國際核能現況 : Olkiluoto Repository Contracts Confirm Costs, But Commodity Prices ‘Remain A Risk’
發表人 nicenter 於 2017/4/21 9:53:42 (57 人讀取)

20 Apr (NucNet): Early construction contracts for Finland’s final deep geologic radioactive waste repository indicate costs meet expectations, but commodity price rises remain a risk over the long term, Sami Hautakangas, head of spent fuel and disposal services at Fortum, co-owner of repository developer Posiva, said.



According to Nuclear Energy Insider, Mr Hautakangas said Posiva’s construction phase procurement costs indicate the developer’s original cost estimate and schedule is “more or less in the right place”.


The cost of key materials such as copper and bentonite will remain a project risk due to the long timelines involved, Mr Hautakangas noted.


“There are risks, but at the moment it seems that when it comes to the construction itself, it seems to be nicely [within] budget and timetable,” he said.


In December 2016, Posiva began construction of the repository, the world's first permanent underground nuclear waste storage facility, on Olkiluoto island, Finland.


In the same month, Posiva said it has signed a €20m ($21m) contract for the excavation of the first tunnels for the Olkiluoto facility with YIT Construction.


Posiva, which is jointly-owned by nuclear utilities Fortum and TVO, is to carry out repository excavation work in a series of eight phases, which will allow investments to be broken down into portions over time and provide new site data to aid subsequent construction decisions, Nuclear Energy Insider said.


Finland's government awarded a construction permit for the project in November 2015 and a year later Finland’s Radiation and Nuclear Safety Authority (Stuk) authorised works to begin.


The facility is expected to be operational by 2024.


Full story online: http://bit.ly/2os6Gai



source: http://www.nucnet.org/all-the-news/2017/04/20/olkiluoto-repository-contracts-confirm-costs-but-commodity-prices-remain-a-risk



其他新聞
2017/8/16 9:20:00 - Major components installed at final Barakah unit
2017/8/10 17:48:32 - 106年8月8日媒體報導「核電廠隨時釀災 地方首長硬起來」之回應說明
2017/8/10 17:47:19 - 核四廠現為資產維護,從未裝填核子燃料,並無所謂核能發電之情事
2017/8/10 17:46:07 - NRC Staff Directed To Gather Information In Preparation For Yucca Restart
2017/8/10 17:45:21 - Nuclear Energy’s Long-Term Potential Remains High, Says IAEA
2017/8/10 17:44:38 - Special Report: Can India Maintain Its Ambitious Push For New Nuclear?
2017/8/10 17:43:44 - Start Of System Testing Approved At Chernobyl Spent Fuel Storage Facility
2017/8/10 17:42:25 - Nuclear capacity could more than double by 2050, says IAEA
2017/8/10 17:41:31 - India awards contract for fast reactor fuel cycle facility
2017/8/10 17:40:32 - Egypt, Russia 'complete Daba'a plant talks'
2017/8/4 17:31:01 - Japan Report Shows Benefits Of Nuclear Restarts
2017/8/4 17:30:14 - Spain’s Garoña To Shut Down Permanently After Ministry Blocks Restart
2017/8/4 17:29:02 - US Utilities To Abandon Summer-3 And -4 AP1000 Nuclear Project
2017/8/4 17:27:48 - Japanese Data On Marine Samples Near Fukushima Reliable, IAEA Concludes
2017/8/4 17:23:19 - Japan to benefit from reactor restarts, says IEEJ
2017/8/4 17:22:47 - Georgia Power expects late August decision on Vogtle
2017/8/4 17:22:01 - Kudankulam Phase III enters design stage
2017/8/4 17:21:32 - US nuclear construction project to be abandoned
2017/7/28 9:53:01 - Latvia Is Against Belarusian Nuclear Station Legislation, Says Foreign Minister
2017/7/28 9:52:01 - Target For Last Hanhikivi Design Documentation Is Spring 2018, Says Fennovoima

 線上期刊目錄

 瀏覽人數
今天: 5
昨天: 94
本月: 2956
總計: 496249

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw