國際核能現況 : Next Vogtle hearings to begin
發表人 nicenter 於 2017/12/6 14:22:47 (109 人讀取)

The next stage of Georgia Public Service Commission (PSC) hearings on the Vogtle nuclear power plant construction project will begin on 11 December, in which the PSC will hear from public witnesses. It will also conduct a hearing on the testimony of its public interest advocacy staff who have recommended the project should only proceed if Georgia Power, rather than its customers, bear the risk for costs that the PSC deems to be unreasonable.







The hearings on Georgia Power's 16th Plant Construction Monitoring (VCM) report will take place in Atlanta, Georgia, and will continue as needed until 14 December. They follow hearings held in November, when Georgia Power CEO Paul Bowers said the owners of Vogtle 3 and 4 - Georgia Power, Oglethorpe Power, MEAG Power and Dalton Utilities - were unified in their recommendation to move forward with the project, which was filed in August. The recommendation was reached after a schedule, cost-to-complete and cancellation assessment was undertaken following contractor Westinghouse's Chapter 11 bankruptcy filing in March.


The PSC said yesterday that Georgia Power has asked it to consider two recommendations, the first one being to proceed with the project provided that the PSC agrees with certain conditions in the company's filing. The second, alternative, recommendation is to cancel the project should the PSC not adopt all the conditions for proceeding.


The PSC's public interest advocacy staff is responsible for representing the interests of ratepayers in the proceedings. In testimony filed on 1 December, it questioned the costs and economics of the project.


"Rather than approving the Company's request, Staff recommends the Project go forward only if the Commission modifies the Company's proposed conditions to: 1) ensure that completion is economic compared to cancellation, 2) provide an appropriate allocation of risks and costs between the Company and its customers, and 3) determine now that the costs identified as unreasonable by Staff be borne by the Company and its shareholders, or at the least ensure that unreasonable costs are not prematurely approved without an in-depth review of the prudence and reasonableness of actual costs after they are incurred," it said.


Under Georgia law, the PSC must within 180 days from the filing of the VCM verify and approve or disapprove expenditures made on the project, and approve or disapprove proposed revisions to forecast costs, schedules and configurations. After staff and intervenors present their testimony in the 11-14 December hearings, Georgia Power is scheduled to file its rebuttal testimony by 29 December and present that testimony on 8-10 January. According to the PSC's current schedule, it will issue its decision on 6 February, which is ahead of the statutory deadline of 27 February.


Work continues on the two AP1000 reactors under construction at the Vogtle site near Waynesboro, Georgia, with Bechtel managing daily construction efforts under the direction of Southern Nuclear. Vogtle unit 3 is currently expected to start commercial operation in November 2021 and unit 4 in November 2022.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Next-Vogtle-hearings-to-begin-0512177.html



其他新聞
2018/8/17 9:52:06 - SteaSteady growth in nuclear generation continuesdy growth in nuclear generation continues
2018/8/17 9:48:13 - FirstEnergy takes "unwelcome" step towards plant closures
2018/8/17 9:46:39 - Upgrades for Slovakian and Korean simulators
2018/8/17 9:44:28 - Nuclear aids New England energy security, say governors
2018/8/17 9:41:24 - NRC clears centrifuge plant decommissioning plan
2018/8/15 9:37:51 - Chinese AP1000 reaches full power operation
2018/8/15 9:35:29 - Public to comment on Hanford tunnel work
2018/8/15 9:30:49 - Chinese research reactor sets operational record
2018/8/15 9:26:52 - ENEC launches youth council
2018/8/15 9:22:04 - Waste package in place ahead of MSSS clearance
2018/8/13 9:42:09 - NNL, Wood contracted for nuclear fuel research
2018/8/13 9:36:48 - Safety review sought for new Japanese reactor
2018/8/13 9:34:22 - US agencies working on critical plant list
2018/8/13 9:28:20 - 全國首創「雙綠能電廠」 台電首座水上光電站大甲溪啟用
2018/8/10 9:51:46 - Call for UK government to back small nuclear projects
2018/8/10 9:37:07 - Fuqing 5 enters system commissioning phase
2018/8/10 9:34:28 - Progress at Vogtle, but cost forecast rises
2018/8/10 9:30:45 - Pickering relicensed to 2028
2018/8/10 9:20:00 - 台灣電力不足?台電重申無缺電問題 能源轉型兼顧穩供與環保
2018/8/8 11:15:18 - UK SMRs ‘Should Get Same Subsidies As Offshore Wind’, Says Independent Review

 線上期刊目錄

 友善連結

單位類

行政院原子能委員會
放射性物料管理局
核能研究所
國立清華大學工程與系統科學系
國立清華大學生醫工程與環境科學系
中華民國核能學會
財團法人核能科技協進會

新聞類


30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw