logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 日本福島核災專區
* 相關資訊
國際核能現況 : Hot functional tests begin at Finnish EPR
發表人 nicenter 於 2017/12/20 16:17:54 (18 人讀取)

Finnish utility Teollisuuden Voima Oyj (TVO) announced today that hot functional tests have started at the first-of-a-kind EPR unit at Olkiluoto. These key pre-operational tests ensure coolant circuits and nuclear safety systems are functioning properly before fuel is loaded.





The Olkiluoto EPR, pictured in September 2016 (Image: TVO)

"This is the first plant-level test where the nuclear island and the turbine island are operated together as a whole," TVO noted. "Several different tests at different pressure levels will be carried out during this stage. The water temperature is raised utilising the thermal energy produced by the reactor coolant pumps."


Cold functional tests - which are carried out to confirm whether components and systems important to safety are properly installed and ready to operate in a cold condition - began at Olkiluoto 3 (OL3) in June and took about four weeks to complete. The main purpose of these tests is to verify the leak-tightness of the primary circuit.


"After successful completion of the hot functional tests, it will be possible to obtain an operating licence for OL3 and continue the project towards nuclear commissioning," the company said.


The consortium of Areva GmbH, Areva NP SAS and Siemens AG began construction of Olkiluoto 3 in 2005 under a turnkey contract signed with TVO in late 2003. Completion of the 1600 MWe reactor was originally scheduled for 2009, but the project has suffered various delays and setbacks.


In October, the schedule for OL3 commencing regular electricity production was again revised from the end of 2018 to May 2019.


No counterfeit components



No parts have been used in the Olkiluoto EPR that "could endanger the safety of the plant due to uncertainties about their manufacturing history", the Finnish Radiation and Nuclear Safety Authority (Stuk) has concluded.


In May 2016, the French nuclear safety regulator said an ongoing quality audit at Areva's Le Creusot forge - which Areva bought in 2006 - had identified "irregularities" in paperwork on some 400 plant components produced there since 1965.


The following month, Stuk requested utilities Fortum and TVO investigate whether equipment whose material quality cannot be fully guaranteed had been supplied by the forge to their nuclear power units. TVO submitted its final report on the investigation into parts used in OL3 to Stuk on 16 November.


Stuk has now confirmed that the investigation into OL3 is complete and that TVO's inspections and investigations have "determined the quality of the materials used in the parts with sufficient certainty".


Investigations into components used in Finland's operating plants - Loviisa units 1 and 2 and Olkiluoto 1 and 2 - have also found that no parts with inadequate or counterfeited documentation have been supplied by Areva.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Hot-functional-tests-begin-at-Finnish-EPR-1912174.html



其他新聞
2018/1/19 14:48:08 - 新北市將停發生煤許可 台電:超超臨界燃煤機組排放接近燃氣排放標準 可兼顧供電與環保
2018/1/19 14:46:08 - 今(17)日台北市北投區發生之有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/1/19 14:45:13 - Toshiba agrees sale of Westinghouse claims
2018/1/19 14:44:05 - Mining resumes at WIPP
2018/1/19 14:37:41 - EDF Energy expects 20% cost saving for Sizewell C
2018/1/17 14:15:15 - Lift nuclear ban, MCA tells Australian government
2018/1/17 14:09:56 - Steam generators installed at second Belarus unit
2018/1/17 14:08:03 - Regulator checks Rostov 4 ahead of start-up
2018/1/10 14:34:19 - 原能會已完成「核子事故常識及其防護」文宣,歡迎下載使用
2018/1/10 14:28:07 - Decommissioning progress for unique Canadian reactor
2018/1/10 14:25:02 - FERC starts new grid resilience proceeding
2018/1/10 14:20:38 - Flamanville EPR completes key pre-operational tests
2018/1/3 14:31:29 - 綠島邁向綠能島 台電首座地熱試驗探勘井開工
2018/1/3 14:30:00 - 全國環境輻射即時監測站107年起再增一站,計47站監測資訊即時網路公開
2018/1/3 14:20:12 - Taishan schedule factors in commissioning tests
2018/1/3 14:09:26 - New Rostov reactor starts up
2018/1/3 14:05:54 - Tianwan 3 starts supplying electricity to grid
2017/12/27 15:50:43 - 原能會今(26)日公開「國際核能安全公約中華民國國家報告」
2017/12/27 15:35:32 - 能源轉型 台電推動興達電廠燃氣機組更新計畫 2023年供電
2017/12/27 15:31:11 - Georgia Commission Gives Conditional Go-Ahead For Completion Of Vogtle-3 And -4

 線上期刊目錄

 瀏覽人數
今天: 31
昨天: 87
本月: 2372
總計: 511078

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw