logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 日本福島核災專區
* 相關資訊
國際核能現況 : Tianwan 3 starts supplying electricity to grid
發表人 nicenter 於 2018/1/3 14:05:54 (22 人讀取)

Unit 3 of the Tianwan nuclear power plant in China's Jiangsu province was connected to the grid on 30 December. The Russian-supplied VVER-1000 is scheduled to enter commercial operation later this year.





Tianwan unit 3 (Image: CNNC)

Tianwan 3 and 4 are AES-91 VVER-1000 units designed by Gidropress and supplied by Russian state nuclear company Rosatom. AtomStroyExport is the main contractor, supplying the nuclear island. First concrete for unit 3 was poured in December 2012, while construction of unit 4 began in September 2013. Two similar VVER-1000 reactors (units 1 and 2) began operating at the site in 2007.


The process to load a total of 163 fuel assemblies into the core of Tianwan 3 got under way on 18 August. The start-up process began on 27 September, with the reactor achieving criticality two days later.


Following permission from the Chinese regulator, power at Tianwan 3 was raised to 25% of capacity, after which the turbine was brought into operation and electrical tests of the field and power delivery systems were carried out. This process was completed at 1.29pm on 30 December, Rosatom noted. "Power unit 3 was, thereby, connected to the grid. All systems performed in normal operational mode."


Power output from the reactor will now be maintained at 25%. Dynamic tests will later be performed at 50%, 75% and 100% of capacity. Upon completion of initial testing at full thermal capacity, demonstration operation will proceed at nominal capacity for 100 hours, after which preliminary acceptance procedures will follow. Preliminary acceptance is the starting point of a two-year warranty period for the operation of Tianwan 3. The unit is scheduled to enter commercial operation later this year.


"Construction of the third and fourth power units of the Tianwan nuclear power plant are being implemented in record-breaking time and can be considered examples of excellent international cooperation in the energy field," said Kirill Komarov, Rosatom's first deputy director-general for corporate development and international business."


The State Council gave its approval for the third phase of the Tianwan plant (units 5 and 6) - both featuring Chinese-designed 1080 MWe ACPR1000 reactors - on 16 December 2015. First safety-related concrete was poured for unit 5 later that month and for unit 6 in September 2016. Unit 5 is expected to enter commercial operation in December 2020 and unit 6 in October 2021.


The Tianwan plant is owned and operated by Jiangsu Nuclear Power Corporation, a joint venture between China National Nuclear Corporation (50%), China Power Investment Corporation (30%) and Jiangsu Guoxin Group (20%).


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Tianwan-3-starts-supplying-electricity-to-grid-0201185.html



其他新聞
2018/1/19 14:48:08 - 新北市將停發生煤許可 台電:超超臨界燃煤機組排放接近燃氣排放標準 可兼顧供電與環保
2018/1/19 14:46:08 - 今(17)日台北市北投區發生之有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/1/19 14:45:13 - Toshiba agrees sale of Westinghouse claims
2018/1/19 14:44:05 - Mining resumes at WIPP
2018/1/19 14:37:41 - EDF Energy expects 20% cost saving for Sizewell C
2018/1/17 14:15:15 - Lift nuclear ban, MCA tells Australian government
2018/1/17 14:09:56 - Steam generators installed at second Belarus unit
2018/1/17 14:08:03 - Regulator checks Rostov 4 ahead of start-up
2018/1/10 14:34:19 - 原能會已完成「核子事故常識及其防護」文宣,歡迎下載使用
2018/1/10 14:28:07 - Decommissioning progress for unique Canadian reactor
2018/1/10 14:25:02 - FERC starts new grid resilience proceeding
2018/1/10 14:20:38 - Flamanville EPR completes key pre-operational tests
2018/1/3 14:31:29 - 綠島邁向綠能島 台電首座地熱試驗探勘井開工
2018/1/3 14:30:00 - 全國環境輻射即時監測站107年起再增一站,計47站監測資訊即時網路公開
2018/1/3 14:20:12 - Taishan schedule factors in commissioning tests
2018/1/3 14:09:26 - New Rostov reactor starts up
2018/1/3 14:05:54 - Tianwan 3 starts supplying electricity to grid
2017/12/27 15:50:43 - 原能會今(26)日公開「國際核能安全公約中華民國國家報告」
2017/12/27 15:35:32 - 能源轉型 台電推動興達電廠燃氣機組更新計畫 2023年供電
2017/12/27 15:31:11 - Georgia Commission Gives Conditional Go-Ahead For Completion Of Vogtle-3 And -4

 線上期刊目錄

 瀏覽人數
今天: 31
昨天: 87
本月: 2372
總計: 511078

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw