logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 日本福島核災專區
* 相關資訊
國際核能現況 : Cost of Hinkley Point C rises by 8%, EDF says
發表人 nicenter 於 2017/7/5 9:36:40 (63 人讀取)

EDF estimates the cost of the Hinkley Point C nuclear power plant project in the UK to now total £19.6 billion ($25.4 billion), up from its earlier estimate of £18.1 billion. The target date for first operation of unit 1 remains by the end of 2025.



An artist's impression of how Hinkley Point C could appear (Image: EDF Energy)

The company announced in its 2016 Annual Financial Report that it would carry out a full review of the costs and schedule of the Hinkley Point C project.


In a statement today, EDF said its latest estimate "includes successful operational action plans, in partnership with suppliers". The increase in costs "result mainly from a better understanding of the design adapted to the requirements of the British regulators, the volume and sequencing of work on site and the gradual implementation of supplier contracts".


EDF's projected rate of return on the project is now around 8.5% compared with the initial estimate of about 9%.


The pouring of first safety-related concrete for unit 1 of will be in mid-2019, EDF confirmed. However, it noted this assumes the final design, "which is on a tight schedule", is completed by the end of next year.


EDF said the risk of deferral of delivery is estimated at 15 months for unit 1 and nine months for unit 2. This risk, it said, would entail an additional potential cost of some £700 million. Under this assumption, the rate of return for EDF would be about 8.2%.


EDF Energy's new build subsidiary, EDF NNB Generation Company, "in compliance with its rules of governance, will study and implement the recommendations of the review".


Under a deal agreed in October 2015, China General Nuclear (CGN) will take a 33.5% stake in EDF Energy's project to construct Hinkley Point C, in Somerset, England. Consisting of two Areva-designed European Pressurised Reactors, it will be the first new nuclear power station to be built in the UK in almost 20 years and will provide about 7% of the country's electricity.


The final agreements enabling construction of two EPRs at Hinkley Point C to proceed were signed on 29 September last year by the UK government, EDF and CGN. These agreements included the contract-for-difference (CfD) and the Secretary of State Investor Agreement. The CfD - the ratepayer-backed guaranteed price for electricity generated by Hinkley Point C - was originally agreed in October 2013 and guarantees the plant will get £92.50 per MWh for for its first 35 years of operation. The signing of the agreements followed a long-awaited and positive final investment decision from the EDF board on 28 July.


The UK EPR design became the first reactor design to complete the country's Generic Design Assessment process and receive a Design Acceptance Confirmation from the Office for Nuclear Regulation (ONR) and a Statement of Design Acceptability from the Environment Agency, in December 2012.


In March, the ONR granted its first consent for the start of construction of a nuclear power plant at Hinkley Point C. The consent covers the placement of the structural concrete for the first nuclear safety-related structure at the site. It does not give consent for all elements of construction.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Cost-of-Hinkley-Point-C-rises-by-8-percent-EDF-says-0307175.html



其他新聞
2017/7/7 9:43:34 - GAO Report And EDF Cost Revisions Reignite Debate On Hinkley Point C
2017/7/7 9:42:18 - IAEA’s Amano Praises Progress At Bangladesh’s Rooppur Nuclear Station
2017/7/7 9:40:51 - IAEA’s Amano Says Agency Will Strengthen Cooperation With Myanmar
2017/7/7 9:39:03 - Progress being made at Rooppur site, says IAEA head
2017/7/5 9:41:46 - UK Report Says ‘Traditional Nuclear Projects’ Will Have To Adapt
2017/7/5 9:40:00 - UK’s Hinkley Point C Is Over Budget And Behind Schedule, Says EDF
2017/7/5 9:39:28 - UK launches 2017 nuclear workforce assessment
2017/7/5 9:38:36 - Russia signs MOU for Vietnam nuclear research centre
2017/7/5 9:37:53 - UK nuclear modular manufacturing R&D centre opens
2017/7/5 9:36:40 - Cost of Hinkley Point C rises by 8%, EDF says
2017/7/5 9:35:16 - Pakistan's Chashma 4 connected to grid
2017/7/1 1:50:00 - 106年6月30日有關媒體刊載「蘭嶼核廢場調查將出爐 朝立法補償」之回應說明
2017/7/1 1:43:25 - 原能會積極落實非核家園政策 完成核一廠除役計畫審查
2017/7/1 1:41:25 - Rosatom Confirms Start Of Construction At India’s Kudankulam-3
2017/7/1 1:40:48 - New Energy Minister Says Britain Needs Nuclear For Security And Climate Goals
2017/7/1 1:39:41 - Trump Believes No Energy Portfolio Is Complete Without Nuclear, Says Perry
2017/7/1 1:36:46 - Trump heralds golden era for US energy
2017/7/1 1:35:27 - US waste management bill passes committee vote
2017/7/1 1:34:34 - UK government remains committed to nuclear, minister says
2017/7/1 1:33:37 - Construction officially begins on Kudankulam 3 and 4

 線上期刊目錄

 瀏覽人數
今天: 1
昨天: 631
本月: 2894
總計: 492928

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw