國際核能現況 : Flamanville EPR completes key pre-operational tests
發表人 nicenter 於 2018/1/10 14:20:38 (86 人讀取)

EDF has completed cold functional tests at the EPR reactor under construction at its Flamanville site in northern France. Flamanville unit 3 is scheduled to begin operating by the end of this year.






The Flamanville EPR (Image: Alexis Morin and Antoine-Soubigou/EDF)

Cold functional tests are carried out to confirm whether components and systems important to safety are properly installed and ready to operate in a cold condition. The main purpose of these tests is to verify the leak-tightness of the primary circuit.


The cold functional test phase for Flamanville 3 began on 18 December and was completed on 6 January.


"This stage is part of the system performance testing, which started in the first quarter of 2017, to check and test operation of all the EPR systems," EDF said.


These tests included a leak performance test on the reactor coolant system at a pressure greater than 240 bar - significantly exceeding the normal operating pressure. During this test, more than 500 welds were inspected, supervised by the French nuclear regulator, Autorité de Sûreté Nucléaire (ASN).


EDF is now preparing to conduct hot functional tests, which will start in July. These will involve checking the equipment under similar temperature and pressure conditions to those under which it will operate.


Construction work began in December 2007 on the 1650 MWe unit at the Flamanville site in Normandy - where two reactors have been operating since 1986 and 1987. The dome of the reactor building was put in place in July 2013 and the reactor vessel was installed in January 2014. The reactor was originally expected to start commercial operation in 2013, but owing to delays this is now expected late this year.


EDF has confirmed its roadmap for the Flamanville 3 project drawn up in September 2015, with fuel loading and start-up of the reactor at the end of the fourth quarter of 2018. It also confirmed the project cost is set at €10.5 billion (at the 2015 rate, excluding interim interest).


The first-of-a-kind EPR at Finland's Olkiluoto plant has been under construction since 2005 and has seen several revisions to its start-up date. In October, the schedule for OL3 commencing regular electricity production was again revised from the end of 2018 to May 2019. The unit began functional hot tests last month.


The Taishan 1 EPR in China, which has been under construction since 2009, has completed functional hot tests and will be the first EPR to operate. It is expected to start up later this year, while Taishan 2 is scheduled to begin operating next year.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Flamanville-EPR-completes-key-pre-operational-tests-0901184.html



其他新聞
2018/4/20 14:20:00 - 台電回應綠色和平,深澳對pm2.5的貢獻度最多0.08~0.18%,不知「相當於160萬輛汽車」的推估是從何而來?
2018/4/20 14:11:05 - 大潭電廠新增機組輸電線路變更 降低環境衝擊 依法提出環差申請
2018/4/20 14:07:49 - IAEA tests drone to fight disease-carrying mosquitos
2018/4/20 14:05:39 - Canada considers participation in Iter fusion project
2018/4/18 15:20:00 - 還原瑞芳保育區爭議的真相,台電籲請外界回歸事實討論
2018/4/18 15:18:00 - 台電深澳超超臨界計畫空品影響不到法規萬分之一 不會有許厝國小第2
2018/4/18 15:13:38 - AEM Technology sees milestone with first VVER-TOI
2018/4/18 15:10:12 - Report highlights impact of US nuclear plant closures
2018/4/18 15:04:37 - India, USA to collaborate on neutrino science
2018/4/11 15:10:00 - 台電簽署離岸風電第三方驗證合作備忘錄 為健全綠色金融環境助力
2018/4/11 15:08:23 - 原能會已設立「核二廠2號機再起動」專區,持續公開管制資訊
2018/4/11 15:03:05 - Council formed to support Canadian isotope production
2018/4/11 14:56:44 - Final Barakah dome complete
2018/3/30 14:47:16 - 今(29)日8時17分南投地區規模4.8有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/3/30 14:46:01 - 地熱發電國家隊首部曲 台電與中油簽MOU開發宜蘭地熱
2018/3/30 14:26:54 - FirstEnergy gives notice to deactivate four units
2018/3/30 14:17:55 - Darlington refurbishment achieves new milestone
2018/3/30 14:13:35 - Court approves Westinghouse reorganisation plan
2018/3/28 15:02:51 - 因應能源轉型 積極面對核四資產處理 台電:採影響最小化
2018/3/28 14:30:22 - Czech new build financing decision by mid-year

 線上期刊目錄

 瀏覽人數
今天: 35
昨天: 101
本月: 1992
總計: 519362

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw