國際核能現況 : Pakistan's Chashma 3 completes acceptance test
發表人 nicenter 於 2016/12/14 9:41:35 (187 人讀取)

Pakistan's fourth reactor - unit 3 of the Chashma nuclear power plant in Punjab province - has passed a preliminary acceptance test, supplier China National Nuclear Corporation (CNNC) has announced.


Chashma units 3 and 4 (Image: China Nuclear Engineering & Construction Corp)

Construction began on the Chinese-designed CNP-300 pressurised water reactor in March 2011. The unit achieved first criticality on 3 October and was connected to the grid on 15 October. The unit's output has since been gradually increased to 100%.


In a 7 December statement, CNNC said Chashma 3 completed a "100-hour reliability demonstration test" at 3.30am on 6 December, marking the end of acceptance tests for the unit. The reactor is expected to enter commercial operation before the end of this year.


Chashma 3 is one of two CNP-300 units being built at the site. Unit 4, which began construction nine months after unit 3, is currently undergoing commissioning and is expected to be connected to the grid during the first half of 2017.


The Chashma site - also referred to as Chasnupp - is already home to two Chinese-supplied 300 MWe PWRs: unit 1, in commercial operation since 2000, and unit 2, in commercial operation since 2011. Pakistan also has a 125 MWe Canadian-supplied pressurized heavy water reactor, Karachi unit 1, which has been in commercial operation since 1972.


Two 1161 MWe Chinese-supplied Hualong One plants are also planned at the Karachi site. A ground-breaking ceremony for Karachi 2 was held in August 2015, and the units are scheduled to enter service in 2021 and 2022.


Researched and written
by World Nuclear News



source: http://www.world-nuclear-news.org/NN-Pakistans-Chashma-3-completes-acceptance-test-0912165.html



其他新聞
2018/2/2 15:53:20 - US commissioners call for action on used fuel
2018/2/2 15:50:58 - Russian president to connect Rostov 4
2018/2/2 15:34:07 - Hot testing of Sanmen 2 AP1000 completed
2018/1/31 14:16:24 - 中油桃園煉油廠輻射源現場檢查結果說明
2018/1/31 14:14:15 - 台電取得國內首張衛福部食品放射性檢驗機構認證 與國際知名檢測機構SGS合作 跨足食品放射性檢驗
2018/1/31 14:11:42 - Westinghouse extends Ukrainian fuel supply to 2025
2018/1/31 14:10:15 - NJ files new legislation recognising nuclear benefits
2018/1/26 17:04:34 - 兼顧供電與環保 台電持續配合空污降載
2018/1/19 14:48:08 - 新北市將停發生煤許可 台電:超超臨界燃煤機組排放接近燃氣排放標準 可兼顧供電與環保
2018/1/19 14:46:08 - 今(17)日台北市北投區發生之有感地震,各核能電廠皆正常運作,原能會持續監控電廠運轉安全
2018/1/19 14:45:13 - Toshiba agrees sale of Westinghouse claims
2018/1/19 14:44:05 - Mining resumes at WIPP
2018/1/19 14:37:41 - EDF Energy expects 20% cost saving for Sizewell C
2018/1/17 14:15:15 - Lift nuclear ban, MCA tells Australian government
2018/1/17 14:09:56 - Steam generators installed at second Belarus unit
2018/1/17 14:08:03 - Regulator checks Rostov 4 ahead of start-up
2018/1/10 14:34:19 - 原能會已完成「核子事故常識及其防護」文宣,歡迎下載使用
2018/1/10 14:28:07 - Decommissioning progress for unique Canadian reactor
2018/1/10 14:25:02 - FERC starts new grid resilience proceeding
2018/1/10 14:20:38 - Flamanville EPR completes key pre-operational tests

 線上期刊目錄

 瀏覽人數
今天: 75
昨天: 47
本月: 1896
總計: 513896

30013 新竹市光復路二段101號 創新育成中心三樓309室 電話:(03)571-1808 傳真:(03)572-5461 Email: nicenter@nicenter.org.tw