國際核能現況 : Olkiluoto 3 commercial operation rescheduled
發表人 nicenter 於 2017/10/11 14:10:55 (74 人讀取)

Regular electricity production at Finland's Olkiluoto 3 is now expected to start in May 2019, the first-of-a-kind EPR unit's supplier consortium has told Finnish utility Teollisuuden Voima Oyj (TVO). Regular production had previously been scheduled to begin at the end of 2018.





Olkiluoto 3 (left) is sited next to TVO's two operating Olkiluoto units (Image: TVO)


TVO said the plant's supplier had been preparing a schedule review for the project completion "for some time". Work has now reached a stage where the supplier can confirm the main milestones, the company said. The previous schedule was provided in September 2014.


The latest schedule sees grid connection taking place in December 2018 with the start of regular electricity production in May 2019. The unit's ramp-up program will see it produce 2-4 TWh of electricity, at varying power levels between those dates.


TVO's Olkiluoto 3 (OL3) project director Jouni Silvennoinen said the company was "very disappointed" by the additional delay.


"There is still substantial work to be accomplished in the OL3 EPR project and it is essential that all the necessary technical, human and financial resources are allocated to the project. The restructuring of the French nuclear industry must not compromise this," he said.


Cold functional tests began at Olkiluoto 3 in June, with hot functional tests scheduled for later this year. TVO said that although the testing program was progressing many important tests remain to be carried out.


"Our objective remains the prompt completion of the OL3 EPR project. TVO continues to be committed to supporting the turn-key plant supplier," Silvennoinen said.


The consortium of Areva GmbH, Areva NP SAS and Siemens AG began construction of Olkiluoto 3 in 2005 under a turnkey contract signed with TVO in late 2003. Completion of the 1600 MWe reactor was originally scheduled for 2009, but the project has suffered various delays and setbacks.


TVO in September filed an appeal against the European Commission's approval for the French government to inject €4.5 billion ($5.4 billion) into Areva as part of the group's restructuring. TVO claimed the plan does not provide sufficient guarantees that the Olkiluoto 3 EPR project will be completed. Bernard Fontana, CEO of French engineering company Areva NP subsequently said that the Commission's approval in January had been made on the understanding there would be no changes to the Olkiluoto 3 project.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Olkiluoto-3-commercial-operation-rescheduled-0910177.html



其他新聞
2018/6/15 15:27:03 - 端午連假豪雨報到 台電成立緊急應變中心待命
2018/6/15 15:14:42 - Nuclear Body Sounds Warning On Premature Shutdowns In France And Calls For ‘Renewal’ Of Nuclear Fleet
2018/6/15 15:13:41 - First yellowcake from seawater for US team
2018/6/15 15:11:29 - Start-up of Finnish EPR put back four months
2018/6/13 15:12:06 - 新機組陸續上線 台電:明年起備用維持15%以上 穩定供電無虞
2018/6/13 15:09:41 - 以最高標準要求安全,核二廠2號機因高壓輸電線路夾板溫度偏高之非機組因素,預定今(12)日晚上解聯調整
2018/6/13 15:04:17 - Jordan Abandons Nuclear Station Deal With Russia
2018/6/13 15:02:06 - Cooperation strengthens mining radiation protection
2018/6/13 14:58:59 - IAEA launches challenge on materials for fusion
2018/6/6 14:39:25 - 竹園超高壓變電所正式啟用 再提升竹科及新竹地區供電品質
2018/6/6 14:28:38 - 原能會今(5)日同意台電公司核二廠2號機急停後再起動
2018/6/6 14:27:30 - DOE announces funding for innovative nuclear technology
2018/6/6 14:25:29 - Tepco frees up Fukushima Daiichi fuel storage space
2018/6/6 14:24:23 - UK starts talks on public investment in nuclear power
2018/6/1 14:22:44 - 針對媒體評論「備轉容量率3%多是『電力供應充足』!」的回應說明
2018/6/1 14:20:00 - 「低放射性廢棄物貯存設施再評估報告審查導則草案」徵詢各界意見
2018/6/1 14:19:06 - Kansai cuts power rates as reactors restart
2018/6/1 14:16:45 - Toshiba scraps project to build ABWRs in Texas
2018/6/1 14:14:33 - US energy regulators back Illinois legislation
2018/5/30 14:20:00 - Barakah 1 start-up schedule revised for operator training

 線上期刊目錄

 瀏覽人數
今天: 33
昨天: 183
本月: 2905
總計: 526321

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw