國際核能現況 : Cost of Hinkley Point C rises by 8%, EDF says
發表人 nicenter 於 2017/7/5 9:36:40 (89 人讀取)

EDF estimates the cost of the Hinkley Point C nuclear power plant project in the UK to now total £19.6 billion ($25.4 billion), up from its earlier estimate of £18.1 billion. The target date for first operation of unit 1 remains by the end of 2025.



An artist's impression of how Hinkley Point C could appear (Image: EDF Energy)

The company announced in its 2016 Annual Financial Report that it would carry out a full review of the costs and schedule of the Hinkley Point C project.


In a statement today, EDF said its latest estimate "includes successful operational action plans, in partnership with suppliers". The increase in costs "result mainly from a better understanding of the design adapted to the requirements of the British regulators, the volume and sequencing of work on site and the gradual implementation of supplier contracts".


EDF's projected rate of return on the project is now around 8.5% compared with the initial estimate of about 9%.


The pouring of first safety-related concrete for unit 1 of will be in mid-2019, EDF confirmed. However, it noted this assumes the final design, "which is on a tight schedule", is completed by the end of next year.


EDF said the risk of deferral of delivery is estimated at 15 months for unit 1 and nine months for unit 2. This risk, it said, would entail an additional potential cost of some £700 million. Under this assumption, the rate of return for EDF would be about 8.2%.


EDF Energy's new build subsidiary, EDF NNB Generation Company, "in compliance with its rules of governance, will study and implement the recommendations of the review".


Under a deal agreed in October 2015, China General Nuclear (CGN) will take a 33.5% stake in EDF Energy's project to construct Hinkley Point C, in Somerset, England. Consisting of two Areva-designed European Pressurised Reactors, it will be the first new nuclear power station to be built in the UK in almost 20 years and will provide about 7% of the country's electricity.


The final agreements enabling construction of two EPRs at Hinkley Point C to proceed were signed on 29 September last year by the UK government, EDF and CGN. These agreements included the contract-for-difference (CfD) and the Secretary of State Investor Agreement. The CfD - the ratepayer-backed guaranteed price for electricity generated by Hinkley Point C - was originally agreed in October 2013 and guarantees the plant will get £92.50 per MWh for for its first 35 years of operation. The signing of the agreements followed a long-awaited and positive final investment decision from the EDF board on 28 July.


The UK EPR design became the first reactor design to complete the country's Generic Design Assessment process and receive a Design Acceptance Confirmation from the Office for Nuclear Regulation (ONR) and a Statement of Design Acceptability from the Environment Agency, in December 2012.


In March, the ONR granted its first consent for the start of construction of a nuclear power plant at Hinkley Point C. The consent covers the placement of the structural concrete for the first nuclear safety-related structure at the site. It does not give consent for all elements of construction.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Cost-of-Hinkley-Point-C-rises-by-8-percent-EDF-says-0307175.html



其他新聞
2017/9/22 15:25:45 - 原能會對低鈉鹽輻射問題之後續處理說明
2017/9/22 15:20:57 - Rosatom outlines future of nuclear in IAEA address
2017/9/22 15:18:31 - IAEA celebrates 20 years of waste safety convention
2017/9/20 14:49:32 - 106年核安第23號演習兵棋推演延期至9月26日舉行
2017/9/20 14:40:00 - 原能會樂意協助經濟部推動核廢料境外合作處置
2017/9/20 14:36:51 - Amano Calls For Budget Support As Demands On IAEA Grow
2017/9/20 14:28:43 - China’s Fuqing-4 Begins Commercial Operation
2017/9/20 14:23:18 - Komarov explains nuclear's role in energy mix
2017/9/20 14:19:44 - NuScale highlights non-power uses of its SMR
2017/9/20 14:15:16 - China plans further high temperature reactor innovation
2017/9/20 14:12:30 - European group calls for JCPOA support
2017/9/14 11:50:00 - 外媒報導韓國境內昨日測得放射性物質氙,原能會密切監控中
2017/9/14 11:43:58 - Swiss Regulator Approves Project Documents For Mühleberg Decommissioning
2017/9/14 11:34:18 - SMRs Can Deliver Electricity For Similar Cost To Offshore Wind, Says Rolls Royce
2017/9/14 11:12:07 - Rosatom head visits Iter, latest equipment batch sent
2017/9/14 11:04:06 - UK SMR consortium calls for government support
2017/9/14 10:56:02 - Steam generator installation underway at Karachi 2
2017/8/16 9:20:00 - Major components installed at final Barakah unit
2017/8/10 17:48:32 - 106年8月8日媒體報導「核電廠隨時釀災 地方首長硬起來」之回應說明
2017/8/10 17:47:19 - 核四廠現為資產維護,從未裝填核子燃料,並無所謂核能發電之情事

 線上期刊目錄

 瀏覽人數
今天: 80
昨天: 126
本月: 2517
總計: 499449

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw