logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 日本福島核災專區
* 相關資訊
國際核能現況 : Decommissioning progress for unique Canadian reactor
發表人 nicenter 於 2018/1/10 14:28:07 (15 人讀取)

Canadian federal and provincial authorities have completed their technical assessment of Canadian Nuclear Laboratories' (CNL's) draft environmental impact statement (EIS) for the proposed in-situ decommissioning of Whiteshell Reactor 1 (WR-1).





The proposal would involve filling the below-grade portions of the WNR-1 reactor, shown in this diagram, with a special grout (Image: CNL)

The research reactor, which reached a maximum of 60 MWt, attained first criticality in 1962 at the Whiteshell Laboratories site in Pinawa, Manitoba. The unique reactor had vertical fuel channels, and was moderated by heavy water but cooled by an organic liquid. It was used until 1972 as a test reactor for a proposed organic-cooled Candu power reactor, and subsequently for irradiation, experimentation and heating the Whiteshell site until its closure in 1985.


At the time the reactor was shut down, deferred decommissioning was the preferred strategy for management of the main reactor building. The reactor was therefore defuelled and has been maintained in a state of "storage with surveillance", according to CNL.


CNL is now proposing to decommission WR-1 using an in-situ technique, an approach which it says will provide a safe, secure and effective disposal solution for the existing contaminated building, much of which is below ground level, while minimising risks to the health, safety and security of the public, workers and the environment. It is proposing a technique which will involve pouring a specially engineered grout into the reactor to lock contaminants in place. A protective cover at the surface which will channel water away from the site and protect it from the elements.


The federal environmental assessment of the proposed decommissioning project, which is required under Canadian environmental law, began in May 2016. The draft EIS was open to public comments from 6 October until 20 December 2017.


The Canadian Nuclear Safety Commission (CNSC), the responsible authority for the environmental assessment process, said it has identified a number of areas where additional information will need to be included in the final EIS and other technical supporting documentation. A consolidated table of over 200 information requests and comments from the CNSC and other federal and provincial authorities participating in the review - Environment and Climate Change Canada, Health Canada, Natural Resources Canada and Manitoba Sustainable Development - has now been submitted back to CNL.


CNL must address all comments received before submitting its final EIS to the CNSC, after which the regulator will then determine if the information is complete. The final EIS is expected to be submitted in April. The CNSC's assessment of the final EIS and the EA report will made available to the public for 60 days prior to a public hearing which is expected to take place in October.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/WR-Decommissioning-progress-for-unique-Canadian-reactor-0801187.html



其他新聞
2018/1/19 14:48:08 - 新北市將停發生煤許可 台電:超超臨界燃煤機組排放接近燃氣排放標準 可兼顧供電與環保
2018/1/19 14:46:08 - 今(17)日台北市北投區發生之有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/1/19 14:45:13 - Toshiba agrees sale of Westinghouse claims
2018/1/19 14:44:05 - Mining resumes at WIPP
2018/1/19 14:37:41 - EDF Energy expects 20% cost saving for Sizewell C
2018/1/17 14:15:15 - Lift nuclear ban, MCA tells Australian government
2018/1/17 14:09:56 - Steam generators installed at second Belarus unit
2018/1/17 14:08:03 - Regulator checks Rostov 4 ahead of start-up
2018/1/10 14:34:19 - 原能會已完成「核子事故常識及其防護」文宣,歡迎下載使用
2018/1/10 14:28:07 - Decommissioning progress for unique Canadian reactor
2018/1/10 14:25:02 - FERC starts new grid resilience proceeding
2018/1/10 14:20:38 - Flamanville EPR completes key pre-operational tests
2018/1/3 14:31:29 - 綠島邁向綠能島 台電首座地熱試驗探勘井開工
2018/1/3 14:30:00 - 全國環境輻射即時監測站107年起再增一站,計47站監測資訊即時網路公開
2018/1/3 14:20:12 - Taishan schedule factors in commissioning tests
2018/1/3 14:09:26 - New Rostov reactor starts up
2018/1/3 14:05:54 - Tianwan 3 starts supplying electricity to grid
2017/12/27 15:50:43 - 原能會今(26)日公開「國際核能安全公約中華民國國家報告」
2017/12/27 15:35:32 - 能源轉型 台電推動興達電廠燃氣機組更新計畫 2023年供電
2017/12/27 15:31:11 - Georgia Commission Gives Conditional Go-Ahead For Completion Of Vogtle-3 And -4

 線上期刊目錄

 瀏覽人數
今天: 31
昨天: 87
本月: 2372
總計: 511078

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw