國際核能現況 : China sets out nuclear plans for 2017
發表人 nicenter 於 2017/3/8 9:37:33 (124 人讀取)

China will complete construction of five nuclear power reactors and start construction of eight more in 2017, according to plans released by the country's National Energy Administration (NEA). Planning for a further eight reactors will also be progressed this year.

In its Energy Work Guidance Opinion for 2017, published on 10 February, the NEA said construction will be completed of the Sanmen 1 and Haiyang 1 AP1000 units, the Taishan 1 EPR and the Fuqing 4 and Yangjiang 4 CPR-1000 units. These, together with "other projects", will add some 6.41 GWe of nuclear generating capacity, it said.


The NEA's plan calls for the safe development of nuclear power. It said it will actively promote the construction of "qualified" nuclear power projects and there would be an orderly approval of coastal projects. There will be continued implementation of major nuclear power science and technology projects to promote the construction of the high-temperature gas-cooled demonstration project in Shidaowan in Shandong province. It also said it would "prudently" promote the preliminary work of small reactor demonstration projects and "actively explore the comprehensive utilisation of nuclear energy".


The Administration plans to start construction of eight units during this year, but it did not name them or state the type of reactors they will feature.


Preparatory work is also to be carried out this year on a further eight units. These include units 3 and 4 of Sanmen, Ningde units 5 and 6, and two units each at new plants at Zhangzhou in Fujian province and Huizhou in Guangdong province. Together with other projects, these will add 9.86 GWe of nuclear generating capacity.


The NEA also said China will promote the export of its nuclear power technology. It is to carry out follow-up cooperation work related to the planned construction of units at Karachi, Pakistan, as well as promote the implementation of the Hualong One reactor design in the UK.


The country will also strengthen its nuclear cooperation with other countries, including Russia and the USA. It will also seek "steady progress" on nuclear power project cooperation with Argentina, Romania and Turkey.


China, the NEA said, would be involved in the reorganisation of France's Areva. Last month, Areva said the capital of New Areva - the entity comprising Areva's nuclear fuel cycle activities ahead of the sale of its reactor business to EDF - "remains open" for an investment by CNNC.


China's operating nuclear generating capacity will double over the next five years under the country's recently-published 13th Five-Year Plan. Under that plan, over the next five years China aims to have all four Sanmen and Haiyang AP1000 units in operation by the end of this year. It also aims to develop Hualong One demonstration projects at Fuqing and Fangchenggang and begin construction on the CAP1400 demonstration project at Shidaowan. China will also start building a number of coastal nuclear power plants and carry out preliminary work for inland projects.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NP-China-sets-out-nuclear-plans-for-2017-0203174.html



其他新聞
2017/12/11 14:18:19 - 核二廠1號機預定於12月10日降載檢修非安全相關設備,原能會持續監控電廠運轉安全
2017/12/11 14:17:18 - 台中電廠新燃氣機組目標112年上路發電
2017/12/11 14:14:01 - UK fusion researchers welcome government support
2017/12/11 14:09:51 - US funds to support advanced nuclear technology development
2017/12/11 14:08:45 - Kepco named preferred bidder for UK's NuGen
2017/12/6 14:27:45 - 原能會謹訂於民國106年12月22日舉辦「核能電廠除役作業與管制規範」專題演講,歡迎報名參加。
2017/12/6 14:25:24 - Kazakhstan to cut uranium production
2017/12/6 14:23:45 - Russia readies for launch of Leningrad and Rostov units
2017/12/6 14:22:47 - Next Vogtle hearings to begin
2017/12/4 14:28:01 - 核三廠1號機預定於12月2日降載例行測試,原能會持續監控電廠運轉安全
2017/12/4 14:26:16 - 網傳買日本淘汰火力發電機組? 台電:不實謠言不排除對亂轉發者提告
2017/12/4 14:25:24 - Reactor vessel installed at Leningrad II-2
2017/12/4 14:24:04 - Decommissioning of Candu protoype moves forward
2017/12/4 14:08:43 - NEI files in support of New York ZEC programme
2017/11/29 14:24:10 - 106年11月27日藍莓相關食品抽樣之檢測結果
2017/11/29 14:21:06 - Governor Approves Restart Of Japan’s Ohi-3 And -4
2017/11/29 14:17:40 - UK, South Korea to extend nuclear cooperation
2017/11/29 14:13:04 - Russian and Brazilian firms to cooperate in nuclear power
2017/11/29 14:11:30 - EU's Energy Union becoming a reality, says Commission
2017/11/24 14:21:18 - 22日嘉義發生之有感地震及其餘震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全

 線上期刊目錄

 瀏覽人數
今天: 20
昨天: 60
本月: 864
總計: 506652

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw