logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 日本福島核災專區
* 相關資訊
國際核能現況 : Cernavodă Negotiations Continuing With China’s CGN, Says Nuclearelectrica
發表人 nicenter 於 2017/10/11 14:21:34 (32 人讀取)

Cernavodă Negotiations Continuing With China’s CGN, Says Nuclearelectrica

10 Oct (NucNet): Negotiations about the construction of two new units at the Cernavodă nuclear station in Romania are continuing between nuclear power operator Nuclearelectrica and China General Nuclear Power Corporation (CGN) with an initial deadline for their conclusion of around March 2018, Nuclearelectrica said on 9 October 2017. In August 2017, a general meeting of Nuclearelectrica shareholders approved the continuation of negotiations with CGN under conditions originally outlined in a memorandum of understanding signed in November 2015. The meeting approved negotiations for an additional six months and they resumed on 13 September 2017, Nuclearelectrica said. The negotiations include key issues such as the establishment of a project company and its initial capital structure, pre-project work, permits and authorisations, fuel supply and decommissioning. The Cernavodă nuclear station has two commercially operational Candu 6 pressurised heavy water reactors supplied by Atomic Energy of Canada Ltd and built under the supervision of a Canadian-Italian consortium of AECL and Ansaldo. Unit 1 began commercial operation in 1996, after work had been suspended on a further four units in 1991. Unit 2 was subsequently completed and began commercial operation in 2007. Efforts to resume work on Cernavoda-3 began in 2003, and a new project company, EnergoNuclear, was established in 2009 to oversee the completion of Cernavoda-3 and -4. Initial partners GDF Suez, CEZ, RWE Power, Iberdrola, Enel and ArcelorMittal Romania subsequently withdrew from the project during 2011-2013, and the company is currently 100% owned by Nuclearelectrica. On 28 September 2017, Nuclearelectrica shareholders approved the start of the first phase of a three-step refurbishment project for Cernavodă-1. The first phase, which will see the 650-MW (net) Candu 6 unit’s operating life extended beyond its original 210,000 equivalent full power hours, involves preparation of a feasibility study that will be presented to shareholders for approval in 2021. The actual implementation of the refurbishment project is scheduled for December 2026 to December 2028.



source:http://www.nucnet.org/all-the-news/2017/10/10/cernavod-negotiations-continuing-with-china-s-cgn-says-nuclearelectrica



其他新聞
2017/12/11 14:18:19 - 核二廠1號機預定於12月10日降載檢修非安全相關設備,原能會持續監控電廠運轉安全
2017/12/11 14:17:18 - 台中電廠新燃氣機組目標112年上路發電
2017/12/11 14:14:01 - UK fusion researchers welcome government support
2017/12/11 14:09:51 - US funds to support advanced nuclear technology development
2017/12/11 14:08:45 - Kepco named preferred bidder for UK's NuGen
2017/12/6 14:27:45 - 原能會謹訂於民國106年12月22日舉辦「核能電廠除役作業與管制規範」專題演講,歡迎報名參加。
2017/12/6 14:25:24 - Kazakhstan to cut uranium production
2017/12/6 14:23:45 - Russia readies for launch of Leningrad and Rostov units
2017/12/6 14:22:47 - Next Vogtle hearings to begin
2017/12/4 14:28:01 - 核三廠1號機預定於12月2日降載例行測試,原能會持續監控電廠運轉安全
2017/12/4 14:26:16 - 網傳買日本淘汰火力發電機組? 台電:不實謠言不排除對亂轉發者提告
2017/12/4 14:25:24 - Reactor vessel installed at Leningrad II-2
2017/12/4 14:24:04 - Decommissioning of Candu protoype moves forward
2017/12/4 14:08:43 - NEI files in support of New York ZEC programme
2017/11/29 14:24:10 - 106年11月27日藍莓相關食品抽樣之檢測結果
2017/11/29 14:21:06 - Governor Approves Restart Of Japan’s Ohi-3 And -4
2017/11/29 14:17:40 - UK, South Korea to extend nuclear cooperation
2017/11/29 14:13:04 - Russian and Brazilian firms to cooperate in nuclear power
2017/11/29 14:11:30 - EU's Energy Union becoming a reality, says Commission
2017/11/24 14:21:18 - 22日嘉義發生之有感地震及其餘震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全

 線上期刊目錄

 瀏覽人數
今天: 48
昨天: 78
本月: 832
總計: 506620

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw