logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 日本福島核災專區
* 相關資訊
國際核能現況 : Start Of System Testing Approved At Chernobyl Spent Fuel Storage Facility
發表人 nicenter 於 2017/8/10 17:43:44 (116 人讀取)

4 Aug (NucNet): Ukraine’s State Nuclear Regulatory Inspectorate approved on 1 August 2017 the start of integrated system testing at the newly built interim spent fuel storage facility on the site of the Chernobyl nuclear power station in Ukraine, project developer Holtec International said in a statement.




US-based Holtec said the initial cold testing phase is expected to transition to hot pre-commissioning testing in December 2017, while the first spent fuel deliveries are scheduled for the beginning of March 2018.

A programme for the design and construction of the facility, known as ISF2, began in 1997 with international funding managed by the European Bank for Reconstruction and Development (EBRD).

The facility will store spent fuel from Units 1, 2 and 3 at Chernobyl.

In 2007, Holtec took over the project after the withdrawal of France’s state-controlled Areva over construction problems.

According to the EBRD, the facility will process, dry and cut more than 21,000 fuel assemblies from Chernobyl-1, -2 and -3.

The assemblies will then be placed in double-walled canisters and stored in concrete modules onsite for a minimum of 100 years.

The EBRD said the project is costing around €380m ($451m) and is jointly funded by the EBRD and the EBRD-managed Nuclear Safety Account (NSA) fund.

The 18 NSA donors have committed more than €280m to safety projects at Chernobyl.

The EBRD provided more than €200m of its own funding for the construction of the ISF2.

Holtec said when it begins operation ISF2 will be the world’s largest interim spent fuel storage facility.

Units 1, 2 and 3 at Chernobyl, all of the Soviet RBMK reactor design, were shut down permanently in 1996, 1991, and 2000.

Unit 4, also an RBMK, was destroyed by an explosion in the April 1986 accident.



source: http://www.nucnet.org/all-the-news/2017/08/04/start-of-system-testing-approved-at-chernobyl-spent-fuel-storage-facility



其他新聞
2018/6/22 15:20:00 - UK regulator reports on progress in 2017-2018
2018/6/22 15:16:25 - Orano Boss Says Brussels Has Not Been ‘Nuclear Positive’
2018/6/22 15:13:20 - Darlington to supply molybdenum-99
2018/6/15 15:27:03 - 端午連假豪雨報到 台電成立緊急應變中心待命
2018/6/15 15:14:42 - Nuclear Body Sounds Warning On Premature Shutdowns In France And Calls For ‘Renewal’ Of Nuclear Fleet
2018/6/15 15:13:41 - First yellowcake from seawater for US team
2018/6/15 15:11:29 - Start-up of Finnish EPR put back four months
2018/6/13 15:12:06 - 新機組陸續上線 台電:明年起備用維持15%以上 穩定供電無虞
2018/6/13 15:09:41 - 以最高標準要求安全,核二廠2號機因高壓輸電線路夾板溫度偏高之非機組因素,預定今(12)日晚上解聯調整
2018/6/13 15:04:17 - Jordan Abandons Nuclear Station Deal With Russia
2018/6/13 15:02:06 - Cooperation strengthens mining radiation protection
2018/6/13 14:58:59 - IAEA launches challenge on materials for fusion
2018/6/6 14:39:25 - 竹園超高壓變電所正式啟用 再提升竹科及新竹地區供電品質
2018/6/6 14:28:38 - 原能會今(5)日同意台電公司核二廠2號機急停後再起動
2018/6/6 14:27:30 - DOE announces funding for innovative nuclear technology
2018/6/6 14:25:29 - Tepco frees up Fukushima Daiichi fuel storage space
2018/6/6 14:24:23 - UK starts talks on public investment in nuclear power
2018/6/1 14:22:44 - 針對媒體評論「備轉容量率3%多是『電力供應充足』!」的回應說明
2018/6/1 14:20:00 - 「低放射性廢棄物貯存設施再評估報告審查導則草案」徵詢各界意見
2018/6/1 14:19:06 - Kansai cuts power rates as reactors restart

 線上期刊目錄

 瀏覽人數
今天: 16
昨天: 214
本月: 3636
總計: 527052

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw