國際核能現況 : Georgia Commission Gives Conditional Go-Ahead For Completion Of Vogtle-3 And -4
發表人 nicenter 於 2017/12/27 15:31:11 (134 人讀取)



22 Dec (NucNet): Georgia’s Public Service Commission has approved Georgia Power’s plans to complete the Vogtle-3 and -4 nuclear units whose future had been under threat because of cost overruns and the bankruptcy in the US of reactor supplier Westinghouse. Georgia Power said in a statement on 21 December 2017 that the PSC had voted unanimously to allow construction to continue after “months of review and evaluation”. PSC chairman Stan Wise said the decision came down to the importance of fuel diversity and the long term benefits the project would have. But he said approval was conditional on Congress approving roughly $800m (€675m) worth of tax credits for the project. Media reports said senators began laying the groundwork for approving the tax credits on Wednesday afternoon, when the finance committee introduced legislation that would effectively guarantee the $23bn project the credits. The two AP1000 units will be the nation's first new nuclear units in 30 years. The new units are co-owned by Georgia Power, Oglethorpe Power, MEAG Power and Dalton Utilities and are the only new nuclear units under construction in the US. Georgia Power said Vogtle-3 is expected online in November 2021 and Vogtle-4 in November 2022. Paul Bowers, chairman, president and CEO of Georgia Power said the PSC had shown leadership in making “this complex and difficult decision”. In August 2017 the units’ owners recommended to the PSC that construction continue. They said the recommendation was based on the results of a comprehensive schedule, cost and cancellation assessment that was prompted by the bankruptcy of former primary Vogtle contractor Westinghouse in March 2017.

Related reports in the NucNet database (available to subscribers):
Vogtle AP1000 Project ‘No Longer Economic’, Says PSC Staff Report (News in Brief No.243, 06 December 2017)
Source:

NucNet

Editor:

David Dalton

© NucNet a.s.b.l Brussels, Belgium

source:https://www.nucnet.org/all-the-news/2017/12/22/georgia-commission-gives-conditional-go-ahead-for-completion-of-vogtle-3-and-4



其他新聞
2018/12/7 10:41:45 - Nuclear important to sustainable energy mix, says UNECE report
2018/12/7 10:40:07 - First Taiwanese reactor to enter decommissioning
2018/12/7 10:31:03 - Russia completes testing of modified VVER-440 fuel
2018/12/7 10:30:00 - 核一廠1號機於107年12月6日進入除役期間,原能會將嚴格監督台電公司落實除役計畫及安全要求
2018/12/7 10:29:55 - Russia and Rwanda to cooperate in nuclear power
2018/12/7 10:20:00 - 核一廠1號機執照屆滿依法停機 待取得除役許可正式啟動除役
2018/12/7 10:19:17 - 回應新北市府指核一乾貯未按圖施工 台電:配合地形調整減少開挖 盼與市府再溝通
2018/12/5 9:56:19 - Argentina, Russia expand nuclear energy cooperation
2018/12/5 9:53:07 - Lawsuit launched as Bellefonte sale falters
2018/12/5 9:51:20 - CNNC launches R&D centre for fuels and materials
2018/12/5 9:48:24 - Nuclear must remain in South African mix, committee finds
2018/12/5 9:44:27 - UK's Bradwell site enters care and maintenance
2018/12/5 9:32:07 - 放射性物質或可發生游離輻射設備銷售服務業者名單
2018/12/3 10:51:18 - US companies collaborate on TRISO fuel facility
2018/12/3 10:49:38 - Amano calls for nuclear technology to go 'mainstream'
2018/12/3 10:48:11 - Russia starts cobalt-60 production at Kursk plant
2018/12/3 10:42:32 - Saskatchewan files suit over mine remediation costs
2018/12/3 9:25:36 - 原能會於今(2)日18時10分同意台電公司核二廠1號機併聯申請
2018/11/30 9:38:48 - New delay in start-up of Finnish EPR
2018/11/30 9:36:30 - Europe aims to be carbon neutral by 2050

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw