logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 日本福島核災專區
* 相關資訊
國際核能現況 : Taishan schedule factors in commissioning tests
發表人 nicenter 於 2018/1/3 14:20:12 (66 人讀取)

The Taishan 1 EPR has finished the hot functional tests of its commissioning and will be the first EPR to operate, owner Chine General Nuclear (CGN) announced to the Hong Kong stock exchange. However, being first meant extra tests are required and this prevented Taishan 1 from starting up at the end of 2017, the company said.




An announcement by CGN in August 2017 held that Taishan 1 would begin commercial operation and routine supply of electricity before the end of the year. On 29 December the company updated this: "As no nuclear power generating unit with EPR technology has been put into commercial operation across the world ... [the construction project company has to] conduct more experimental verifications in respect of the design and equipmentm which accordingly requires longer engineering construction time."


Taishan 1 was the third EPR unit to begin construction, in November 2009. It followed Finland's Olkiluoto 3 in August 2005 and France's Flamanville 3 in December 2007. Those units are at similar levels of development - Olkiluoto 3 began hot functional tests last month, while Flamanville 3 is at the earlier stage of cold tests.




Taishan 1 (Image: CGN)

CGN said it had "conducted a comprehensive evaluation on subsequent engineering contruction plans and relevant risks and, after due consideration, decided to adjust the constrution plan."


"Accordingly, it is expected commercial operation of Taishan 1 and Taishan 2 will commence in 2018 and 2019 respectively," said CGN. Taishan 2 is in the equipment installation phase.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Taishan-schedule-factors-in-commissioning-tests-0201181.html



其他新聞
2018/4/20 14:20:00 - 台電回應綠色和平,深澳對pm2.5的貢獻度最多0.08~0.18%,不知「相當於160萬輛汽車」的推估是從何而來?
2018/4/20 14:11:05 - 大潭電廠新增機組輸電線路變更 降低環境衝擊 依法提出環差申請
2018/4/20 14:07:49 - IAEA tests drone to fight disease-carrying mosquitos
2018/4/20 14:05:39 - Canada considers participation in Iter fusion project
2018/4/18 15:20:00 - 還原瑞芳保育區爭議的真相,台電籲請外界回歸事實討論
2018/4/18 15:18:00 - 台電深澳超超臨界計畫空品影響不到法規萬分之一 不會有許厝國小第2
2018/4/18 15:13:38 - AEM Technology sees milestone with first VVER-TOI
2018/4/18 15:10:12 - Report highlights impact of US nuclear plant closures
2018/4/18 15:04:37 - India, USA to collaborate on neutrino science
2018/4/11 15:10:00 - 台電簽署離岸風電第三方驗證合作備忘錄 為健全綠色金融環境助力
2018/4/11 15:08:23 - 原能會已設立「核二廠2號機再起動」專區,持續公開管制資訊
2018/4/11 15:03:05 - Council formed to support Canadian isotope production
2018/4/11 14:56:44 - Final Barakah dome complete
2018/3/30 14:47:16 - 今(29)日8時17分南投地區規模4.8有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/3/30 14:46:01 - 地熱發電國家隊首部曲 台電與中油簽MOU開發宜蘭地熱
2018/3/30 14:26:54 - FirstEnergy gives notice to deactivate four units
2018/3/30 14:17:55 - Darlington refurbishment achieves new milestone
2018/3/30 14:13:35 - Court approves Westinghouse reorganisation plan
2018/3/28 15:02:51 - 因應能源轉型 積極面對核四資產處理 台電:採影響最小化
2018/3/28 14:30:22 - Czech new build financing decision by mid-year

 線上期刊目錄

 瀏覽人數
今天: 35
昨天: 101
本月: 1992
總計: 519362

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw