28 14:30:22 - Czech new build financing decision by mid-year

 線上期刊目錄

 瀏覽人數
今天: 36
昨天: 101
本月: 1993
總計: 519363

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw