國際核能現況 : Flushing Of Primary Systems Complete As World’s First Floating Nuclear Station Nears Completion In Russia
發表人 nicenter 於 2017/10/11 14:27:28 (11 人讀取)

10 Oct (NucNet): Flushing of the primary systems has been completed at the world’s first floating nuclear power station, the Akademik Lomonosov, which is under construction at Baltiysky Zavod JSC (the Baltic Shipyard) in St Petersburg, Russia, nuclear operator Rosenergoatom said on 9 October 2017.





Rosenergoatom said the operation was originally planned for November 2017 and had been completed ahead of schedule.

The flushing involves pumping demineralised water through the systems of both reactors to remove construction debris. It is the last step in building the primary systems.

In July 2017, Rosenergoatom said the facility was 96% complete.

The Akademik Lomonosov will be the first vessel of a proposed fleet of floating plants with small pressurised water reactor units that can provide energy, heat and water to remote and arid areas of the country.

The 21,000-tonne vessel will have two Russian-designed KLT-40S reactor units with an electrical power generating capacity of 35 MW each, sufficient for a city with a population of around 200,000 people.

The Akademik Lomonosov is scheduled for deployment at a site in the Arctic town of Pavek in Russia’s far northeast Chukotka region, where coastal infrastructure work began in October 2016.



source:http://www.nucnet.org/all-the-news/2017/10/10/flushing-of-primary-systems-complete-as-russia-s-first-floating-nuclear-station-nears-completion



其他新聞
2017/10/20 14:31:21 - 第三天然氣接收站是大潭增建機組供氣的唯一選擇
2017/10/20 14:20:51 - First Paks 2 Unit To Begin Commercial Operation In 2026, Hungary Official Tells Brussels Conference
2017/10/20 14:19:02 - Russia completes hot tests at Rostov 4
2017/10/20 14:16:48 - IAEA sees safety commitment at EDF's Bugey plant
2017/10/20 14:14:03 - Wide interest in small reactor plan, says CNL
2017/10/18 14:30:00 - 原能會對蘭嶼地區發現模擬低放射性廢棄物桶隨意棄置之處理說明
2017/10/18 14:27:54 - 106年10月16日蘭嶼地區發現模擬低放射性廢棄物桶隨意棄置之說明
2017/10/18 14:25:04 - South Africa Approves Environmental Impact Report For Eskom’s Duynefontein Nuclear Site
2017/10/18 14:24:22 - UK Announces Plans To Invest £460 Million In Nuclear Energy
2017/10/18 14:18:51 - WANO members 'consider challenges of the future'
2017/10/18 14:17:27 - NEI calls for reform to design certification process
2017/10/18 14:12:39 - Lightbridge fuel moves towards irradiation testing
2017/10/18 14:10:43 - Impact of Hanhikivi 1 licensing delay remains unclear
2017/10/13 14:36:56 - 原能會即時掌握北韓13日發生地震與發展
2017/10/13 14:35:50 - Foratom Calls For ‘Rapid Establishment’ Of Brexit Cooperation Agreement For Nuclear Industry
2017/10/13 14:34:08 - US group calls for SMR support
2017/10/13 14:32:43 - UK prepares legislation for Euratom exit
2017/10/13 14:30:27 - ASN gives final opinion on Flamanville EPR vessel
2017/10/11 14:32:48 - 台電「能源轉型」造型花車超吸睛 慶賀中華民國106歲生日快樂
2017/10/11 14:27:28 - Flushing Of Primary Systems Complete As World’s First Floating Nuclear Station Nears Completion In Russia

 線上期刊目錄

 瀏覽人數
今天: 58
昨天: 92
本月: 2039
總計: 502071

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw