logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 日本福島核災專區
* 相關資訊
國際核能現況 : Olkiluoto 3 commercial operation rescheduled
發表人 nicenter 於 2017/10/11 14:10:55 (32 人讀取)

Regular electricity production at Finland's Olkiluoto 3 is now expected to start in May 2019, the first-of-a-kind EPR unit's supplier consortium has told Finnish utility Teollisuuden Voima Oyj (TVO). Regular production had previously been scheduled to begin at the end of 2018.





Olkiluoto 3 (left) is sited next to TVO's two operating Olkiluoto units (Image: TVO)


TVO said the plant's supplier had been preparing a schedule review for the project completion "for some time". Work has now reached a stage where the supplier can confirm the main milestones, the company said. The previous schedule was provided in September 2014.


The latest schedule sees grid connection taking place in December 2018 with the start of regular electricity production in May 2019. The unit's ramp-up program will see it produce 2-4 TWh of electricity, at varying power levels between those dates.


TVO's Olkiluoto 3 (OL3) project director Jouni Silvennoinen said the company was "very disappointed" by the additional delay.


"There is still substantial work to be accomplished in the OL3 EPR project and it is essential that all the necessary technical, human and financial resources are allocated to the project. The restructuring of the French nuclear industry must not compromise this," he said.


Cold functional tests began at Olkiluoto 3 in June, with hot functional tests scheduled for later this year. TVO said that although the testing program was progressing many important tests remain to be carried out.


"Our objective remains the prompt completion of the OL3 EPR project. TVO continues to be committed to supporting the turn-key plant supplier," Silvennoinen said.


The consortium of Areva GmbH, Areva NP SAS and Siemens AG began construction of Olkiluoto 3 in 2005 under a turnkey contract signed with TVO in late 2003. Completion of the 1600 MWe reactor was originally scheduled for 2009, but the project has suffered various delays and setbacks.


TVO in September filed an appeal against the European Commission's approval for the French government to inject €4.5 billion ($5.4 billion) into Areva as part of the group's restructuring. TVO claimed the plan does not provide sufficient guarantees that the Olkiluoto 3 EPR project will be completed. Bernard Fontana, CEO of French engineering company Areva NP subsequently said that the Commission's approval in January had been made on the understanding there would be no changes to the Olkiluoto 3 project.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Olkiluoto-3-commercial-operation-rescheduled-0910177.html



其他新聞
2017/12/11 14:18:19 - 核二廠1號機預定於12月10日降載檢修非安全相關設備,原能會持續監控電廠運轉安全
2017/12/11 14:17:18 - 台中電廠新燃氣機組目標112年上路發電
2017/12/11 14:14:01 - UK fusion researchers welcome government support
2017/12/11 14:09:51 - US funds to support advanced nuclear technology development
2017/12/11 14:08:45 - Kepco named preferred bidder for UK's NuGen
2017/12/6 14:27:45 - 原能會謹訂於民國106年12月22日舉辦「核能電廠除役作業與管制規範」專題演講,歡迎報名參加。
2017/12/6 14:25:24 - Kazakhstan to cut uranium production
2017/12/6 14:23:45 - Russia readies for launch of Leningrad and Rostov units
2017/12/6 14:22:47 - Next Vogtle hearings to begin
2017/12/4 14:28:01 - 核三廠1號機預定於12月2日降載例行測試,原能會持續監控電廠運轉安全
2017/12/4 14:26:16 - 網傳買日本淘汰火力發電機組? 台電:不實謠言不排除對亂轉發者提告
2017/12/4 14:25:24 - Reactor vessel installed at Leningrad II-2
2017/12/4 14:24:04 - Decommissioning of Candu protoype moves forward
2017/12/4 14:08:43 - NEI files in support of New York ZEC programme
2017/11/29 14:24:10 - 106年11月27日藍莓相關食品抽樣之檢測結果
2017/11/29 14:21:06 - Governor Approves Restart Of Japan’s Ohi-3 And -4
2017/11/29 14:17:40 - UK, South Korea to extend nuclear cooperation
2017/11/29 14:13:04 - Russian and Brazilian firms to cooperate in nuclear power
2017/11/29 14:11:30 - EU's Energy Union becoming a reality, says Commission
2017/11/24 14:21:18 - 22日嘉義發生之有感地震及其餘震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全

 線上期刊目錄

 瀏覽人數
今天: 39
昨天: 60
本月: 883
總計: 506671

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw