國際核能現況 : Completed Barakah 1 awaits permission to load fuel
發表人 nicenter 於 2017/5/17 9:41:49 (14 人讀取)

05 May 2017

Initial construction has been completed at the UAE's first power reactor, Barakah 1. The operating company, Nawah Energy Company, must gain approval from national regulators before the final stage of loading fuel and bringing it into service.




The APR-1400 pressurized water reactor has been built by a South Korean consortium for its customer Emirates Nuclear Energy Corporation (Enec). Initial construction covering 95% of work is complete, including tests of safety systems, said Enec.


The remaining 5% of construction is the commissioning the reactor and final preparation of its 277 systems. This process starts with loading nuclear fuel into the reactor core, an operation which cannot take place until the Federal Authority for Nuclear Regulation (FANR) issues an operating licence to Nawah Energy Company, a joint venture of Enec and Kepco.





Barakah 1 (Image: Enec)

Enec today announced that Nawah continues to work with FANR towards obtaining this operating licence. In addition the UAE nuclear community has committed to completing two voluntary pre-operation peer reviews before moving forward: one at the industry level with the World Association of Nuclear Operators, another at the national level with the International Atomic Energy Agency. It was expected that the FANR review and licence would be completed last of these.


Enec applied for an operating licence in March 2015, but one year later created Nawah as a joint venture with Kepco to take that role instead. Nawah was boosted in July last year by an $880 million operating support services agreement where KHNP will supply 400 qualified staff until 2030. Yesterday Arabian Business reported that Nawah had finalised appointments to its board.


Acting Nawah CEO Mohammed Sahoo alSuwaidi said: "As we move towards unit 1 fuel load, we recognise the scale of both our responsibilities and of the challenges that lie ahead of us. Nawah's commitment to meeting the highest standards of safety and quality in nuclear operations is what drives the work of all our personnel, who are striving to ensure that we meet FANR's expectations."


Enec said the start-up schedule for Barakah 1 had been moved back in accordance with "a desire to achieve the highest possible nuclear quality and safety standards ... as well as lessons learned from [the commissioning of] Shin Kori 3 in South Korea, the reference plant for Barakah".


It added that the timeline includes an extension for the start-up of nuclear operations for unit 1, from 2017 to 2018, to ensure sufficient time for international assessments and adherence to nuclear industry safety standards, as well as "a reinforcement of operational proficiency for plant personnel". A spokesman for Enec told World Nuclear News it is "confident in the capacity to deliver" four APR-1400s by 2020, pending regulatory approval.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Completed-Barakah-1-awaits-permission-to-load-fuel-0505171.html



其他新聞
2017/5/24 10:12:08 - German Nuclear Forum Sounds Warning On Need For Long-Term Skills And Training
2017/5/24 10:10:43 - Switzerland Votes To Phase Out Nuclear Energy
2017/5/24 10:10:00 - 2017輻射源實體防護及保安管理訓練
2017/5/24 10:09:26 - Greenland’s Kvanefjeld Uranium Project Going Through Feasibility Study And EIA
2017/5/24 10:03:21 - 原能會審查同意台電公司核一廠2號機降載延時運轉案
2017/5/24 10:01:50 - 2017大型活動輻射事件應變訓練
2017/5/24 10:00:23 - 原能會同意核三廠2號機可開始依計畫執行受損組件更換作業
2017/5/24 9:59:38 - 原能會同意核二廠1號機護箱裝載池可啟用置放用過燃料
2017/5/24 9:57:41 - Swiss voters approve gradual nuclear phase out
2017/5/24 9:57:00 - Mixed progress for Ohio legislation
2017/5/24 9:56:06 - ANS urges support for continued nuclear operation
2017/5/24 9:55:25 - UK parties make scant reference to nuclear power
2017/5/24 9:53:58 - European consortium completes first Iter magnet
2017/5/19 9:54:55 - Argentina and China sign contract for two reactors
2017/5/19 9:53:39 - Indian units to boost domestic nuclear industry
2017/5/19 9:52:47 - China, Saudi Arabia begin HTGR feasibility study
2017/5/19 9:51:12 - Japan's Takahama-4 Resumes Commercial Operation After More Than A Year Offline
2017/5/19 9:50:00 - 106年5月17日「核二廠燃料廠房護箱裝載池設備修改案」完工後聯合視察
2017/5/19 9:50:00 - 「重現北火足跡」開展 老員工講古 再現電廠人文風華
2017/5/17 9:55:46 - Belgium’s Regulator Approves Tihange-1 Restart

 線上期刊目錄

 瀏覽人數
今天: 53
昨天: 64
本月: 1749
總計: 486837

30013 新竹市光復路二段101號 研發大樓二樓208室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw