國際核能現況 : Summer plant construction progress continues
發表人 nicenter 於 2017/5/17 9:43:24 (101 人讀取)

08 May 2017

The VC Summer nuclear construction project is now over 64% complete, South Carolina Electricity & Gas (SCG&E) said in its latest progress report to the state's Public Service Commission. The substantial completion dates for the two AP1000 units are currently unchanged from previous timelines but are to be re-evaluated in light of Westinghouse's recent bankruptcy filing.






The Summer construction site, pictured in January (Image: SCE&G)


Construction of Summer unit 2 began in March 2013, with work starting on unit 3 in November 2013. The units are targeted for substantial completion in April 2020 for unit 2 and December 2020 for unit 3. Scana subsidiary SCE&G is required to make quarterly reports to the PSC under the provisions of the state's Base Load Review Act (BLRA), which applies to the construction of power plants by all regulated electric utilities in the state.


Recent schedule information from Westinghouse suggests that the project remains on track to achieve the substantial completion dates within the 18 months contingency period provided in the order establishing milestones for BLRA monitoring purposes, SCE&G said. "[T]hese dates will be re-evaluated in light of [Westinghouse's] historical inability to achieve forecasted productivity and work for efficiency levels and in light of [Westinghouse's] bankruptcy filing]," it added.


As of 31 March, the project's engineering phase was 96.0% complete, with procurement 88.2% complete, construction 34.3% complete and start-up activities 8.6% complete. These figures are weighted and aggregated to deliver the total percentage completion of 64.1%. During the quarter, the last of the project's four steam generators and two of unit 2's four reactor coolant pumps (RCPs) were received on site. The remaining RCPs for unit 2 are completed and awaiting shipment, while the RCPs for unit 3 are undergoing final assembly and testing.


SCE&G told the PSC it is still evaluating whether or not to complete one or both of the units following Westinghouse's 29 March bankruptcy filing. The company told the PSC it expects to complete its evaluation, which will assess the relative merits of completing both units, cancelling or deferring both units, or completing unit 2 and cancelling or deferring unit 3, during the second quarter of this year.


The company said it has not yet validated Westinghouse's revised estimate that it will cost about $829 million more to complete the units than Westinghouse will be entitled to charge SCE&G under the EPC contract for the project. Damages that could be claimed under the EPC contract are capped at a level of 25% of payments already made at the time that a breach of contract occurs.


"The cap currently stands at approximately $940 million, which exceeds the amount of additional cost reflected in [Westinghouse's] unvalidated estimate," the company said. Westinghouse's payment obligations under the EPC contract are guaranteed directly by its parent company, Toshiba.


Westinghouse is willing to continue to support the project in areas such as engineering, procurement, testing, licensing, start-up, cyber security and records administration, SCE&G said.


"SCE&G is analysing what support [Westinghouse] might provide going forward and what resources would be required to continue the project without [Westinghouse] in the lead role," the company said. An assessment of damages due from Westinghouse for the anticipated breach of the EPC contract, and Westinghouse and Toshiba's ability to pay for those damages, would be an important component of its cost analysis for the completion of the units, it said.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Summer-plant-construction-progress-continues-0805177.html



其他新聞
2018/4/25 14:18:47 - 經濟部、台電昨開深澳電廠記者會 宣示打造世界高效低排電廠 不讓供電與環保成為選擇題
2018/4/25 14:13:20 - Bruce Power signs advanced manufacturing contracts
2018/4/25 14:11:19 - Macron: Europe must prioritise emission reductions
2018/4/25 14:09:36 - State Backing Means China Can Absorb Risks Of New Nuclear, Says Report
2018/4/20 14:20:00 - 台電回應綠色和平,深澳對pm2.5的貢獻度最多0.08~0.18%,不知「相當於160萬輛汽車」的推估是從何而來?
2018/4/20 14:11:05 - 大潭電廠新增機組輸電線路變更 降低環境衝擊 依法提出環差申請
2018/4/20 14:07:49 - IAEA tests drone to fight disease-carrying mosquitos
2018/4/20 14:05:39 - Canada considers participation in Iter fusion project
2018/4/18 15:20:00 - 還原瑞芳保育區爭議的真相,台電籲請外界回歸事實討論
2018/4/18 15:18:00 - 台電深澳超超臨界計畫空品影響不到法規萬分之一 不會有許厝國小第2
2018/4/18 15:13:38 - AEM Technology sees milestone with first VVER-TOI
2018/4/18 15:10:12 - Report highlights impact of US nuclear plant closures
2018/4/18 15:04:37 - India, USA to collaborate on neutrino science
2018/4/11 15:10:00 - 台電簽署離岸風電第三方驗證合作備忘錄 為健全綠色金融環境助力
2018/4/11 15:08:23 - 原能會已設立「核二廠2號機再起動」專區,持續公開管制資訊
2018/4/11 15:03:05 - Council formed to support Canadian isotope production
2018/4/11 14:56:44 - Final Barakah dome complete
2018/3/30 14:47:16 - 今(29)日8時17分南投地區規模4.8有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/3/30 14:46:01 - 地熱發電國家隊首部曲 台電與中油簽MOU開發宜蘭地熱
2018/3/30 14:26:54 - FirstEnergy gives notice to deactivate four units

 線上期刊目錄

 瀏覽人數
今天: 89
昨天: 71
本月: 2435
總計: 519805

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw