國際核能現況 : Tianwan 3 starts supplying electricity to grid
發表人 nicenter 於 2018/1/3 14:05:54 (79 人讀取)

Unit 3 of the Tianwan nuclear power plant in China's Jiangsu province was connected to the grid on 30 December. The Russian-supplied VVER-1000 is scheduled to enter commercial operation later this year.





Tianwan unit 3 (Image: CNNC)

Tianwan 3 and 4 are AES-91 VVER-1000 units designed by Gidropress and supplied by Russian state nuclear company Rosatom. AtomStroyExport is the main contractor, supplying the nuclear island. First concrete for unit 3 was poured in December 2012, while construction of unit 4 began in September 2013. Two similar VVER-1000 reactors (units 1 and 2) began operating at the site in 2007.


The process to load a total of 163 fuel assemblies into the core of Tianwan 3 got under way on 18 August. The start-up process began on 27 September, with the reactor achieving criticality two days later.


Following permission from the Chinese regulator, power at Tianwan 3 was raised to 25% of capacity, after which the turbine was brought into operation and electrical tests of the field and power delivery systems were carried out. This process was completed at 1.29pm on 30 December, Rosatom noted. "Power unit 3 was, thereby, connected to the grid. All systems performed in normal operational mode."


Power output from the reactor will now be maintained at 25%. Dynamic tests will later be performed at 50%, 75% and 100% of capacity. Upon completion of initial testing at full thermal capacity, demonstration operation will proceed at nominal capacity for 100 hours, after which preliminary acceptance procedures will follow. Preliminary acceptance is the starting point of a two-year warranty period for the operation of Tianwan 3. The unit is scheduled to enter commercial operation later this year.


"Construction of the third and fourth power units of the Tianwan nuclear power plant are being implemented in record-breaking time and can be considered examples of excellent international cooperation in the energy field," said Kirill Komarov, Rosatom's first deputy director-general for corporate development and international business."


The State Council gave its approval for the third phase of the Tianwan plant (units 5 and 6) - both featuring Chinese-designed 1080 MWe ACPR1000 reactors - on 16 December 2015. First safety-related concrete was poured for unit 5 later that month and for unit 6 in September 2016. Unit 5 is expected to enter commercial operation in December 2020 and unit 6 in October 2021.


The Tianwan plant is owned and operated by Jiangsu Nuclear Power Corporation, a joint venture between China National Nuclear Corporation (50%), China Power Investment Corporation (30%) and Jiangsu Guoxin Group (20%).


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Tianwan-3-starts-supplying-electricity-to-grid-0201185.html



其他新聞
2018/4/20 14:20:00 - 台電回應綠色和平,深澳對pm2.5的貢獻度最多0.08~0.18%,不知「相當於160萬輛汽車」的推估是從何而來?
2018/4/20 14:11:05 - 大潭電廠新增機組輸電線路變更 降低環境衝擊 依法提出環差申請
2018/4/20 14:07:49 - IAEA tests drone to fight disease-carrying mosquitos
2018/4/20 14:05:39 - Canada considers participation in Iter fusion project
2018/4/18 15:20:00 - 還原瑞芳保育區爭議的真相,台電籲請外界回歸事實討論
2018/4/18 15:18:00 - 台電深澳超超臨界計畫空品影響不到法規萬分之一 不會有許厝國小第2
2018/4/18 15:13:38 - AEM Technology sees milestone with first VVER-TOI
2018/4/18 15:10:12 - Report highlights impact of US nuclear plant closures
2018/4/18 15:04:37 - India, USA to collaborate on neutrino science
2018/4/11 15:10:00 - 台電簽署離岸風電第三方驗證合作備忘錄 為健全綠色金融環境助力
2018/4/11 15:08:23 - 原能會已設立「核二廠2號機再起動」專區,持續公開管制資訊
2018/4/11 15:03:05 - Council formed to support Canadian isotope production
2018/4/11 14:56:44 - Final Barakah dome complete
2018/3/30 14:47:16 - 今(29)日8時17分南投地區規模4.8有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/3/30 14:46:01 - 地熱發電國家隊首部曲 台電與中油簽MOU開發宜蘭地熱
2018/3/30 14:26:54 - FirstEnergy gives notice to deactivate four units
2018/3/30 14:17:55 - Darlington refurbishment achieves new milestone
2018/3/30 14:13:35 - Court approves Westinghouse reorganisation plan
2018/3/28 15:02:51 - 因應能源轉型 積極面對核四資產處理 台電:採影響最小化
2018/3/28 14:30:22 - Czech new build financing decision by mid-year

 線上期刊目錄

 瀏覽人數
今天: 35
昨天: 101
本月: 1992
總計: 519362

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw