國際核能現況 : Olkiluoto 3 commercial operation rescheduled
發表人 nicenter 於 2017/10/11 14:10:55 (45 人讀取)

Regular electricity production at Finland's Olkiluoto 3 is now expected to start in May 2019, the first-of-a-kind EPR unit's supplier consortium has told Finnish utility Teollisuuden Voima Oyj (TVO). Regular production had previously been scheduled to begin at the end of 2018.





Olkiluoto 3 (left) is sited next to TVO's two operating Olkiluoto units (Image: TVO)


TVO said the plant's supplier had been preparing a schedule review for the project completion "for some time". Work has now reached a stage where the supplier can confirm the main milestones, the company said. The previous schedule was provided in September 2014.


The latest schedule sees grid connection taking place in December 2018 with the start of regular electricity production in May 2019. The unit's ramp-up program will see it produce 2-4 TWh of electricity, at varying power levels between those dates.


TVO's Olkiluoto 3 (OL3) project director Jouni Silvennoinen said the company was "very disappointed" by the additional delay.


"There is still substantial work to be accomplished in the OL3 EPR project and it is essential that all the necessary technical, human and financial resources are allocated to the project. The restructuring of the French nuclear industry must not compromise this," he said.


Cold functional tests began at Olkiluoto 3 in June, with hot functional tests scheduled for later this year. TVO said that although the testing program was progressing many important tests remain to be carried out.


"Our objective remains the prompt completion of the OL3 EPR project. TVO continues to be committed to supporting the turn-key plant supplier," Silvennoinen said.


The consortium of Areva GmbH, Areva NP SAS and Siemens AG began construction of Olkiluoto 3 in 2005 under a turnkey contract signed with TVO in late 2003. Completion of the 1600 MWe reactor was originally scheduled for 2009, but the project has suffered various delays and setbacks.


TVO in September filed an appeal against the European Commission's approval for the French government to inject €4.5 billion ($5.4 billion) into Areva as part of the group's restructuring. TVO claimed the plan does not provide sufficient guarantees that the Olkiluoto 3 EPR project will be completed. Bernard Fontana, CEO of French engineering company Areva NP subsequently said that the Commission's approval in January had been made on the understanding there would be no changes to the Olkiluoto 3 project.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Olkiluoto-3-commercial-operation-rescheduled-0910177.html



其他新聞
2018/2/2 15:53:20 - US commissioners call for action on used fuel
2018/2/2 15:50:58 - Russian president to connect Rostov 4
2018/2/2 15:34:07 - Hot testing of Sanmen 2 AP1000 completed
2018/1/31 14:16:24 - 中油桃園煉油廠輻射源現場檢查結果說明
2018/1/31 14:14:15 - 台電取得國內首張衛福部食品放射性檢驗機構認證 與國際知名檢測機構SGS合作 跨足食品放射性檢驗
2018/1/31 14:11:42 - Westinghouse extends Ukrainian fuel supply to 2025
2018/1/31 14:10:15 - NJ files new legislation recognising nuclear benefits
2018/1/26 17:04:34 - 兼顧供電與環保 台電持續配合空污降載
2018/1/19 14:48:08 - 新北市將停發生煤許可 台電:超超臨界燃煤機組排放接近燃氣排放標準 可兼顧供電與環保
2018/1/19 14:46:08 - 今(17)日台北市北投區發生之有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/1/19 14:45:13 - Toshiba agrees sale of Westinghouse claims
2018/1/19 14:44:05 - Mining resumes at WIPP
2018/1/19 14:37:41 - EDF Energy expects 20% cost saving for Sizewell C
2018/1/17 14:15:15 - Lift nuclear ban, MCA tells Australian government
2018/1/17 14:09:56 - Steam generators installed at second Belarus unit
2018/1/17 14:08:03 - Regulator checks Rostov 4 ahead of start-up
2018/1/10 14:34:19 - 原能會已完成「核子事故常識及其防護」文宣,歡迎下載使用
2018/1/10 14:28:07 - Decommissioning progress for unique Canadian reactor
2018/1/10 14:25:02 - FERC starts new grid resilience proceeding
2018/1/10 14:20:38 - Flamanville EPR completes key pre-operational tests

 線上期刊目錄

 瀏覽人數
今天: 11
昨天: 82
本月: 1785
總計: 513785

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw