國際核能現況 : Russia starts pre-commissioning Leningrad II unit 1
發表人 nicenter 於 2017/4/14 11:34:40 (35 人讀取)

Rosenergoatom has started cold and hot function testing at unit 1 of the Leningrad Phase II nuclear power plant under construction in western Russia. The procedure at the VVER-1200 unit will take 72 days to complete and will include more than 100 pre-operational tests of reactor equipment and systems, the Rosatom subsidiary said yesterday.


Leningrad II unit 1 (Image: Rosenergoatom)


The tests mark the beginning of full-scale commissioning of the unit and are intended to confirm its reliable and safe operation, the company said.


The Leningrad II plant's director, Vladimir Pereguda, said hydraulic tests will be performed to confirm the density and strength of the reactor installation.


Oleg Ivanov, chief engineer at the plant, said 'cold' was a relative term regarding cold testing, since the temperature of the chemically desalinated water to be pumped through the pipes will be about 120°C.


Hot testing will include checks on the four main circulation pumping units at 260°C over 100 hours.


The existing Leningrad plant site has four operating RMBK-1000 units, while Leningrad II will have four VVER-1200 units.


The general designer of Leningrad II is Atomproekt, while the general contractor is TITAN-2 JSC.


The Rosenergoatom statement did not give a target date for the start-up of unit 1.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Russia-starts-pre-commissioning-Leningrad-II-unit-1-13041702.html



其他新聞
2017/5/19 9:54:55 - Argentina and China sign contract for two reactors
2017/5/19 9:53:39 - Indian units to boost domestic nuclear industry
2017/5/19 9:52:47 - China, Saudi Arabia begin HTGR feasibility study
2017/5/19 9:51:12 - Japan's Takahama-4 Resumes Commercial Operation After More Than A Year Offline
2017/5/19 9:50:00 - 106年5月17日「核二廠燃料廠房護箱裝載池設備修改案」完工後聯合視察
2017/5/19 9:50:00 - 「重現北火足跡」開展 老員工講古 再現電廠人文風華
2017/5/17 9:55:46 - Belgium’s Regulator Approves Tihange-1 Restart
2017/5/17 9:54:33 - Energy Minister Says South Africa Will Sign New Intergovernmental Agreements
2017/5/17 9:53:36 - Tepco Recovery Plan Includes Search For Partners, Restart Of Kashiwazaki Kariwa
2017/5/17 9:52:10 - UK Needs Fallback Position On ‘Difficult’ Withdrawal From Euratom, Says Think-Tank
2017/5/17 9:50:35 - South African ministry accepts court ruling
2017/5/17 9:49:56 - Uganda seeks Chinese cooperation in nuclear energy
2017/5/17 9:47:58 - General Fusion, Microsoft team up on data analysis
2017/5/17 9:46:59 - First Iter plasma chamber tool ready for shipment
2017/5/17 9:45:40 - National Grid puts Moorside plans on hold
2017/5/17 9:44:41 - NuScale commissions second SMR simulator
2017/5/17 9:43:24 - Summer plant construction progress continues
2017/5/17 9:41:49 - Completed Barakah 1 awaits permission to load fuel
2017/5/17 9:40:00 - 原能會持續監控核一廠2號機降載運轉安全
2017/5/17 9:38:58 - 106年5月11日媒體報導「核一廠是否降載運轉coast down,經濟部及原能會說法不同」之回應說明

 線上期刊目錄

 瀏覽人數
今天: 1
昨天: 67
本月: 1633
總計: 486721

30013 新竹市光復路二段101號 研發大樓二樓208室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw