國際核能現況 : Russia starts pre-commissioning Leningrad II unit 1
發表人 nicenter 於 2017/4/14 11:34:40 (49 人讀取)

Rosenergoatom has started cold and hot function testing at unit 1 of the Leningrad Phase II nuclear power plant under construction in western Russia. The procedure at the VVER-1200 unit will take 72 days to complete and will include more than 100 pre-operational tests of reactor equipment and systems, the Rosatom subsidiary said yesterday.


Leningrad II unit 1 (Image: Rosenergoatom)


The tests mark the beginning of full-scale commissioning of the unit and are intended to confirm its reliable and safe operation, the company said.


The Leningrad II plant's director, Vladimir Pereguda, said hydraulic tests will be performed to confirm the density and strength of the reactor installation.


Oleg Ivanov, chief engineer at the plant, said 'cold' was a relative term regarding cold testing, since the temperature of the chemically desalinated water to be pumped through the pipes will be about 120°C.


Hot testing will include checks on the four main circulation pumping units at 260°C over 100 hours.


The existing Leningrad plant site has four operating RMBK-1000 units, while Leningrad II will have four VVER-1200 units.


The general designer of Leningrad II is Atomproekt, while the general contractor is TITAN-2 JSC.


The Rosenergoatom statement did not give a target date for the start-up of unit 1.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Russia-starts-pre-commissioning-Leningrad-II-unit-1-13041702.html



其他新聞
2017/6/21 10:42:30 - 國際原子能總署連續第11年宣告我國「所有核物料均用於核能和平用途」
2017/6/21 10:41:21 - Q&A: What Progress Has Germany Made Half Way Down The Phaseout Path?
2017/6/21 10:39:44 - Rosatom Agrees To Sell 49% Stake In Turkey’s Akkuyu Project
2017/6/21 10:38:53 - EC Clears Creation Of €24 Billion Public Fund For Handling Radwaste In Germany
2017/6/21 10:37:52 - Turkey’s Energy Market Regulator Grants Power Generation Licence To Akkuyu Project
2017/6/21 10:36:42 - Akkuyu project receives production licence
2017/6/16 9:40:00 - 原能會於今(15)日16時50分同意台電公司核三廠2號機併聯發電
2017/6/16 9:36:46 - [輿情回應]106年6月15日媒體報導「核二1號機重起後監測到溫度過高及輻射超標,有安全疑慮」之回應說明
2017/6/16 9:33:44 - Russia Expects ‘Active’ Participation Of Hungarian Industry In Paks 2 Project, Says Rosatom CEO
2017/6/16 9:32:54 - Why Pressure Is Growing For ‘Clear And Consistent’ Policy Support For Nuclear
2017/6/16 9:32:01 - Japanese District Court Denies Injunction Against Restart Of Genkai-3 and -4
2017/6/16 9:29:20 - Fuel loading under way at Fuqing 4
2017/6/16 9:27:59 - Steam generators shipped to second Belarusian unit
2017/6/14 9:44:46 - Toshiba Agrees On Payment Schedule For Vogtle Guarantee Obligations
2017/6/14 9:43:01 - Construction Of LEU Bank On Schedule, Shipments Expected In 2018, Says Amano
2017/6/14 9:42:31 - EBRD Announces Start Of Hot Trials At Ignalina Waste Facility
2017/6/14 9:40:00 - 核二廠1號機因主變壓器至開關場之鐵塔C相懸垂礙子處溫度偏高,預定今(12)日晚上解聯檢修
2017/6/14 9:36:20 - IAEA fuel 'bank' on course
2017/6/14 9:34:06 - Rolls-Royce elaborates on its SMR plans
2017/6/14 9:32:59 - Finnish EPR starts key pre-operational tests

 線上期刊目錄

 瀏覽人數
今天: 12
昨天: 133
本月: 2280
總計: 489591

30013 新竹市光復路二段101號 研發大樓二樓208室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw