logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 日本福島核災專區
* 相關資訊
國際核能現況 : Start Of System Testing Approved At Chernobyl Spent Fuel Storage Facility
發表人 nicenter 於 2017/8/10 17:43:44 (16 人讀取)

4 Aug (NucNet): Ukraine’s State Nuclear Regulatory Inspectorate approved on 1 August 2017 the start of integrated system testing at the newly built interim spent fuel storage facility on the site of the Chernobyl nuclear power station in Ukraine, project developer Holtec International said in a statement.




US-based Holtec said the initial cold testing phase is expected to transition to hot pre-commissioning testing in December 2017, while the first spent fuel deliveries are scheduled for the beginning of March 2018.

A programme for the design and construction of the facility, known as ISF2, began in 1997 with international funding managed by the European Bank for Reconstruction and Development (EBRD).

The facility will store spent fuel from Units 1, 2 and 3 at Chernobyl.

In 2007, Holtec took over the project after the withdrawal of France’s state-controlled Areva over construction problems.

According to the EBRD, the facility will process, dry and cut more than 21,000 fuel assemblies from Chernobyl-1, -2 and -3.

The assemblies will then be placed in double-walled canisters and stored in concrete modules onsite for a minimum of 100 years.

The EBRD said the project is costing around €380m ($451m) and is jointly funded by the EBRD and the EBRD-managed Nuclear Safety Account (NSA) fund.

The 18 NSA donors have committed more than €280m to safety projects at Chernobyl.

The EBRD provided more than €200m of its own funding for the construction of the ISF2.

Holtec said when it begins operation ISF2 will be the world’s largest interim spent fuel storage facility.

Units 1, 2 and 3 at Chernobyl, all of the Soviet RBMK reactor design, were shut down permanently in 1996, 1991, and 2000.

Unit 4, also an RBMK, was destroyed by an explosion in the April 1986 accident.



source: http://www.nucnet.org/all-the-news/2017/08/04/start-of-system-testing-approved-at-chernobyl-spent-fuel-storage-facility



其他新聞
2017/8/16 9:20:00 - Major components installed at final Barakah unit
2017/8/10 17:48:32 - 106年8月8日媒體報導「核電廠隨時釀災 地方首長硬起來」之回應說明
2017/8/10 17:47:19 - 核四廠現為資產維護,從未裝填核子燃料,並無所謂核能發電之情事
2017/8/10 17:46:07 - NRC Staff Directed To Gather Information In Preparation For Yucca Restart
2017/8/10 17:45:21 - Nuclear Energy’s Long-Term Potential Remains High, Says IAEA
2017/8/10 17:44:38 - Special Report: Can India Maintain Its Ambitious Push For New Nuclear?
2017/8/10 17:43:44 - Start Of System Testing Approved At Chernobyl Spent Fuel Storage Facility
2017/8/10 17:42:25 - Nuclear capacity could more than double by 2050, says IAEA
2017/8/10 17:41:31 - India awards contract for fast reactor fuel cycle facility
2017/8/10 17:40:32 - Egypt, Russia 'complete Daba'a plant talks'
2017/8/4 17:31:01 - Japan Report Shows Benefits Of Nuclear Restarts
2017/8/4 17:30:14 - Spain’s Garoña To Shut Down Permanently After Ministry Blocks Restart
2017/8/4 17:29:02 - US Utilities To Abandon Summer-3 And -4 AP1000 Nuclear Project
2017/8/4 17:27:48 - Japanese Data On Marine Samples Near Fukushima Reliable, IAEA Concludes
2017/8/4 17:23:19 - Japan to benefit from reactor restarts, says IEEJ
2017/8/4 17:22:47 - Georgia Power expects late August decision on Vogtle
2017/8/4 17:22:01 - Kudankulam Phase III enters design stage
2017/8/4 17:21:32 - US nuclear construction project to be abandoned
2017/7/28 9:53:01 - Latvia Is Against Belarusian Nuclear Station Legislation, Says Foreign Minister
2017/7/28 9:52:01 - Target For Last Hanhikivi Design Documentation Is Spring 2018, Says Fennovoima

 線上期刊目錄

 瀏覽人數
今天: 5
昨天: 94
本月: 2956
總計: 496249

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw