國際核能現況 : Fourth Yangjiang unit enters commerci
發表人 nicenter 於 2017/3/17 10:56:49 (181 人讀取)

Unit 4 of the Yangjiang nuclear power plant in China's Guangdong province has completed commissioning tests and now meets the conditions for entering commercial operation, China General Nuclear (CGN) announced yesterday.



The control room of Yangjiang unit 4 (Image: CGN)

The loading of fuel assemblies into the core of the 1080 MWe CPR-1000 pressurised water reactor was completed on 21 November and it achieved first criticality on 30 December. The unit was connected to the grid on 8 January.


Since then, a series of commissioning tests have been conducted at the unit, including a load test run and a test run lasting 168 hours. Although CGN must still obtain necessary permits and documentation, the unit can now be considered to be in commercial operation.


Six units are planned for the Yangjiang site. The first four units are CPR-1000s, with units 5 and 6 being ACPR-1000s. Unit 1 entered commercial operation in March 2015, with units 2 and 3 following in June 2015 and January 2016, respectively.


China's post-Fukushima hiatus in new reactor approvals meant the start of construction of unit 4 was delayed until November 2012.


First concrete for Yangjiang unit 5 was poured in September 2013, with that for unit 6 following three months later. CGN said the units are currently in the equipment installation phase, of which unit 5 marks the first application of a digital control system designed in China.


All six reactors at Yangjiang should be in operation by 2019.


The plant is owned and operated by Yangjiang Nuclear Power Company Limited (YJNPC), which is currently 46% owned by CGN Power, 30% by CGN Power subsidiary GNIC, 7% by CGN Power associate company CGN Industry Investment Fund Phase I, and 17% by Guangdong Yudean Group. In November 2016, Hong Kong-based power company CLP Holdings Limited won a bid to acquire a 17% stake in YJNPC from CGN. The transaction is expected to be completed by mid-2017.


CGN noted the start-up of Yangjiang 4 brings its total number of power reactors in operation to 20, with a combined installed capacity of 21.47 GWe.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Fourth-Yangjiang-unit-enters-commercial-operation-1603174.html



其他新聞
2018/5/25 14:30:00 - 夏月電價6月1日起跑 台電邀全民節電
2018/5/25 14:15:30 - The German government approved a draft law on 23 May 2018 that paves the way for energy giants RWE and Vattenfall to receive hundreds of millions of euros in compensation for the country’s decision to phase out nuclear power.
2018/5/25 14:13:59 - Germany to compensate utilities for nuclear phaseout losses
2018/5/25 14:12:57 - Alliance launched to highlight nuclear on world stage
2018/5/23 14:20:00 - 綠能創新 全台首座離島大型微電網誕生澎湖七美
2018/5/23 14:18:31 - UK Nuclear Industry Welcomes PM’s Plan To Seek Euratom Associate Status
2018/5/23 14:16:55 - Japanese utility seeks to start up new reactor
2018/5/23 14:14:18 - Supreme Court to consider Virginia uranium ban
2018/5/18 15:10:00 - Belgium and China award simulator contracts
2018/5/18 15:09:56 - 有關韓國電力公社(KEPCO)旗下核燃料廠爆炸案,據悉目前無輻射外洩,本會持續查證中
2018/5/18 15:08:34 - Foratom Boss: EU Is In Danger Of Overlooking The Long-Term Benefits Of Nuclear
2018/5/18 15:06:47 - DR Congo research reactor requires improvement, says IAEA
2018/5/16 14:19:36 - 節電就可不蓋電廠? 台電:嚴重誤導 開源節流都重要
2018/5/16 14:17:48 - IAEA Mission Reviews Afghanistan’s Cancer Care Needs
2018/5/16 14:16:56 - NWMO broadens its international cooperation
2018/5/16 14:13:57 - Rising: Nuclear surge builds sustainable energy mix
2018/5/11 14:38:01 - 台電努力維持今年供電穩定 明年達成法定備用容量率目標
2018/5/11 14:35:49 - Perry Urges Saudi Arabia To Sign Nuclear Agreement With US
2018/5/11 14:34:50 - UK seeks to improve decommissioning policy
2018/5/11 14:32:27 - Nuclear for US grid resilience and climate

 線上期刊目錄

 瀏覽人數
今天: 7
昨天: 123
本月: 2696
總計: 522810

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw