國際核能現況 : Taishan schedule factors in commissioning tests
發表人 nicenter 於 2018/1/3 14:20:12 (19 人讀取)

The Taishan 1 EPR has finished the hot functional tests of its commissioning and will be the first EPR to operate, owner Chine General Nuclear (CGN) announced to the Hong Kong stock exchange. However, being first meant extra tests are required and this prevented Taishan 1 from starting up at the end of 2017, the company said.




An announcement by CGN in August 2017 held that Taishan 1 would begin commercial operation and routine supply of electricity before the end of the year. On 29 December the company updated this: "As no nuclear power generating unit with EPR technology has been put into commercial operation across the world ... [the construction project company has to] conduct more experimental verifications in respect of the design and equipmentm which accordingly requires longer engineering construction time."


Taishan 1 was the third EPR unit to begin construction, in November 2009. It followed Finland's Olkiluoto 3 in August 2005 and France's Flamanville 3 in December 2007. Those units are at similar levels of development - Olkiluoto 3 began hot functional tests last month, while Flamanville 3 is at the earlier stage of cold tests.




Taishan 1 (Image: CGN)

CGN said it had "conducted a comprehensive evaluation on subsequent engineering contruction plans and relevant risks and, after due consideration, decided to adjust the constrution plan."


"Accordingly, it is expected commercial operation of Taishan 1 and Taishan 2 will commence in 2018 and 2019 respectively," said CGN. Taishan 2 is in the equipment installation phase.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Taishan-schedule-factors-in-commissioning-tests-0201181.html



其他新聞
2018/1/19 14:48:08 - 新北市將停發生煤許可 台電:超超臨界燃煤機組排放接近燃氣排放標準 可兼顧供電與環保
2018/1/19 14:46:08 - 今(17)日台北市北投區發生之有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/1/19 14:45:13 - Toshiba agrees sale of Westinghouse claims
2018/1/19 14:44:05 - Mining resumes at WIPP
2018/1/19 14:37:41 - EDF Energy expects 20% cost saving for Sizewell C
2018/1/17 14:15:15 - Lift nuclear ban, MCA tells Australian government
2018/1/17 14:09:56 - Steam generators installed at second Belarus unit
2018/1/17 14:08:03 - Regulator checks Rostov 4 ahead of start-up
2018/1/10 14:34:19 - 原能會已完成「核子事故常識及其防護」文宣,歡迎下載使用
2018/1/10 14:28:07 - Decommissioning progress for unique Canadian reactor
2018/1/10 14:25:02 - FERC starts new grid resilience proceeding
2018/1/10 14:20:38 - Flamanville EPR completes key pre-operational tests
2018/1/3 14:31:29 - 綠島邁向綠能島 台電首座地熱試驗探勘井開工
2018/1/3 14:30:00 - 全國環境輻射即時監測站107年起再增一站,計47站監測資訊即時網路公開
2018/1/3 14:20:12 - Taishan schedule factors in commissioning tests
2018/1/3 14:09:26 - New Rostov reactor starts up
2018/1/3 14:05:54 - Tianwan 3 starts supplying electricity to grid
2017/12/27 15:50:43 - 原能會今(26)日公開「國際核能安全公約中華民國國家報告」
2017/12/27 15:35:32 - 能源轉型 台電推動興達電廠燃氣機組更新計畫 2023年供電
2017/12/27 15:31:11 - Georgia Commission Gives Conditional Go-Ahead For Completion Of Vogtle-3 And -4

 線上期刊目錄

 瀏覽人數
今天: 31
昨天: 87
本月: 2372
總計: 511078

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw