國際核能現況 : Olkiluoto 3 commercial operation rescheduled
發表人 nicenter 於 2017/10/11 14:10:55 (11 人讀取)

Regular electricity production at Finland's Olkiluoto 3 is now expected to start in May 2019, the first-of-a-kind EPR unit's supplier consortium has told Finnish utility Teollisuuden Voima Oyj (TVO). Regular production had previously been scheduled to begin at the end of 2018.





Olkiluoto 3 (left) is sited next to TVO's two operating Olkiluoto units (Image: TVO)


TVO said the plant's supplier had been preparing a schedule review for the project completion "for some time". Work has now reached a stage where the supplier can confirm the main milestones, the company said. The previous schedule was provided in September 2014.


The latest schedule sees grid connection taking place in December 2018 with the start of regular electricity production in May 2019. The unit's ramp-up program will see it produce 2-4 TWh of electricity, at varying power levels between those dates.


TVO's Olkiluoto 3 (OL3) project director Jouni Silvennoinen said the company was "very disappointed" by the additional delay.


"There is still substantial work to be accomplished in the OL3 EPR project and it is essential that all the necessary technical, human and financial resources are allocated to the project. The restructuring of the French nuclear industry must not compromise this," he said.


Cold functional tests began at Olkiluoto 3 in June, with hot functional tests scheduled for later this year. TVO said that although the testing program was progressing many important tests remain to be carried out.


"Our objective remains the prompt completion of the OL3 EPR project. TVO continues to be committed to supporting the turn-key plant supplier," Silvennoinen said.


The consortium of Areva GmbH, Areva NP SAS and Siemens AG began construction of Olkiluoto 3 in 2005 under a turnkey contract signed with TVO in late 2003. Completion of the 1600 MWe reactor was originally scheduled for 2009, but the project has suffered various delays and setbacks.


TVO in September filed an appeal against the European Commission's approval for the French government to inject €4.5 billion ($5.4 billion) into Areva as part of the group's restructuring. TVO claimed the plan does not provide sufficient guarantees that the Olkiluoto 3 EPR project will be completed. Bernard Fontana, CEO of French engineering company Areva NP subsequently said that the Commission's approval in January had been made on the understanding there would be no changes to the Olkiluoto 3 project.


Researched and written
by World Nuclear News



source:http://www.world-nuclear-news.org/NN-Olkiluoto-3-commercial-operation-rescheduled-0910177.html



其他新聞
2017/10/20 14:31:21 - 第三天然氣接收站是大潭增建機組供氣的唯一選擇
2017/10/20 14:20:51 - First Paks 2 Unit To Begin Commercial Operation In 2026, Hungary Official Tells Brussels Conference
2017/10/20 14:19:02 - Russia completes hot tests at Rostov 4
2017/10/20 14:16:48 - IAEA sees safety commitment at EDF's Bugey plant
2017/10/20 14:14:03 - Wide interest in small reactor plan, says CNL
2017/10/18 14:30:00 - 原能會對蘭嶼地區發現模擬低放射性廢棄物桶隨意棄置之處理說明
2017/10/18 14:27:54 - 106年10月16日蘭嶼地區發現模擬低放射性廢棄物桶隨意棄置之說明
2017/10/18 14:25:04 - South Africa Approves Environmental Impact Report For Eskom’s Duynefontein Nuclear Site
2017/10/18 14:24:22 - UK Announces Plans To Invest £460 Million In Nuclear Energy
2017/10/18 14:18:51 - WANO members 'consider challenges of the future'
2017/10/18 14:17:27 - NEI calls for reform to design certification process
2017/10/18 14:12:39 - Lightbridge fuel moves towards irradiation testing
2017/10/18 14:10:43 - Impact of Hanhikivi 1 licensing delay remains unclear
2017/10/13 14:36:56 - 原能會即時掌握北韓13日發生地震與發展
2017/10/13 14:35:50 - Foratom Calls For ‘Rapid Establishment’ Of Brexit Cooperation Agreement For Nuclear Industry
2017/10/13 14:34:08 - US group calls for SMR support
2017/10/13 14:32:43 - UK prepares legislation for Euratom exit
2017/10/13 14:30:27 - ASN gives final opinion on Flamanville EPR vessel
2017/10/11 14:32:48 - 台電「能源轉型」造型花車超吸睛 慶賀中華民國106歲生日快樂
2017/10/11 14:27:28 - Flushing Of Primary Systems Complete As World’s First Floating Nuclear Station Nears Completion In Russia

 線上期刊目錄

 瀏覽人數
今天: 58
昨天: 92
本月: 2039
總計: 502071

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw