logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 相關資訊
* 瀏覽人數
今天: 117
昨天: 123
本月: 2345
總計: 539833
國際核能現況 : Georgia Power hires Summer operators for Vogtle
發表人 nicenter 於 2018/3/2 14:08:36 (75 人讀取)

Georgia Power has hired 14 operators for Vogtle 3 and 4 from the abandoned VC Summer nuclear project. In its latest report to the Georgia Public Service Commission (PSC), the company said this will save nearly two years of training time and costs.






Vogtle unit 3, pictured in January 2018 (Image: Georgia Power)

Georgia Power is required to file reports with the PSC every six month to provide an update on construction progress and other information related to the construction the two AP1000 units. The 18th VCM report, filed yesterday, covers the period from 1 July to 31 December 2017, and is the first since the PSC's decision in December to approve Georgia Power's recommendation to complete the units.


The latest report includes a revised, lower projected rate impact for customers and outlines continued progress and productivity improvement at the construction site near Waynesboro, Georgia. It also reaffirms the target in-service dates of November 2021 for Vogtle 3 and November 2022 for Vogtle 4, and that completing the units remains the best cost option to meeting the state's future energy needs following contractor Westinghouse's Chapter 11 bankruptcy filing in March 2017.


Construction work has continued, with Southern Nuclear taking over as project manager at the site and Bechtel managing construction. The 18th VCM report notes that productivity at the construction site has improved since Southern Nuclear assumed overall project management. Construction work is currently tracking ahead of the plan to achieve the target in-service dates, Georgia Power said.


The past six months have seen construction progress on both units. Key modules and components including both steam generators and the pressuriser for unit 3, and structural modules CA02 and CA03 for unit 4, have been installed and thousands of tonnes of rebar and tens of thousands of cubic yards of concrete placed throughout the site, the company said. Major equipment, including squib valves for both units, the passive residual heat removal heat exchanger and the reactor vessel internals for unit 4 have been delivered, and most of the modules and equipment needed to complete the project is now onsite.


The company must ensure the necessary number of licensed operators are in place to support fuel loading at the two units.


Scana Corporation subsidiary South Carolina Electric & Gas in August decided to cease construction of two AP1000 reactors at VC Summer in South Carolina, and 14 operators who passed the US Nuclear Regulatory Commission (NRC) exam at VC Summer have now been hired by Georgia Power. Thirty-six Vogtle candidates have now passed the NRC operator licensing exam, and further candidates are preparing to sit the NRC Initial License Training exam later this month. Another wave of candidates is due to begin training for the NRC exams in June.


The PSC in January approved a revised capital cost forecast for the Vogtle project of $7.3 billion. Georgia Power is requesting PSC verification and approval of $448 million of capital expenditures incurred during the reporting period for the 18th VCM.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Georgia-Power-hires-Summer-operators-for-Vogtle-0103187.html



其他新聞
2018/9/19 9:50:17 - Centrus and Doosan sign advanced reactor MoU
2018/9/19 9:48:52 - French EPR engineering simulator to be upgraded
2018/9/19 9:47:20 - IAEA highlights nuclear's role in combating climate change
2018/9/19 9:45:28 - Challenging the nuclear finance status quo
2018/9/19 9:42:52 - Hualong One simulator ready for operator training
2018/9/17 9:35:44 - UK and USA enhance nuclear research cooperation
2018/9/17 9:33:05 - UK collaboration for safety and security research
2018/9/17 9:31:22 - Nuclear industry faces wake-up call, says IAEA's Chudakov
2018/9/17 9:26:43 - US plant operators prepare for Hurricane Florence
2018/9/14 9:39:51 - Newcomer countries need 'collaborative approach'
2018/9/14 9:36:42 - Investment needed to maintain nuclear's growth, says IAEA
2018/9/14 9:34:49 - Climate targets need market reform, says NEA's Magwood
2018/9/14 9:27:18 - India recommissions Apsara research reactor
2018/9/14 9:25:19 - California to be carbon neutral by 2045
2018/9/14 9:22:17 - 輻射監測更上層樓,蘭嶼氣象站標準型環境輻射監測設施啟用
2018/9/12 10:06:26 - Help the public understand radiation, advises cancer expert
2018/9/12 10:02:33 - Belgian government approves funding for Myrrha
2018/9/12 10:00:34 - IAEA completes Sudan nuclear infrastructure review
2018/9/12 9:58:46 - California to be carbon neutral by 2045
2018/9/12 9:49:01 - 原能會讓國人「石」在安心-持續執行107年石材建材業者輻射檢測

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw