國際核能現況 : GAO Report And EDF Cost Revisions Reignite Debate On Hinkley Point C
發表人 nicenter 於 2017/7/7 9:43:34 (130 人讀取)

6 Jul (NucNet): The recent announcement by French state-controlled utility EDF that it has added £1.5bn (€1.7bn, $1.9bn) to its estimated costs for two new reactors at Hinkley Point C, has led to questions about whether the government should rethink the project, with some politicians calling for it to be abandoned.

EDF’s announcement, on 3 July 2017, came less than two weeks after a report from the Government Accountability Office said the government’s deal for the two EPR units, now estimated to be costing £19.6bn (€22.3bn, $25.5bn), has locked consumers into a risky and expensive project with uncertain strategic and economic benefits.


The same report concludes, however, that the UK needs nuclear.


This special NucNet report looks at the latest developments on both sides of the Hinkley debate.


Full story for subscribers: http://bit.ly/2tV3480



source: http://www.nucnet.org/all-the-news/2017/07/06/gao-report-and-edf-cost-revisions-reignite-debate-on-hinkley-point-c-II



其他新聞
2018/4/20 14:20:00 - 台電回應綠色和平,深澳對pm2.5的貢獻度最多0.08~0.18%,不知「相當於160萬輛汽車」的推估是從何而來?
2018/4/20 14:11:05 - 大潭電廠新增機組輸電線路變更 降低環境衝擊 依法提出環差申請
2018/4/20 14:07:49 - IAEA tests drone to fight disease-carrying mosquitos
2018/4/20 14:05:39 - Canada considers participation in Iter fusion project
2018/4/18 15:20:00 - 還原瑞芳保育區爭議的真相,台電籲請外界回歸事實討論
2018/4/18 15:18:00 - 台電深澳超超臨界計畫空品影響不到法規萬分之一 不會有許厝國小第2
2018/4/18 15:13:38 - AEM Technology sees milestone with first VVER-TOI
2018/4/18 15:10:12 - Report highlights impact of US nuclear plant closures
2018/4/18 15:04:37 - India, USA to collaborate on neutrino science
2018/4/11 15:10:00 - 台電簽署離岸風電第三方驗證合作備忘錄 為健全綠色金融環境助力
2018/4/11 15:08:23 - 原能會已設立「核二廠2號機再起動」專區,持續公開管制資訊
2018/4/11 15:03:05 - Council formed to support Canadian isotope production
2018/4/11 14:56:44 - Final Barakah dome complete
2018/3/30 14:47:16 - 今(29)日8時17分南投地區規模4.8有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/3/30 14:46:01 - 地熱發電國家隊首部曲 台電與中油簽MOU開發宜蘭地熱
2018/3/30 14:26:54 - FirstEnergy gives notice to deactivate four units
2018/3/30 14:17:55 - Darlington refurbishment achieves new milestone
2018/3/30 14:13:35 - Court approves Westinghouse reorganisation plan
2018/3/28 15:02:51 - 因應能源轉型 積極面對核四資產處理 台電:採影響最小化
2018/3/28 14:30:22 - Czech new build financing decision by mid-year

 線上期刊目錄

 瀏覽人數
今天: 20
昨天: 101
本月: 1977
總計: 519347

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw