國際核能現況 : Completed Barakah 1 awaits permission to load fuel
發表人 nicenter 於 2017/5/17 9:41:49 (52 人讀取)

05 May 2017

Initial construction has been completed at the UAE's first power reactor, Barakah 1. The operating company, Nawah Energy Company, must gain approval from national regulators before the final stage of loading fuel and bringing it into service.




The APR-1400 pressurized water reactor has been built by a South Korean consortium for its customer Emirates Nuclear Energy Corporation (Enec). Initial construction covering 95% of work is complete, including tests of safety systems, said Enec.


The remaining 5% of construction is the commissioning the reactor and final preparation of its 277 systems. This process starts with loading nuclear fuel into the reactor core, an operation which cannot take place until the Federal Authority for Nuclear Regulation (FANR) issues an operating licence to Nawah Energy Company, a joint venture of Enec and Kepco.





Barakah 1 (Image: Enec)

Enec today announced that Nawah continues to work with FANR towards obtaining this operating licence. In addition the UAE nuclear community has committed to completing two voluntary pre-operation peer reviews before moving forward: one at the industry level with the World Association of Nuclear Operators, another at the national level with the International Atomic Energy Agency. It was expected that the FANR review and licence would be completed last of these.


Enec applied for an operating licence in March 2015, but one year later created Nawah as a joint venture with Kepco to take that role instead. Nawah was boosted in July last year by an $880 million operating support services agreement where KHNP will supply 400 qualified staff until 2030. Yesterday Arabian Business reported that Nawah had finalised appointments to its board.


Acting Nawah CEO Mohammed Sahoo alSuwaidi said: "As we move towards unit 1 fuel load, we recognise the scale of both our responsibilities and of the challenges that lie ahead of us. Nawah's commitment to meeting the highest standards of safety and quality in nuclear operations is what drives the work of all our personnel, who are striving to ensure that we meet FANR's expectations."


Enec said the start-up schedule for Barakah 1 had been moved back in accordance with "a desire to achieve the highest possible nuclear quality and safety standards ... as well as lessons learned from [the commissioning of] Shin Kori 3 in South Korea, the reference plant for Barakah".


It added that the timeline includes an extension for the start-up of nuclear operations for unit 1, from 2017 to 2018, to ensure sufficient time for international assessments and adherence to nuclear industry safety standards, as well as "a reinforcement of operational proficiency for plant personnel". A spokesman for Enec told World Nuclear News it is "confident in the capacity to deliver" four APR-1400s by 2020, pending regulatory approval.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Completed-Barakah-1-awaits-permission-to-load-fuel-0505171.html



其他新聞
2017/10/18 14:30:00 - 原能會對蘭嶼地區發現模擬低放射性廢棄物桶隨意棄置之處理說明
2017/10/18 14:27:54 - 106年10月16日蘭嶼地區發現模擬低放射性廢棄物桶隨意棄置之說明
2017/10/18 14:25:04 - South Africa Approves Environmental Impact Report For Eskom’s Duynefontein Nuclear Site
2017/10/18 14:24:22 - UK Announces Plans To Invest £460 Million In Nuclear Energy
2017/10/18 14:18:51 - WANO members 'consider challenges of the future'
2017/10/18 14:17:27 - NEI calls for reform to design certification process
2017/10/18 14:12:39 - Lightbridge fuel moves towards irradiation testing
2017/10/18 14:10:43 - Impact of Hanhikivi 1 licensing delay remains unclear
2017/10/13 14:36:56 - 原能會即時掌握北韓13日發生地震與發展
2017/10/13 14:35:50 - Foratom Calls For ‘Rapid Establishment’ Of Brexit Cooperation Agreement For Nuclear Industry
2017/10/13 14:34:08 - US group calls for SMR support
2017/10/13 14:32:43 - UK prepares legislation for Euratom exit
2017/10/13 14:30:27 - ASN gives final opinion on Flamanville EPR vessel
2017/10/11 14:32:48 - 台電「能源轉型」造型花車超吸睛 慶賀中華民國106歲生日快樂
2017/10/11 14:27:28 - Flushing Of Primary Systems Complete As World’s First Floating Nuclear Station Nears Completion In Russia
2017/10/11 14:21:34 - Cernavodă Negotiations Continuing With China’s CGN, Says Nuclearelectrica
2017/10/11 14:19:43 - South Korea's AP1400 clear for European export
2017/10/11 14:15:02 - Robot deployed into Magnox Swarf Storage Silo
2017/10/11 14:13:05 - Westinghouse offers large-scale water jet machining
2017/10/11 14:10:55 - Olkiluoto 3 commercial operation rescheduled

 線上期刊目錄

 瀏覽人數
今天: 69
昨天: 86
本月: 1785
總計: 501817

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw