國際核能現況 : Georgia Power hires Summer operators for Vogtle
發表人 nicenter 於 2018/3/2 14:08:36 (25 人讀取)

Georgia Power has hired 14 operators for Vogtle 3 and 4 from the abandoned VC Summer nuclear project. In its latest report to the Georgia Public Service Commission (PSC), the company said this will save nearly two years of training time and costs.

Vogtle unit 3, pictured in January 2018 (Image: Georgia Power)

Georgia Power is required to file reports with the PSC every six month to provide an update on construction progress and other information related to the construction the two AP1000 units. The 18th VCM report, filed yesterday, covers the period from 1 July to 31 December 2017, and is the first since the PSC's decision in December to approve Georgia Power's recommendation to complete the units.

The latest report includes a revised, lower projected rate impact for customers and outlines continued progress and productivity improvement at the construction site near Waynesboro, Georgia. It also reaffirms the target in-service dates of November 2021 for Vogtle 3 and November 2022 for Vogtle 4, and that completing the units remains the best cost option to meeting the state's future energy needs following contractor Westinghouse's Chapter 11 bankruptcy filing in March 2017.

Construction work has continued, with Southern Nuclear taking over as project manager at the site and Bechtel managing construction. The 18th VCM report notes that productivity at the construction site has improved since Southern Nuclear assumed overall project management. Construction work is currently tracking ahead of the plan to achieve the target in-service dates, Georgia Power said.

The past six months have seen construction progress on both units. Key modules and components including both steam generators and the pressuriser for unit 3, and structural modules CA02 and CA03 for unit 4, have been installed and thousands of tonnes of rebar and tens of thousands of cubic yards of concrete placed throughout the site, the company said. Major equipment, including squib valves for both units, the passive residual heat removal heat exchanger and the reactor vessel internals for unit 4 have been delivered, and most of the modules and equipment needed to complete the project is now onsite.

The company must ensure the necessary number of licensed operators are in place to support fuel loading at the two units.

Scana Corporation subsidiary South Carolina Electric & Gas in August decided to cease construction of two AP1000 reactors at VC Summer in South Carolina, and 14 operators who passed the US Nuclear Regulatory Commission (NRC) exam at VC Summer have now been hired by Georgia Power. Thirty-six Vogtle candidates have now passed the NRC operator licensing exam, and further candidates are preparing to sit the NRC Initial License Training exam later this month. Another wave of candidates is due to begin training for the NRC exams in June.

The PSC in January approved a revised capital cost forecast for the Vogtle project of $7.3 billion. Georgia Power is requesting PSC verification and approval of $448 million of capital expenditures incurred during the reporting period for the 18th VCM.

Researched and written
by World Nuclear News


2018/3/23 14:20:49 - Drones to venture into Fukushima containment vessels
2018/3/23 14:19:53 - IEA sees record energy sector emissions in 2017
2018/3/23 14:11:02 - Pipe robot aids enrichment plant decommissioning
2018/3/21 14:51:19 - 今(20)日17時22分嘉義地區規模5.2有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/3/21 14:44:45 - 深澳計畫14日環評修正通過 台電:新機組排放接近燃氣標準 兼顧供電與環保
2018/3/21 14:41:51 - Chalk River laboratory request for proposals issued
2018/3/21 14:38:10 - Reactor vessel installation under way at Hongyanhe 5
2018/3/21 14:30:39 - Court rules against bid to halt Ohma construction
2018/3/16 14:35:17 - 龍門電廠燃料束預計最快6月起陸續運回美國原廠 拆解再利用
2018/3/16 14:33:58 - 深澳電廠更新計畫 台電:採最先進USC燃煤機組 取供電環保平衡
2018/3/16 14:31:01 - Amano commends Pakistan nuclear safety and security
2018/3/16 14:30:00 - Ohi 3 reaches critical milestone in restart
2018/3/16 14:26:19 - NRC issues confirmatory order for Entergy violations
2018/3/14 14:14:33 - 311七週年 台電:持續推動核電除役、核廢處理與能源轉型
2018/3/14 14:13:29 - Regulator approves Fessenheim 2 steam generator
2018/3/14 14:11:43 - Westinghouse ready to supply VVER-440 fuel
2018/3/14 14:10:00 - Russia brings Chinese funding into uranium mining
2018/3/9 14:16:39 - Russia discusses African nuclear power prospects
2018/3/9 14:10:45 - India plans tenfold uranium output growth
2018/3/9 14:09:42 - China to start building up to eight reactors in 2018


今天: 15
昨天: 61
本月: 2249
總計: 516766

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw