Unit 4 of the Yangjiang nuclear power plant in China's Guangdong province has completed commissioning tests and now meets the conditions for entering commercial operation, China General Nuclear (CGN) announced yesterday.



The control room of Yangjiang unit 4 (Image: CGN)

The loading of fuel assemblies into the core of the 1080 MWe CPR-1000 pressurised water reactor was completed on 21 November and it achieved first criticality on 30 December. The unit was connected to the grid on 8 January.


Since then, a series of commissioning tests have been conducted at the unit, including a load test run and a test run lasting 168 hours. Although CGN must still obtain necessary permits and documentation, the unit can now be considered to be in commercial operation.


Six units are planned for the Yangjiang site. The first four units are CPR-1000s, with units 5 and 6 being ACPR-1000s. Unit 1 entered commercial operation in March 2015, with units 2 and 3 following in June 2015 and January 2016, respectively.


China's post-Fukushima hiatus in new reactor approvals meant the start of construction of unit 4 was delayed until November 2012.


First concrete for Yangjiang unit 5 was poured in September 2013, with that for unit 6 following three months later. CGN said the units are currently in the equipment installation phase, of which unit 5 marks the first application of a digital control system designed in China.


All six reactors at Yangjiang should be in operation by 2019.


The plant is owned and operated by Yangjiang Nuclear Power Company Limited (YJNPC), which is currently 46% owned by CGN Power, 30% by CGN Power subsidiary GNIC, 7% by CGN Power associate company CGN Industry Investment Fund Phase I, and 17% by Guangdong Yudean Group. In November 2016, Hong Kong-based power company CLP Holdings Limited won a bid to acquire a 17% stake in YJNPC from CGN. The transaction is expected to be completed by mid-2017.


CGN noted the start-up of Yangjiang 4 brings its total number of power reactors in operation to 20, with a combined installed capacity of 21.47 GWe.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Fourth-Yangjiang-unit-enters-commercial-operation-1603174.html



其他新聞
2017/9/22 15:25:45 - 原能會對低鈉鹽輻射問題之後續處理說明
2017/9/22 15:20:57 - Rosatom outlines future of nuclear in IAEA address
2017/9/22 15:18:31 - IAEA celebrates 20 years of waste safety convention
2017/9/20 14:49:32 - 106年核安第23號演習兵棋推演延期至9月26日舉行
2017/9/20 14:40:00 - 原能會樂意協助經濟部推動核廢料境外合作處置
2017/9/20 14:36:51 - Amano Calls For Budget Support As Demands On IAEA Grow
2017/9/20 14:28:43 - China’s Fuqing-4 Begins Commercial Operation
2017/9/20 14:23:18 - Komarov explains nuclear's role in energy mix
2017/9/20 14:19:44 - NuScale highlights non-power uses of its SMR
2017/9/20 14:15:16 - China plans further high temperature reactor innovation
2017/9/20 14:12:30 - European group calls for JCPOA support
2017/9/14 11:50:00 - 外媒報導韓國境內昨日測得放射性物質氙,原能會密切監控中
2017/9/14 11:43:58 - Swiss Regulator Approves Project Documents For Mühleberg Decommissioning
2017/9/14 11:34:18 - SMRs Can Deliver Electricity For Similar Cost To Offshore Wind, Says Rolls Royce
2017/9/14 11:12:07 - Rosatom head visits Iter, latest equipment batch sent
2017/9/14 11:04:06 - UK SMR consortium calls for government support
2017/9/14 10:56:02 - Steam generator installation underway at Karachi 2
2017/8/16 9:20:00 - Major components installed at final Barakah unit
2017/8/10 17:48:32 - 106年8月8日媒體報導「核電廠隨時釀災 地方首長硬起來」之回應說明
2017/8/10 17:47:19 - 核四廠現為資產維護,從未裝填核子燃料,並無所謂核能發電之情事

 線上期刊目錄

 瀏覽人數
今天: 80
昨天: 126
本月: 2517
總計: 499449

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw