國際核能現況 : Russian floating plant cargo arrives at Pevek
發表人 nicenter 於 2017/11/1 14:58:51 (45 人讀取)

Ships carrying cargo to support "the world's first" floating nuclear power plant have arrived at the port of Pevek, in the Chukotka district of Russia, Rosenergoatom announced today. Rosenergoatom, the nuclear power plant operator subsidiary of Rosatom, also said the floating plant Akademik Lomonosov will be towed to Murmansk in May, be loaded with fuel in October and commissioned in November next year.





Akademik Lomonosov (Image: Rosenergoatom)

Currently moored at the Baltiysky Zavod shipyard in Saint Petersburg, Akademik Lomonosov houses two 35 MW KLT-40S nuclear reactors, similar to those used in Russia's nuclear-powered ice breakers.


By the end of this week, almost 10,000 tonnes of building materials, including sand, gravel and cement, will have arrived at Pevek from Arkhangelsk on the steam ships Kuznetsov and Sabetta. They are also carrying metal structures to support the construction of hydraulic systems and coastal infrastructure. Once the cargo has been unloaded, the materials will enable the schedule for Akademik Lomonosov to be met and provide a reserve for the entire inter-navigational period until 2018, Rosenergoatom said. A third vessel, the motor ship Mahmastal, was due to leave the port of Arkhangelsk for Pevek today with an additional batch of building materials.


The washing of the reactor circuit was completed at Akademik Lomonosov at the beginning of this month, which Rosenergoatom described as the final procedure that completes the assembly of the reactor and its subsystems. Testing of its systems and equipment according to its design parameters will continue until the end of this year, it added.


"The Akademik Lomonosov floating thermal nuclear power plant project is based on proven nuclear icebreaker technologies and is designed with a large safety margin, which makes nuclear reactors invulnerable to tsunamis and other natural disasters," the company said. "In addition, the nuclear processes on the ships meet all the requirements of the International Atomic Energy Agency and pose no threat to the environment," it added.


The plant is intended to replace the outgoing capacity of the Bilibino nuclear power plant in the Chukotka district. The first Bilibino unit is scheduled to be shut down in 2019 and the whole plant will be shut down in 2021.


Rosenergoatom also said that the floating nuclear power plant project received unanimous public support during discussions on the application for an operating licence held on 24 October.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Russian-floating-plant-cargo-arrives-at-Pevek-30101701.html



其他新聞
2018/2/2 15:53:20 - US commissioners call for action on used fuel
2018/2/2 15:50:58 - Russian president to connect Rostov 4
2018/2/2 15:34:07 - Hot testing of Sanmen 2 AP1000 completed
2018/1/31 14:16:24 - 中油桃園煉油廠輻射源現場檢查結果說明
2018/1/31 14:14:15 - 台電取得國內首張衛福部食品放射性檢驗機構認證 與國際知名檢測機構SGS合作 跨足食品放射性檢驗
2018/1/31 14:11:42 - Westinghouse extends Ukrainian fuel supply to 2025
2018/1/31 14:10:15 - NJ files new legislation recognising nuclear benefits
2018/1/26 17:04:34 - 兼顧供電與環保 台電持續配合空污降載
2018/1/19 14:48:08 - 新北市將停發生煤許可 台電:超超臨界燃煤機組排放接近燃氣排放標準 可兼顧供電與環保
2018/1/19 14:46:08 - 今(17)日台北市北投區發生之有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/1/19 14:45:13 - Toshiba agrees sale of Westinghouse claims
2018/1/19 14:44:05 - Mining resumes at WIPP
2018/1/19 14:37:41 - EDF Energy expects 20% cost saving for Sizewell C
2018/1/17 14:15:15 - Lift nuclear ban, MCA tells Australian government
2018/1/17 14:09:56 - Steam generators installed at second Belarus unit
2018/1/17 14:08:03 - Regulator checks Rostov 4 ahead of start-up
2018/1/10 14:34:19 - 原能會已完成「核子事故常識及其防護」文宣,歡迎下載使用
2018/1/10 14:28:07 - Decommissioning progress for unique Canadian reactor
2018/1/10 14:25:02 - FERC starts new grid resilience proceeding
2018/1/10 14:20:38 - Flamanville EPR completes key pre-operational tests

 線上期刊目錄

 瀏覽人數
今天: 149
昨天: 38
本月: 1576
總計: 513576

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw