國際核能現況 : Completed Barakah 1 awaits permission to load fuel
發表人 nicenter 於 2017/5/17 9:41:49 (23 人讀取)

05 May 2017

Initial construction has been completed at the UAE's first power reactor, Barakah 1. The operating company, Nawah Energy Company, must gain approval from national regulators before the final stage of loading fuel and bringing it into service.




The APR-1400 pressurized water reactor has been built by a South Korean consortium for its customer Emirates Nuclear Energy Corporation (Enec). Initial construction covering 95% of work is complete, including tests of safety systems, said Enec.


The remaining 5% of construction is the commissioning the reactor and final preparation of its 277 systems. This process starts with loading nuclear fuel into the reactor core, an operation which cannot take place until the Federal Authority for Nuclear Regulation (FANR) issues an operating licence to Nawah Energy Company, a joint venture of Enec and Kepco.





Barakah 1 (Image: Enec)

Enec today announced that Nawah continues to work with FANR towards obtaining this operating licence. In addition the UAE nuclear community has committed to completing two voluntary pre-operation peer reviews before moving forward: one at the industry level with the World Association of Nuclear Operators, another at the national level with the International Atomic Energy Agency. It was expected that the FANR review and licence would be completed last of these.


Enec applied for an operating licence in March 2015, but one year later created Nawah as a joint venture with Kepco to take that role instead. Nawah was boosted in July last year by an $880 million operating support services agreement where KHNP will supply 400 qualified staff until 2030. Yesterday Arabian Business reported that Nawah had finalised appointments to its board.


Acting Nawah CEO Mohammed Sahoo alSuwaidi said: "As we move towards unit 1 fuel load, we recognise the scale of both our responsibilities and of the challenges that lie ahead of us. Nawah's commitment to meeting the highest standards of safety and quality in nuclear operations is what drives the work of all our personnel, who are striving to ensure that we meet FANR's expectations."


Enec said the start-up schedule for Barakah 1 had been moved back in accordance with "a desire to achieve the highest possible nuclear quality and safety standards ... as well as lessons learned from [the commissioning of] Shin Kori 3 in South Korea, the reference plant for Barakah".


It added that the timeline includes an extension for the start-up of nuclear operations for unit 1, from 2017 to 2018, to ensure sufficient time for international assessments and adherence to nuclear industry safety standards, as well as "a reinforcement of operational proficiency for plant personnel". A spokesman for Enec told World Nuclear News it is "confident in the capacity to deliver" four APR-1400s by 2020, pending regulatory approval.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Completed-Barakah-1-awaits-permission-to-load-fuel-0505171.html



其他新聞
2017/6/21 10:42:30 - 國際原子能總署連續第11年宣告我國「所有核物料均用於核能和平用途」
2017/6/21 10:41:21 - Q&A: What Progress Has Germany Made Half Way Down The Phaseout Path?
2017/6/21 10:39:44 - Rosatom Agrees To Sell 49% Stake In Turkey’s Akkuyu Project
2017/6/21 10:38:53 - EC Clears Creation Of €24 Billion Public Fund For Handling Radwaste In Germany
2017/6/21 10:37:52 - Turkey’s Energy Market Regulator Grants Power Generation Licence To Akkuyu Project
2017/6/21 10:36:42 - Akkuyu project receives production licence
2017/6/16 9:40:00 - 原能會於今(15)日16時50分同意台電公司核三廠2號機併聯發電
2017/6/16 9:36:46 - [輿情回應]106年6月15日媒體報導「核二1號機重起後監測到溫度過高及輻射超標,有安全疑慮」之回應說明
2017/6/16 9:33:44 - Russia Expects ‘Active’ Participation Of Hungarian Industry In Paks 2 Project, Says Rosatom CEO
2017/6/16 9:32:54 - Why Pressure Is Growing For ‘Clear And Consistent’ Policy Support For Nuclear
2017/6/16 9:32:01 - Japanese District Court Denies Injunction Against Restart Of Genkai-3 and -4
2017/6/16 9:29:20 - Fuel loading under way at Fuqing 4
2017/6/16 9:27:59 - Steam generators shipped to second Belarusian unit
2017/6/14 9:44:46 - Toshiba Agrees On Payment Schedule For Vogtle Guarantee Obligations
2017/6/14 9:43:01 - Construction Of LEU Bank On Schedule, Shipments Expected In 2018, Says Amano
2017/6/14 9:42:31 - EBRD Announces Start Of Hot Trials At Ignalina Waste Facility
2017/6/14 9:40:00 - 核二廠1號機因主變壓器至開關場之鐵塔C相懸垂礙子處溫度偏高,預定今(12)日晚上解聯檢修
2017/6/14 9:36:20 - IAEA fuel 'bank' on course
2017/6/14 9:34:06 - Rolls-Royce elaborates on its SMR plans
2017/6/14 9:32:59 - Finnish EPR starts key pre-operational tests

 線上期刊目錄

 瀏覽人數
今天: 69
昨天: 69
本月: 1957
總計: 489268

30013 新竹市光復路二段101號 研發大樓二樓208室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw