國際核能現況 : Flamanville EPR completes key pre-operational tests
發表人 nicenter 於 2018/1/10 14:20:38 (15 人讀取)

EDF has completed cold functional tests at the EPR reactor under construction at its Flamanville site in northern France. Flamanville unit 3 is scheduled to begin operating by the end of this year.






The Flamanville EPR (Image: Alexis Morin and Antoine-Soubigou/EDF)

Cold functional tests are carried out to confirm whether components and systems important to safety are properly installed and ready to operate in a cold condition. The main purpose of these tests is to verify the leak-tightness of the primary circuit.


The cold functional test phase for Flamanville 3 began on 18 December and was completed on 6 January.


"This stage is part of the system performance testing, which started in the first quarter of 2017, to check and test operation of all the EPR systems," EDF said.


These tests included a leak performance test on the reactor coolant system at a pressure greater than 240 bar - significantly exceeding the normal operating pressure. During this test, more than 500 welds were inspected, supervised by the French nuclear regulator, Autorité de Sûreté Nucléaire (ASN).


EDF is now preparing to conduct hot functional tests, which will start in July. These will involve checking the equipment under similar temperature and pressure conditions to those under which it will operate.


Construction work began in December 2007 on the 1650 MWe unit at the Flamanville site in Normandy - where two reactors have been operating since 1986 and 1987. The dome of the reactor building was put in place in July 2013 and the reactor vessel was installed in January 2014. The reactor was originally expected to start commercial operation in 2013, but owing to delays this is now expected late this year.


EDF has confirmed its roadmap for the Flamanville 3 project drawn up in September 2015, with fuel loading and start-up of the reactor at the end of the fourth quarter of 2018. It also confirmed the project cost is set at €10.5 billion (at the 2015 rate, excluding interim interest).


The first-of-a-kind EPR at Finland's Olkiluoto plant has been under construction since 2005 and has seen several revisions to its start-up date. In October, the schedule for OL3 commencing regular electricity production was again revised from the end of 2018 to May 2019. The unit began functional hot tests last month.


The Taishan 1 EPR in China, which has been under construction since 2009, has completed functional hot tests and will be the first EPR to operate. It is expected to start up later this year, while Taishan 2 is scheduled to begin operating next year.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Flamanville-EPR-completes-key-pre-operational-tests-0901184.html



其他新聞
2018/1/19 14:48:08 - 新北市將停發生煤許可 台電:超超臨界燃煤機組排放接近燃氣排放標準 可兼顧供電與環保
2018/1/19 14:46:08 - 今(17)日台北市北投區發生之有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/1/19 14:45:13 - Toshiba agrees sale of Westinghouse claims
2018/1/19 14:44:05 - Mining resumes at WIPP
2018/1/19 14:37:41 - EDF Energy expects 20% cost saving for Sizewell C
2018/1/17 14:15:15 - Lift nuclear ban, MCA tells Australian government
2018/1/17 14:09:56 - Steam generators installed at second Belarus unit
2018/1/17 14:08:03 - Regulator checks Rostov 4 ahead of start-up
2018/1/10 14:34:19 - 原能會已完成「核子事故常識及其防護」文宣,歡迎下載使用
2018/1/10 14:28:07 - Decommissioning progress for unique Canadian reactor
2018/1/10 14:25:02 - FERC starts new grid resilience proceeding
2018/1/10 14:20:38 - Flamanville EPR completes key pre-operational tests
2018/1/3 14:31:29 - 綠島邁向綠能島 台電首座地熱試驗探勘井開工
2018/1/3 14:30:00 - 全國環境輻射即時監測站107年起再增一站,計47站監測資訊即時網路公開
2018/1/3 14:20:12 - Taishan schedule factors in commissioning tests
2018/1/3 14:09:26 - New Rostov reactor starts up
2018/1/3 14:05:54 - Tianwan 3 starts supplying electricity to grid
2017/12/27 15:50:43 - 原能會今(26)日公開「國際核能安全公約中華民國國家報告」
2017/12/27 15:35:32 - 能源轉型 台電推動興達電廠燃氣機組更新計畫 2023年供電
2017/12/27 15:31:11 - Georgia Commission Gives Conditional Go-Ahead For Completion Of Vogtle-3 And -4

 線上期刊目錄

 瀏覽人數
今天: 31
昨天: 87
本月: 2372
總計: 511078

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw