logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 相關資訊
* 瀏覽人數
今天: 94
昨天: 96
本月: 2653
總計: 540141
國際核能現況 : Flamanville EPR completes key pre-operational tests
發表人 nicenter 於 2018/1/10 14:20:38 (124 人讀取)

EDF has completed cold functional tests at the EPR reactor under construction at its Flamanville site in northern France. Flamanville unit 3 is scheduled to begin operating by the end of this year.






The Flamanville EPR (Image: Alexis Morin and Antoine-Soubigou/EDF)

Cold functional tests are carried out to confirm whether components and systems important to safety are properly installed and ready to operate in a cold condition. The main purpose of these tests is to verify the leak-tightness of the primary circuit.


The cold functional test phase for Flamanville 3 began on 18 December and was completed on 6 January.


"This stage is part of the system performance testing, which started in the first quarter of 2017, to check and test operation of all the EPR systems," EDF said.


These tests included a leak performance test on the reactor coolant system at a pressure greater than 240 bar - significantly exceeding the normal operating pressure. During this test, more than 500 welds were inspected, supervised by the French nuclear regulator, Autorité de Sûreté Nucléaire (ASN).


EDF is now preparing to conduct hot functional tests, which will start in July. These will involve checking the equipment under similar temperature and pressure conditions to those under which it will operate.


Construction work began in December 2007 on the 1650 MWe unit at the Flamanville site in Normandy - where two reactors have been operating since 1986 and 1987. The dome of the reactor building was put in place in July 2013 and the reactor vessel was installed in January 2014. The reactor was originally expected to start commercial operation in 2013, but owing to delays this is now expected late this year.


EDF has confirmed its roadmap for the Flamanville 3 project drawn up in September 2015, with fuel loading and start-up of the reactor at the end of the fourth quarter of 2018. It also confirmed the project cost is set at €10.5 billion (at the 2015 rate, excluding interim interest).


The first-of-a-kind EPR at Finland's Olkiluoto plant has been under construction since 2005 and has seen several revisions to its start-up date. In October, the schedule for OL3 commencing regular electricity production was again revised from the end of 2018 to May 2019. The unit began functional hot tests last month.


The Taishan 1 EPR in China, which has been under construction since 2009, has completed functional hot tests and will be the first EPR to operate. It is expected to start up later this year, while Taishan 2 is scheduled to begin operating next year.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Flamanville-EPR-completes-key-pre-operational-tests-0901184.html



其他新聞
2018/9/21 9:47:13 - EDF awards Framatome I&C upgrade contract
2018/9/21 9:44:29 - US nuclear innovation legislation makes progress
2018/9/21 9:38:40 - Korea expands cooperation with IAEA on radwaste
2018/9/21 9:37:10 - Norwegian, Belgian research centres enhance cooperation
2018/9/21 9:34:06 - Rooppur protocol signed on physical protection scope
2018/9/21 9:16:37 - 台電:侯反深澳影片 煙囪移花接木意圖恐嚇大眾
2018/9/19 9:50:17 - Centrus and Doosan sign advanced reactor MoU
2018/9/19 9:48:52 - French EPR engineering simulator to be upgraded
2018/9/19 9:47:20 - IAEA highlights nuclear's role in combating climate change
2018/9/19 9:45:28 - Challenging the nuclear finance status quo
2018/9/19 9:42:52 - Hualong One simulator ready for operator training
2018/9/17 9:35:44 - UK and USA enhance nuclear research cooperation
2018/9/17 9:33:05 - UK collaboration for safety and security research
2018/9/17 9:31:22 - Nuclear industry faces wake-up call, says IAEA's Chudakov
2018/9/17 9:26:43 - US plant operators prepare for Hurricane Florence
2018/9/14 9:39:51 - Newcomer countries need 'collaborative approach'
2018/9/14 9:36:42 - Investment needed to maintain nuclear's growth, says IAEA
2018/9/14 9:34:49 - Climate targets need market reform, says NEA's Magwood
2018/9/14 9:27:18 - India recommissions Apsara research reactor
2018/9/14 9:25:19 - California to be carbon neutral by 2045

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw