國際核能現況 : Summer plant construction progress continues
發表人 nicenter 於 2017/5/17 9:43:24 (11 人讀取)

08 May 2017

The VC Summer nuclear construction project is now over 64% complete, South Carolina Electricity & Gas (SCG&E) said in its latest progress report to the state's Public Service Commission. The substantial completion dates for the two AP1000 units are currently unchanged from previous timelines but are to be re-evaluated in light of Westinghouse's recent bankruptcy filing.






The Summer construction site, pictured in January (Image: SCE&G)


Construction of Summer unit 2 began in March 2013, with work starting on unit 3 in November 2013. The units are targeted for substantial completion in April 2020 for unit 2 and December 2020 for unit 3. Scana subsidiary SCE&G is required to make quarterly reports to the PSC under the provisions of the state's Base Load Review Act (BLRA), which applies to the construction of power plants by all regulated electric utilities in the state.


Recent schedule information from Westinghouse suggests that the project remains on track to achieve the substantial completion dates within the 18 months contingency period provided in the order establishing milestones for BLRA monitoring purposes, SCE&G said. "[T]hese dates will be re-evaluated in light of [Westinghouse's] historical inability to achieve forecasted productivity and work for efficiency levels and in light of [Westinghouse's] bankruptcy filing]," it added.


As of 31 March, the project's engineering phase was 96.0% complete, with procurement 88.2% complete, construction 34.3% complete and start-up activities 8.6% complete. These figures are weighted and aggregated to deliver the total percentage completion of 64.1%. During the quarter, the last of the project's four steam generators and two of unit 2's four reactor coolant pumps (RCPs) were received on site. The remaining RCPs for unit 2 are completed and awaiting shipment, while the RCPs for unit 3 are undergoing final assembly and testing.


SCE&G told the PSC it is still evaluating whether or not to complete one or both of the units following Westinghouse's 29 March bankruptcy filing. The company told the PSC it expects to complete its evaluation, which will assess the relative merits of completing both units, cancelling or deferring both units, or completing unit 2 and cancelling or deferring unit 3, during the second quarter of this year.


The company said it has not yet validated Westinghouse's revised estimate that it will cost about $829 million more to complete the units than Westinghouse will be entitled to charge SCE&G under the EPC contract for the project. Damages that could be claimed under the EPC contract are capped at a level of 25% of payments already made at the time that a breach of contract occurs.


"The cap currently stands at approximately $940 million, which exceeds the amount of additional cost reflected in [Westinghouse's] unvalidated estimate," the company said. Westinghouse's payment obligations under the EPC contract are guaranteed directly by its parent company, Toshiba.


Westinghouse is willing to continue to support the project in areas such as engineering, procurement, testing, licensing, start-up, cyber security and records administration, SCE&G said.


"SCE&G is analysing what support [Westinghouse] might provide going forward and what resources would be required to continue the project without [Westinghouse] in the lead role," the company said. An assessment of damages due from Westinghouse for the anticipated breach of the EPC contract, and Westinghouse and Toshiba's ability to pay for those damages, would be an important component of its cost analysis for the completion of the units, it said.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Summer-plant-construction-progress-continues-0805177.html



其他新聞
2017/5/24 10:12:08 - German Nuclear Forum Sounds Warning On Need For Long-Term Skills And Training
2017/5/24 10:10:43 - Switzerland Votes To Phase Out Nuclear Energy
2017/5/24 10:10:00 - 2017輻射源實體防護及保安管理訓練
2017/5/24 10:09:26 - Greenland’s Kvanefjeld Uranium Project Going Through Feasibility Study And EIA
2017/5/24 10:03:21 - 原能會審查同意台電公司核一廠2號機降載延時運轉案
2017/5/24 10:01:50 - 2017大型活動輻射事件應變訓練
2017/5/24 10:00:23 - 原能會同意核三廠2號機可開始依計畫執行受損組件更換作業
2017/5/24 9:59:38 - 原能會同意核二廠1號機護箱裝載池可啟用置放用過燃料
2017/5/24 9:57:41 - Swiss voters approve gradual nuclear phase out
2017/5/24 9:57:00 - Mixed progress for Ohio legislation
2017/5/24 9:56:06 - ANS urges support for continued nuclear operation
2017/5/24 9:55:25 - UK parties make scant reference to nuclear power
2017/5/24 9:53:58 - European consortium completes first Iter magnet
2017/5/19 9:54:55 - Argentina and China sign contract for two reactors
2017/5/19 9:53:39 - Indian units to boost domestic nuclear industry
2017/5/19 9:52:47 - China, Saudi Arabia begin HTGR feasibility study
2017/5/19 9:51:12 - Japan's Takahama-4 Resumes Commercial Operation After More Than A Year Offline
2017/5/19 9:50:00 - 106年5月17日「核二廠燃料廠房護箱裝載池設備修改案」完工後聯合視察
2017/5/19 9:50:00 - 「重現北火足跡」開展 老員工講古 再現電廠人文風華
2017/5/17 9:55:46 - Belgium’s Regulator Approves Tihange-1 Restart

 線上期刊目錄

 瀏覽人數
今天: 53
昨天: 64
本月: 1749
總計: 486837

30013 新竹市光復路二段101號 研發大樓二樓208室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw