國際核能現況 : Taishan schedule factors in commissioning tests
發表人 nicenter 於 2018/1/3 14:20:12 (85 人讀取)

The Taishan 1 EPR has finished the hot functional tests of its commissioning and will be the first EPR to operate, owner Chine General Nuclear (CGN) announced to the Hong Kong stock exchange. However, being first meant extra tests are required and this prevented Taishan 1 from starting up at the end of 2017, the company said.




An announcement by CGN in August 2017 held that Taishan 1 would begin commercial operation and routine supply of electricity before the end of the year. On 29 December the company updated this: "As no nuclear power generating unit with EPR technology has been put into commercial operation across the world ... [the construction project company has to] conduct more experimental verifications in respect of the design and equipmentm which accordingly requires longer engineering construction time."


Taishan 1 was the third EPR unit to begin construction, in November 2009. It followed Finland's Olkiluoto 3 in August 2005 and France's Flamanville 3 in December 2007. Those units are at similar levels of development - Olkiluoto 3 began hot functional tests last month, while Flamanville 3 is at the earlier stage of cold tests.




Taishan 1 (Image: CGN)

CGN said it had "conducted a comprehensive evaluation on subsequent engineering contruction plans and relevant risks and, after due consideration, decided to adjust the constrution plan."


"Accordingly, it is expected commercial operation of Taishan 1 and Taishan 2 will commence in 2018 and 2019 respectively," said CGN. Taishan 2 is in the equipment installation phase.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Taishan-schedule-factors-in-commissioning-tests-0201181.html



其他新聞
2018/7/16 10:00:56 - WANO completes reviews of Leningrad and Tianwan plants
2018/7/16 9:57:23 - Yangjiang 5 enters commercial operation
2018/7/16 9:46:00 - ‘Breakthrough’ For Bulgaria As €31M Plasma Melting Plant Begins Operations At Kozloduy Nuclear Station
2018/7/16 9:43:19 - European Court Dismisses Austria’s Objections To Hinkley Point C
2018/7/13 10:22:08 - Austrian case against Hinkley Point C aid rejected
2018/7/13 10:19:37 - UK's post-Brexit nuclear plans face scrutiny
2018/7/13 10:13:34 - 輻射監測生力軍!石門水庫、清華大學環境輻射監測站正式上線
2018/7/13 10:06:30 - 核三廠1號機預定於7月15日降載例行測試,原能會持續監控電廠運轉安全
2018/7/9 10:51:40 - Think-tanks call for states to adopt Clean Energy Standards
2018/7/9 10:49:29 - EDF maintains plant safety is a priority
2018/7/9 10:47:06 - NEI issues guidelines for regulatory interactions
2018/7/6 12:09:34 - 核二廠2號機於今(6)日降載進行例行測試,原能會持續監控電廠運轉安全(更新)
2018/7/6 12:08:15 - 核二廠2號機預定於7月7日降載例行測試,原能會持續監控電廠運轉安全
2018/7/4 10:08:53 - Boss launches Honeymoon restart strategy
2018/7/4 10:04:16 - NDA to take over management of Magnox sites
2018/7/4 9:58:23 - Japanese Cabinet approves new basic energy plan
2018/7/4 9:50:06 - 今(04)日04時10分台東縣政府北方規模4.6有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/7/4 9:42:18 - 核二廠1號機反應器圍阻體廠房氣體流程輻射監測器發出警戒訊號之說明
2018/7/2 10:44:58 - China's Taishan 1 reactor connected to grid
2018/7/2 10:40:05 - Bruce Power and ITM to supply cancer therapy isotope

 線上期刊目錄

 瀏覽人數
今天: 5
昨天: 158
本月: 2645
總計: 530872

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw