logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 日本福島核災專區
* 相關資訊
國際核能現況 : Belgium’s Regulator Approves Tihange-1 Restart
發表人 nicenter 於 2017/5/17 9:55:46 (56 人讀取)

Belgium’s Regulator Approves Tihange-1 Restart



16 May (NucNet): Belgium’s Federal Agency for Nuclear Control (Fanc) has approved the restart of the Tihange-1 nuclear reactor unit, which has been offline since 7 September 2016 following damage to a non-nuclear building during upgrade work. Fanc said on 15 May 2017 that operator Engie Electrabel had shown all necessary work for the safe operation of the plant had been carried out. FANC said upgrade work that led to the damage was being done as part of a life extension of the unit to 1 October 2025. During the upgrade work, the building equipped with auxiliary components was damaged, causing the reactor to trip. The pumps in the auxiliary building must be continuously available, Fanc said. Tihange-1, a 962-MW pressurised water reactor unit, began commercial operation on 1 October 1975.



source: http://www.nucnet.org/all-the-news/2017/05/16/belgium-s-regulator-approves-tihange-1-restart



其他新聞
2017/8/16 9:20:00 - Major components installed at final Barakah unit
2017/8/10 17:48:32 - 106年8月8日媒體報導「核電廠隨時釀災 地方首長硬起來」之回應說明
2017/8/10 17:47:19 - 核四廠現為資產維護,從未裝填核子燃料,並無所謂核能發電之情事
2017/8/10 17:46:07 - NRC Staff Directed To Gather Information In Preparation For Yucca Restart
2017/8/10 17:45:21 - Nuclear Energy’s Long-Term Potential Remains High, Says IAEA
2017/8/10 17:44:38 - Special Report: Can India Maintain Its Ambitious Push For New Nuclear?
2017/8/10 17:43:44 - Start Of System Testing Approved At Chernobyl Spent Fuel Storage Facility
2017/8/10 17:42:25 - Nuclear capacity could more than double by 2050, says IAEA
2017/8/10 17:41:31 - India awards contract for fast reactor fuel cycle facility
2017/8/10 17:40:32 - Egypt, Russia 'complete Daba'a plant talks'
2017/8/4 17:31:01 - Japan Report Shows Benefits Of Nuclear Restarts
2017/8/4 17:30:14 - Spain’s Garoña To Shut Down Permanently After Ministry Blocks Restart
2017/8/4 17:29:02 - US Utilities To Abandon Summer-3 And -4 AP1000 Nuclear Project
2017/8/4 17:27:48 - Japanese Data On Marine Samples Near Fukushima Reliable, IAEA Concludes
2017/8/4 17:23:19 - Japan to benefit from reactor restarts, says IEEJ
2017/8/4 17:22:47 - Georgia Power expects late August decision on Vogtle
2017/8/4 17:22:01 - Kudankulam Phase III enters design stage
2017/8/4 17:21:32 - US nuclear construction project to be abandoned
2017/7/28 9:53:01 - Latvia Is Against Belarusian Nuclear Station Legislation, Says Foreign Minister
2017/7/28 9:52:01 - Target For Last Hanhikivi Design Documentation Is Spring 2018, Says Fennovoima

 線上期刊目錄

 瀏覽人數
今天: 47
昨天: 123
本月: 2619
總計: 495912

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw