國際核能現況 : Summer plant construction progress continues
發表人 nicenter 於 2017/5/17 9:43:24 (22 人讀取)

08 May 2017

The VC Summer nuclear construction project is now over 64% complete, South Carolina Electricity & Gas (SCG&E) said in its latest progress report to the state's Public Service Commission. The substantial completion dates for the two AP1000 units are currently unchanged from previous timelines but are to be re-evaluated in light of Westinghouse's recent bankruptcy filing.






The Summer construction site, pictured in January (Image: SCE&G)


Construction of Summer unit 2 began in March 2013, with work starting on unit 3 in November 2013. The units are targeted for substantial completion in April 2020 for unit 2 and December 2020 for unit 3. Scana subsidiary SCE&G is required to make quarterly reports to the PSC under the provisions of the state's Base Load Review Act (BLRA), which applies to the construction of power plants by all regulated electric utilities in the state.


Recent schedule information from Westinghouse suggests that the project remains on track to achieve the substantial completion dates within the 18 months contingency period provided in the order establishing milestones for BLRA monitoring purposes, SCE&G said. "[T]hese dates will be re-evaluated in light of [Westinghouse's] historical inability to achieve forecasted productivity and work for efficiency levels and in light of [Westinghouse's] bankruptcy filing]," it added.


As of 31 March, the project's engineering phase was 96.0% complete, with procurement 88.2% complete, construction 34.3% complete and start-up activities 8.6% complete. These figures are weighted and aggregated to deliver the total percentage completion of 64.1%. During the quarter, the last of the project's four steam generators and two of unit 2's four reactor coolant pumps (RCPs) were received on site. The remaining RCPs for unit 2 are completed and awaiting shipment, while the RCPs for unit 3 are undergoing final assembly and testing.


SCE&G told the PSC it is still evaluating whether or not to complete one or both of the units following Westinghouse's 29 March bankruptcy filing. The company told the PSC it expects to complete its evaluation, which will assess the relative merits of completing both units, cancelling or deferring both units, or completing unit 2 and cancelling or deferring unit 3, during the second quarter of this year.


The company said it has not yet validated Westinghouse's revised estimate that it will cost about $829 million more to complete the units than Westinghouse will be entitled to charge SCE&G under the EPC contract for the project. Damages that could be claimed under the EPC contract are capped at a level of 25% of payments already made at the time that a breach of contract occurs.


"The cap currently stands at approximately $940 million, which exceeds the amount of additional cost reflected in [Westinghouse's] unvalidated estimate," the company said. Westinghouse's payment obligations under the EPC contract are guaranteed directly by its parent company, Toshiba.


Westinghouse is willing to continue to support the project in areas such as engineering, procurement, testing, licensing, start-up, cyber security and records administration, SCE&G said.


"SCE&G is analysing what support [Westinghouse] might provide going forward and what resources would be required to continue the project without [Westinghouse] in the lead role," the company said. An assessment of damages due from Westinghouse for the anticipated breach of the EPC contract, and Westinghouse and Toshiba's ability to pay for those damages, would be an important component of its cost analysis for the completion of the units, it said.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Summer-plant-construction-progress-continues-0805177.html



其他新聞
2017/6/21 10:42:30 - 國際原子能總署連續第11年宣告我國「所有核物料均用於核能和平用途」
2017/6/21 10:41:21 - Q&A: What Progress Has Germany Made Half Way Down The Phaseout Path?
2017/6/21 10:39:44 - Rosatom Agrees To Sell 49% Stake In Turkey’s Akkuyu Project
2017/6/21 10:38:53 - EC Clears Creation Of €24 Billion Public Fund For Handling Radwaste In Germany
2017/6/21 10:37:52 - Turkey’s Energy Market Regulator Grants Power Generation Licence To Akkuyu Project
2017/6/21 10:36:42 - Akkuyu project receives production licence
2017/6/16 9:40:00 - 原能會於今(15)日16時50分同意台電公司核三廠2號機併聯發電
2017/6/16 9:36:46 - [輿情回應]106年6月15日媒體報導「核二1號機重起後監測到溫度過高及輻射超標,有安全疑慮」之回應說明
2017/6/16 9:33:44 - Russia Expects ‘Active’ Participation Of Hungarian Industry In Paks 2 Project, Says Rosatom CEO
2017/6/16 9:32:54 - Why Pressure Is Growing For ‘Clear And Consistent’ Policy Support For Nuclear
2017/6/16 9:32:01 - Japanese District Court Denies Injunction Against Restart Of Genkai-3 and -4
2017/6/16 9:29:20 - Fuel loading under way at Fuqing 4
2017/6/16 9:27:59 - Steam generators shipped to second Belarusian unit
2017/6/14 9:44:46 - Toshiba Agrees On Payment Schedule For Vogtle Guarantee Obligations
2017/6/14 9:43:01 - Construction Of LEU Bank On Schedule, Shipments Expected In 2018, Says Amano
2017/6/14 9:42:31 - EBRD Announces Start Of Hot Trials At Ignalina Waste Facility
2017/6/14 9:40:00 - 核二廠1號機因主變壓器至開關場之鐵塔C相懸垂礙子處溫度偏高,預定今(12)日晚上解聯檢修
2017/6/14 9:36:20 - IAEA fuel 'bank' on course
2017/6/14 9:34:06 - Rolls-Royce elaborates on its SMR plans
2017/6/14 9:32:59 - Finnish EPR starts key pre-operational tests

 線上期刊目錄

 瀏覽人數
今天: 69
昨天: 69
本月: 1957
總計: 489268

30013 新竹市光復路二段101號 研發大樓二樓208室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw