國際核能現況 : Completed Barakah 1 awaits permission to load fuel
發表人 nicenter 於 2017/5/17 9:41:49 (63 人讀取)

05 May 2017

Initial construction has been completed at the UAE's first power reactor, Barakah 1. The operating company, Nawah Energy Company, must gain approval from national regulators before the final stage of loading fuel and bringing it into service.




The APR-1400 pressurized water reactor has been built by a South Korean consortium for its customer Emirates Nuclear Energy Corporation (Enec). Initial construction covering 95% of work is complete, including tests of safety systems, said Enec.


The remaining 5% of construction is the commissioning the reactor and final preparation of its 277 systems. This process starts with loading nuclear fuel into the reactor core, an operation which cannot take place until the Federal Authority for Nuclear Regulation (FANR) issues an operating licence to Nawah Energy Company, a joint venture of Enec and Kepco.





Barakah 1 (Image: Enec)

Enec today announced that Nawah continues to work with FANR towards obtaining this operating licence. In addition the UAE nuclear community has committed to completing two voluntary pre-operation peer reviews before moving forward: one at the industry level with the World Association of Nuclear Operators, another at the national level with the International Atomic Energy Agency. It was expected that the FANR review and licence would be completed last of these.


Enec applied for an operating licence in March 2015, but one year later created Nawah as a joint venture with Kepco to take that role instead. Nawah was boosted in July last year by an $880 million operating support services agreement where KHNP will supply 400 qualified staff until 2030. Yesterday Arabian Business reported that Nawah had finalised appointments to its board.


Acting Nawah CEO Mohammed Sahoo alSuwaidi said: "As we move towards unit 1 fuel load, we recognise the scale of both our responsibilities and of the challenges that lie ahead of us. Nawah's commitment to meeting the highest standards of safety and quality in nuclear operations is what drives the work of all our personnel, who are striving to ensure that we meet FANR's expectations."


Enec said the start-up schedule for Barakah 1 had been moved back in accordance with "a desire to achieve the highest possible nuclear quality and safety standards ... as well as lessons learned from [the commissioning of] Shin Kori 3 in South Korea, the reference plant for Barakah".


It added that the timeline includes an extension for the start-up of nuclear operations for unit 1, from 2017 to 2018, to ensure sufficient time for international assessments and adherence to nuclear industry safety standards, as well as "a reinforcement of operational proficiency for plant personnel". A spokesman for Enec told World Nuclear News it is "confident in the capacity to deliver" four APR-1400s by 2020, pending regulatory approval.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Completed-Barakah-1-awaits-permission-to-load-fuel-0505171.html



其他新聞
2017/12/11 14:18:19 - 核二廠1號機預定於12月10日降載檢修非安全相關設備,原能會持續監控電廠運轉安全
2017/12/11 14:17:18 - 台中電廠新燃氣機組目標112年上路發電
2017/12/11 14:14:01 - UK fusion researchers welcome government support
2017/12/11 14:09:51 - US funds to support advanced nuclear technology development
2017/12/11 14:08:45 - Kepco named preferred bidder for UK's NuGen
2017/12/6 14:27:45 - 原能會謹訂於民國106年12月22日舉辦「核能電廠除役作業與管制規範」專題演講,歡迎報名參加。
2017/12/6 14:25:24 - Kazakhstan to cut uranium production
2017/12/6 14:23:45 - Russia readies for launch of Leningrad and Rostov units
2017/12/6 14:22:47 - Next Vogtle hearings to begin
2017/12/4 14:28:01 - 核三廠1號機預定於12月2日降載例行測試,原能會持續監控電廠運轉安全
2017/12/4 14:26:16 - 網傳買日本淘汰火力發電機組? 台電:不實謠言不排除對亂轉發者提告
2017/12/4 14:25:24 - Reactor vessel installed at Leningrad II-2
2017/12/4 14:24:04 - Decommissioning of Candu protoype moves forward
2017/12/4 14:08:43 - NEI files in support of New York ZEC programme
2017/11/29 14:24:10 - 106年11月27日藍莓相關食品抽樣之檢測結果
2017/11/29 14:21:06 - Governor Approves Restart Of Japan’s Ohi-3 And -4
2017/11/29 14:17:40 - UK, South Korea to extend nuclear cooperation
2017/11/29 14:13:04 - Russian and Brazilian firms to cooperate in nuclear power
2017/11/29 14:11:30 - EU's Energy Union becoming a reality, says Commission
2017/11/24 14:21:18 - 22日嘉義發生之有感地震及其餘震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全

 線上期刊目錄

 瀏覽人數
今天: 49
昨天: 78
本月: 833
總計: 506621

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw