國際核能現況 : Hot functional tests begin at Finnish EPR
發表人 nicenter 於 2017/12/20 16:17:54 (96 人讀取)

Finnish utility Teollisuuden Voima Oyj (TVO) announced today that hot functional tests have started at the first-of-a-kind EPR unit at Olkiluoto. These key pre-operational tests ensure coolant circuits and nuclear safety systems are functioning properly before fuel is loaded.





The Olkiluoto EPR, pictured in September 2016 (Image: TVO)

"This is the first plant-level test where the nuclear island and the turbine island are operated together as a whole," TVO noted. "Several different tests at different pressure levels will be carried out during this stage. The water temperature is raised utilising the thermal energy produced by the reactor coolant pumps."


Cold functional tests - which are carried out to confirm whether components and systems important to safety are properly installed and ready to operate in a cold condition - began at Olkiluoto 3 (OL3) in June and took about four weeks to complete. The main purpose of these tests is to verify the leak-tightness of the primary circuit.


"After successful completion of the hot functional tests, it will be possible to obtain an operating licence for OL3 and continue the project towards nuclear commissioning," the company said.


The consortium of Areva GmbH, Areva NP SAS and Siemens AG began construction of Olkiluoto 3 in 2005 under a turnkey contract signed with TVO in late 2003. Completion of the 1600 MWe reactor was originally scheduled for 2009, but the project has suffered various delays and setbacks.


In October, the schedule for OL3 commencing regular electricity production was again revised from the end of 2018 to May 2019.


No counterfeit components



No parts have been used in the Olkiluoto EPR that "could endanger the safety of the plant due to uncertainties about their manufacturing history", the Finnish Radiation and Nuclear Safety Authority (Stuk) has concluded.


In May 2016, the French nuclear safety regulator said an ongoing quality audit at Areva's Le Creusot forge - which Areva bought in 2006 - had identified "irregularities" in paperwork on some 400 plant components produced there since 1965.


The following month, Stuk requested utilities Fortum and TVO investigate whether equipment whose material quality cannot be fully guaranteed had been supplied by the forge to their nuclear power units. TVO submitted its final report on the investigation into parts used in OL3 to Stuk on 16 November.


Stuk has now confirmed that the investigation into OL3 is complete and that TVO's inspections and investigations have "determined the quality of the materials used in the parts with sufficient certainty".


Investigations into components used in Finland's operating plants - Loviisa units 1 and 2 and Olkiluoto 1 and 2 - have also found that no parts with inadequate or counterfeited documentation have been supplied by Areva.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Hot-functional-tests-begin-at-Finnish-EPR-1912174.html



其他新聞
2018/7/16 10:00:56 - WANO completes reviews of Leningrad and Tianwan plants
2018/7/16 9:57:23 - Yangjiang 5 enters commercial operation
2018/7/16 9:46:00 - ‘Breakthrough’ For Bulgaria As €31M Plasma Melting Plant Begins Operations At Kozloduy Nuclear Station
2018/7/16 9:43:19 - European Court Dismisses Austria’s Objections To Hinkley Point C
2018/7/13 10:22:08 - Austrian case against Hinkley Point C aid rejected
2018/7/13 10:19:37 - UK's post-Brexit nuclear plans face scrutiny
2018/7/13 10:13:34 - 輻射監測生力軍!石門水庫、清華大學環境輻射監測站正式上線
2018/7/13 10:06:30 - 核三廠1號機預定於7月15日降載例行測試,原能會持續監控電廠運轉安全
2018/7/9 10:51:40 - Think-tanks call for states to adopt Clean Energy Standards
2018/7/9 10:49:29 - EDF maintains plant safety is a priority
2018/7/9 10:47:06 - NEI issues guidelines for regulatory interactions
2018/7/6 12:09:34 - 核二廠2號機於今(6)日降載進行例行測試,原能會持續監控電廠運轉安全(更新)
2018/7/6 12:08:15 - 核二廠2號機預定於7月7日降載例行測試,原能會持續監控電廠運轉安全
2018/7/4 10:08:53 - Boss launches Honeymoon restart strategy
2018/7/4 10:04:16 - NDA to take over management of Magnox sites
2018/7/4 9:58:23 - Japanese Cabinet approves new basic energy plan
2018/7/4 9:50:06 - 今(04)日04時10分台東縣政府北方規模4.6有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/7/4 9:42:18 - 核二廠1號機反應器圍阻體廠房氣體流程輻射監測器發出警戒訊號之說明
2018/7/2 10:44:58 - China's Taishan 1 reactor connected to grid
2018/7/2 10:40:05 - Bruce Power and ITM to supply cancer therapy isotope

 線上期刊目錄

 瀏覽人數
今天: 5
昨天: 158
本月: 2645
總計: 530872

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw