logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 日本福島核災專區
* 相關資訊
國際核能現況 : Cernavodă Negotiations Continuing With China’s CGN, Says Nuclearelectrica
發表人 nicenter 於 2017/10/11 14:21:34 (11 人讀取)

Cernavodă Negotiations Continuing With China’s CGN, Says Nuclearelectrica

10 Oct (NucNet): Negotiations about the construction of two new units at the Cernavodă nuclear station in Romania are continuing between nuclear power operator Nuclearelectrica and China General Nuclear Power Corporation (CGN) with an initial deadline for their conclusion of around March 2018, Nuclearelectrica said on 9 October 2017. In August 2017, a general meeting of Nuclearelectrica shareholders approved the continuation of negotiations with CGN under conditions originally outlined in a memorandum of understanding signed in November 2015. The meeting approved negotiations for an additional six months and they resumed on 13 September 2017, Nuclearelectrica said. The negotiations include key issues such as the establishment of a project company and its initial capital structure, pre-project work, permits and authorisations, fuel supply and decommissioning. The Cernavodă nuclear station has two commercially operational Candu 6 pressurised heavy water reactors supplied by Atomic Energy of Canada Ltd and built under the supervision of a Canadian-Italian consortium of AECL and Ansaldo. Unit 1 began commercial operation in 1996, after work had been suspended on a further four units in 1991. Unit 2 was subsequently completed and began commercial operation in 2007. Efforts to resume work on Cernavoda-3 began in 2003, and a new project company, EnergoNuclear, was established in 2009 to oversee the completion of Cernavoda-3 and -4. Initial partners GDF Suez, CEZ, RWE Power, Iberdrola, Enel and ArcelorMittal Romania subsequently withdrew from the project during 2011-2013, and the company is currently 100% owned by Nuclearelectrica. On 28 September 2017, Nuclearelectrica shareholders approved the start of the first phase of a three-step refurbishment project for Cernavodă-1. The first phase, which will see the 650-MW (net) Candu 6 unit’s operating life extended beyond its original 210,000 equivalent full power hours, involves preparation of a feasibility study that will be presented to shareholders for approval in 2021. The actual implementation of the refurbishment project is scheduled for December 2026 to December 2028.



source:http://www.nucnet.org/all-the-news/2017/10/10/cernavod-negotiations-continuing-with-china-s-cgn-says-nuclearelectrica



其他新聞
2017/10/20 14:31:21 - 第三天然氣接收站是大潭增建機組供氣的唯一選擇
2017/10/20 14:20:51 - First Paks 2 Unit To Begin Commercial Operation In 2026, Hungary Official Tells Brussels Conference
2017/10/20 14:19:02 - Russia completes hot tests at Rostov 4
2017/10/20 14:16:48 - IAEA sees safety commitment at EDF's Bugey plant
2017/10/20 14:14:03 - Wide interest in small reactor plan, says CNL
2017/10/18 14:30:00 - 原能會對蘭嶼地區發現模擬低放射性廢棄物桶隨意棄置之處理說明
2017/10/18 14:27:54 - 106年10月16日蘭嶼地區發現模擬低放射性廢棄物桶隨意棄置之說明
2017/10/18 14:25:04 - South Africa Approves Environmental Impact Report For Eskom’s Duynefontein Nuclear Site
2017/10/18 14:24:22 - UK Announces Plans To Invest £460 Million In Nuclear Energy
2017/10/18 14:18:51 - WANO members 'consider challenges of the future'
2017/10/18 14:17:27 - NEI calls for reform to design certification process
2017/10/18 14:12:39 - Lightbridge fuel moves towards irradiation testing
2017/10/18 14:10:43 - Impact of Hanhikivi 1 licensing delay remains unclear
2017/10/13 14:36:56 - 原能會即時掌握北韓13日發生地震與發展
2017/10/13 14:35:50 - Foratom Calls For ‘Rapid Establishment’ Of Brexit Cooperation Agreement For Nuclear Industry
2017/10/13 14:34:08 - US group calls for SMR support
2017/10/13 14:32:43 - UK prepares legislation for Euratom exit
2017/10/13 14:30:27 - ASN gives final opinion on Flamanville EPR vessel
2017/10/11 14:32:48 - 台電「能源轉型」造型花車超吸睛 慶賀中華民國106歲生日快樂
2017/10/11 14:27:28 - Flushing Of Primary Systems Complete As World’s First Floating Nuclear Station Nears Completion In Russia

 線上期刊目錄

 瀏覽人數
今天: 58
昨天: 92
本月: 2039
總計: 502071

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw