logo
* 搜尋
* 核能資訊中心
* 中心簡介
* 日本福島核災專區
* 相關資訊
國際核能現況 : Iran starts building unit 2 of Bushehr plant
發表人 nicenter 於 2017/3/17 10:55:18 (169 人讀取)

Construction and installation work formally started yesterday at the site of unit 2 of the Bushehr nuclear power plant in Iran, Atomproekt, the reactor design subsidiary of Russian state nuclear corporation Rosatom, announced today. The first foundation stone for units 2 and 3 of the plant was laid in a ceremony held at the construction site in southern Iran in September last year.



Work starts on Bushehr unit 2 (Image: ASE)

AtomStroyExport (ASE) - another Rosatom subsidiary and the general contractor for the Bushehr project - and Nuclear Power Production and Development Company (NPPD) of Iran signed an EPC turnkey contract for construction of the units at Bushehr in November 2014. The two VVER-1000 units will be built with Generation III+ technology, including the latest safety features, and have a combined capacity of 2100 MWe, ASE has said. During the ceremony held on 10 September, the two sides signed a protocol on the start of work on the project to build units 2 and 3, known as Bushehr II.


Russian-built Bushehr 1 was connected to the national grid on 3 September 2011 and became the first nuclear power plant in the Middle East.


A ceremony to launch construction work yesterday was attended by representatives of the customer for the Bushehr II project, Iran's NPPD. They were project manager Mahmoud Jafari, Bushehr Nuclear Power plant director-general Hossein Ghaffari, the head of the Bushehr project Ali Reza Moradian, and members of parliament from Bushehr Province. ASE representatives included the director for the construction of the Bushehr plant, Suren Ambartsumyan.


Ambartsumyan said a "technologically competent" team of Russian and Iranian specialists had been formed for the first phase of the Bushehr project that had been able to "quickly navigate complex technical issues and contingencies", according to the Atomproekt statement. "The high potential of Iranian specialists will be actively involved in the construction of Bushehr II," he added. Ambartsumyan also said he was confident the new unit would be built to a high standard and according to schedule.


Bushehr units 2 and 3 are to be completed in 2024 and 2026, respectively.


Last September, ASE director Valery Limarenko said Rosatom is keen on the "wide use" of Iranian-made materials and would therefore invite Iranian manufacturing companies to compete to work on the project via contract tenders.


Rosatom has said previously that Bushehr II is expected to cost about $10 billion to build, and that the physical start-ups of unit 2 and unit 3 are planned for October 2024 and April 2026, respectively. Provisional acceptance of unit 2 by the Iranian customer is scheduled for August 2025 and that for unit 3 in February 2027.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Iran-starts-building-unit-2-of-Bushehr-15031701.html



其他新聞
2018/1/19 14:48:08 - 新北市將停發生煤許可 台電:超超臨界燃煤機組排放接近燃氣排放標準 可兼顧供電與環保
2018/1/19 14:46:08 - 今(17)日台北市北投區發生之有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/1/19 14:45:13 - Toshiba agrees sale of Westinghouse claims
2018/1/19 14:44:05 - Mining resumes at WIPP
2018/1/19 14:37:41 - EDF Energy expects 20% cost saving for Sizewell C
2018/1/17 14:15:15 - Lift nuclear ban, MCA tells Australian government
2018/1/17 14:09:56 - Steam generators installed at second Belarus unit
2018/1/17 14:08:03 - Regulator checks Rostov 4 ahead of start-up
2018/1/10 14:34:19 - 原能會已完成「核子事故常識及其防護」文宣,歡迎下載使用
2018/1/10 14:28:07 - Decommissioning progress for unique Canadian reactor
2018/1/10 14:25:02 - FERC starts new grid resilience proceeding
2018/1/10 14:20:38 - Flamanville EPR completes key pre-operational tests
2018/1/3 14:31:29 - 綠島邁向綠能島 台電首座地熱試驗探勘井開工
2018/1/3 14:30:00 - 全國環境輻射即時監測站107年起再增一站,計47站監測資訊即時網路公開
2018/1/3 14:20:12 - Taishan schedule factors in commissioning tests
2018/1/3 14:09:26 - New Rostov reactor starts up
2018/1/3 14:05:54 - Tianwan 3 starts supplying electricity to grid
2017/12/27 15:50:43 - 原能會今(26)日公開「國際核能安全公約中華民國國家報告」
2017/12/27 15:35:32 - 能源轉型 台電推動興達電廠燃氣機組更新計畫 2023年供電
2017/12/27 15:31:11 - Georgia Commission Gives Conditional Go-Ahead For Completion Of Vogtle-3 And -4

 線上期刊目錄

 瀏覽人數
今天: 76
昨天: 231
本月: 2648
總計: 511354

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw